To permit the Navy the use of three roadside sites within the existing Military Operations Area, to place mobile vehicles with emitters to conduct training in order to maintain, train, and equip combat-ready military forces.
Location
Mt. Hull site is adjacent to FR 3525 at the helicopter landing. Peony Creek site is located near the dispersed camping site on FR 3010. Deep Creek site is located near FR 3120020 & 3120060 junction.
Project timeline
1
Scoping Start
10/17/2014
2
Decision
01/2018 (Estimated)
3
Implementation
05/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Tonasket Ranger District |
| Legal Land Description | Not Applicable |