Project is to tear down an existing cabin and replace with new structure. Existing cabin is in disrepair. The new cabin would be within the same footprint.
Location
Wenatchee River Ranger District, Crescent Beach Recreation Residence cabin #3
Project timeline
1
Scoping Start
04/03/2018
2
Decision
04/2018 (Estimated)
3
Implementation
04/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Crescent Beach Recreation Residence Rebuild Project | Decision Signed Date: 04/04/2018 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Wenatchee River Ranger District |
| Legal Land Description | Not Applicable |