About four acres of young-growth conifers to the north of the currently developed area. The timber would be cut and removed through a small commercial timber sale. A short existing unclassified road would be developed to provide access from FSR2923.
Location
The pit is located off FSR2923070 and adjacent to 2923.
Project timeline
1
Scoping Start
04/01/2014
2
Decision
05/2014 (Estimated)
3
Implementation
07/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| Grindstone Pit Expansion Grindstone Pit Expansion Grindstone Rock Pit | Decision Signed Date: 05/09/2014 |
| Forests | Olympic National Forest |
| Districts | Pacific Ranger District / Quinault |
| Legal Land Description | T29N R11W, Sec 5 and 8 |