Excavate an area approximately 41'x50'for additional 12' x 26' storage area next to existing facility and construct retaining wall to match existing
Location
Round Mountain
Project timeline
1
Scoping Start
03/08/2017
2
Decision
05/2017 (Estimated)
3
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Round Mountain - LocalTel communications | Decision Signed Date: 05/30/2017 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Wenatchee River Ranger District |
| Legal Land Description | T26N, R16E, Sec. 2 |