Green Diamond Resource Company has applied for a special use permit to use 3 stumps on the forest boundary as tailholds for their logging operations in the Satsop watershed. The logging operations will start April 1 and go through May 1.
Location
21N 6W Sec 11 (along E section line in SE ¼ of NE ¼ ) ON the Forest boundary
Project timeline
1
Scoping Start
03/20/2013
2
Comment Period
03/20/2013
3
Decision
03/2013 (Estimated)
4
Implementation
04/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Tailhold Permit | Decision Signed Date: 03/27/2013 |
| Forests | Olympic National Forest |
| Districts | Hood Canal Ranger District / Hoodsport |
| Legal Land Description | 21N 6W Sec 11 |