Improve the Washington State Patrol existing communications facility at the Tunk Mountain Communications Site by removing the existing generator fuel tank and replacing it with a new equipment shelter in the same location.
Location
The facility is located at the Tunk Mountain Communications Site on Tunk Mountain outside of .
Project timeline
1
Scoping Start
11/20/2012
2
Comment Period
05/12/2013
3
Decision
05/2013 (Estimated)
4
Implementation
06/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| WSP Tunk Mountain Communications Site | Decision Signed Date: 05/07/2013 Legal Notice Date: 05/12/2013 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Tonasket Ranger District |
| Legal Land Description | Section 8, Township 35 North, Range 29 East, W.M. |