Construct a new bridge across Prince Creek and 1400 feet of new non-motorized trail. The trail to the old collapsed bridge site will be obliterated.
Location
Township 31, Range 19, Section 32
Project timeline
1
Scoping Start
06/05/2019
2
Decision
07/2019 (Estimated)
3
Implementation
07/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Prince Creek Bridge Replacement | Decision Signed Date: 07/08/2019 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Chelan Ranger District |
| Legal Land Description | Not Applicable |