Replacement chair lift in the same alignment as the existing Chair 2. Chair 2 replacement lift would begin in the same location as existing Chair 2.
Location
Township 21N, Range 19E., W.M. section 26
Project timeline
1
Scoping Start
07/19/2019
2
Decision
04/2020 (Estimated)
3
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Mission Ridge Chair 2 replacement | Decision Signed Date: 04/15/2020 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Wenatchee River Ranger District |
| Legal Land Description | Not Applicable |