To develop approximately 11 miles of non-motorized trail within the Echo Ridge Trail System.The new trails will consist of 6.5 miles of newly constructed single track trail and 4.4 miles of trail on existing non-system roads.
Location
Echo Ridge Recreation Trail
Project timeline
1
Scoping Start
10/28/2013
2
Decision
06/2014 (Estimated)
3
Implementation
09/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Echo Ridge Summer Trails - Non-Motorized Trail Development | Decision Signed Date: 06/14/2014 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Chelan Ranger District |
| Legal Land Description | T28N, R22E, Sections: 1,2,9,10,11,12,13,14 |