The Project has been cancelled due to the project being on hold since 2014. Re-evaluation of the projects approach is being considered.
Location
Okanogan-Wenatchee National Forest, outside Wilderness
Project timeline
1
Scoping Start
12/22/2014
2
Comment Period
06/08/2016
3
Objection Period Start
04/2019 (Estimated)
4
Decision
09/2019 (Estimated)
5
Implementation
10/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Trail Management; Travel Management |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Okanogan-Wenatchee National Forest All Units |
| Legal Land Description | Not Applicable |