At worksite no.6 (NFS land) permit temporary use of 1/4 mi of existing FS road for access to Cle Elum River, placement of 1-5 ballasted snags in river, excavation at Domerie inlet to widen inlet to side channel, and restoration of disturbed shoreline
Location
Cle Elum River, below Cle Elum Dam
Project timeline
1
Scoping Start
12/13/2013
2
Decision
09/2014 (Estimated)
3
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3); 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Special Use Authorizations; Watershed Improvements |
| KCT Cle Elum River Restoration - Phase II Construction | Decision Signed Date: 09/08/2014 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Cle Elum Ranger District |
| Legal Land Description | Secs. 11, 13, and 14, T. 20 N., R. 14 E., W.M. |