Environmental Assessment Completed

Ski Hill Improvements EA

Okanogan-Wenatchee National Forest Chelan, Washington Wenatchee River Ranger District

Repair and upgrade utilities, upgrade kitchen,construct patio and restroom, install two towers and regrade the small alpine hill

Location

Leavenworth Ski Hill facility

Project timeline

1
Scoping Start
01/30/2014
2
Comment Period
04/14/2016
3
Decision
05/2016 (Estimated)
4
Implementation
06/2016 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFacility Improvements/Construction; Special Use Authorizations; Facility Maintenance
Ski Hill Improvements EADecision Signed Date: 05/20/2016
ForestsOkanogan-Wenatchee National Forest
DistrictsWenatchee River Ranger District
Legal Land DescriptionT25N, R17E, Sec 36
Facility managementRecreation managementSpecial use management