Aquatic and terrestrial restoration including road management, hazardous fuels reduction, forest health, and timber stand improvement.
Location
The project is located immediately northwest of Blewett Pass, west of Hwy 97, approximately 16 miles south of Leavenworth, WA. It includes Scotty Creek, Shaser Creek, and the upper reaches of Peshastin Creek subwatersheds.
Project timeline
1
Scoping Start
10/2015 (Estimated)
2
Comment Period
11/2015 (Estimated)
3
Objection Period Start
01/2016 (Estimated)
4
Decision
03/2016 (Estimated)
5
Implementation
05/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Timber Sales (Green); Watershed Improvements |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Wenatchee River Ranger District |
| Legal Land Description | T21N, R17E; T21N, R18E; T22N, R17E; T22N, R18E. |