Project will replace a perched 48 inch culvert and install an open bottom, 3 sided concrete culvert under SR 207. The project will improve hydraulic connectivity and fish access to the floodplain that was cut-off by construction of SR207.
Location
Nason Creek RM4.6, on SR207, immediately south of powerlines
Project timeline
1
Scoping Start
03/12/2018
2
Decision
05/2018 (Estimated)
3
Implementation
05/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Nason Creek (N1) Side Channel Reconnection (AOP) Aquatic Organism Passage | Decision Signed Date: 05/14/2018 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Wenatchee River Ranger District |
| Legal Land Description | T26N R17E Section 9 |