Project timeline

1
Scoping Start
03/16/2012
2
Comment Period
05/31/2012
3
Decision
09/2012 (Estimated)
4
Implementation
09/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecies Habitat Improvements; Watershed Improvements
Bockette Creek Fish Passage ImprovementDecision Signed Date: 09/12/2012 Legal Notice Date: 09/12/2012
ForestsOlympic National Forest
DistrictsPacific Ranger District / Forks
Legal Land DescriptionT29 N, R12W, S 7
Wildlife, fish, rare plants