Reconstruct and construct approximately 2500 feet of trail, install a footlog (bridge) across Meadow Creek on the Lakeshore Trail #1247 to repair flash flood damage.
Location
Lakeshore Trail on the north shore of Lake Chelan.
Project timeline
1
Scoping Start
03/13/2014
2
Decision
04/2014 (Estimated)
3
Implementation
09/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Lakeshore Trail - Meadow Creek Reroute | Decision Signed Date: 04/16/2014 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Chelan Ranger District |
| Legal Land Description | T31N, R18E, Section 2 |