Repair and upgrade utilities, upgrade kitchen,construct patio and restroom, install two towers and regrade the small alpine hill
Location
Leavenworth Ski Hill facility
Project timeline
1
Scoping Start
01/30/2014
2
Comment Period
04/14/2016
3
Decision
05/2016 (Estimated)
4
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Ski Hill Improvements EA | Decision Signed Date: 05/20/2016 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Wenatchee River Ranger District |
| Legal Land Description | T25N, R17E, Sec 36 |