The purpose of this project is to implement a project approved in the Mission Ridge Master Plan EA to install a new chair lift within the existing special use permit and ski area boundary (ref. pg. 16, 1.2.3.3 Bowl Four Lift -now called Chair 5.
Location
Mission Ridge Ski Area
Project timeline
1
Scoping Start
03/06/2023
2
Decision
05/2023 (Estimated)
3
Implementation
06/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Wenatchee River Ranger District |
| Legal Land Description | Not Applicable |