Project timeline
1
Scoping Start
05/28/2019
2
Decision
06/2019 (Estimated)
3
Implementation
06/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Natapoc FS Communication Site | Decision Signed Date: 06/11/2019 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Wenatchee River Ranger District |
| Legal Land Description | Not Applicable |