We will dig an 18-24" deep trench using a ditch witch, replace failed water lines throughout the compound, install 7 new water sub meters, and coordinate relocation of the compound's main water meter.
Location
Quinault Ranger Station Compound Facility
Project timeline
1
Scoping Start
09/05/2013
2
Decision
09/2013 (Estimated)
3
Implementation
10/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance |
| Quinault Admin Site Waterline Repair/Replacement | Decision Signed Date: 09/06/2013 |
| Forests | Olympic National Forest |
| Districts | Pacific Ranger District / Forks |
| Legal Land Description | 23 N / 9 W / 20 |