Issuing a special use permit to Washington State Department of Transportation for conducting preliminary exploratory fieldwork necessary for the design of a possible future bridge replacement.
Location
Along U.S. Highway 12 from Mileposts 165.38 to 166.14
Project timeline
1
Scoping Start
08/17/2016
2
Decision
07/2017 (Estimated)
3
Implementation
08/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Wildcat Bridge Exploratory Special Use Permit Issuance | Decision Signed Date: 07/14/2017 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Naches Ranger District |
| Legal Land Description | Sections 30 & 31, T.14N. R.14E. |