Issue a special use permit for the replacement of 11 pole structures not having adequate access along the McKenzie-Beverly Transmission line that crosses NFS lands. Current poles need critical maintenance on cross arms or be replaced.
Location
Transmission line runs east from Nahahum Canyon to Stevens pass.
Project timeline
1
Scoping Start
07/10/2015
2
Decision
09/2015 (Estimated)
3
Implementation
10/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Chelan County Public Utility District (CCPUD) Pole Access and Maintenance CE | Decision Signed Date: 09/21/2015 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Wenatchee River Ranger District |
| Legal Land Description | T25N, R17E, Sections 1,2,12; T26N, R17E, Sections 7, 8, 27, 28 34; T26N, R16E, Sections 3,4,5,6; T26N, R15E, Sections 1, 2, 3,6, 8, 9. |