Treatment of about 25 miles of roads identified in the Dungeness Watershed Action Plan as impacting or at risk of impacting aquatic resources. Treatment may include road closures, road decommissioning, or road to trail conversions.
Location
Project area is located south of Sequim, WA, in the following watersheds: Headwaters Dungeness River, Upper Dungeness River, Middle Dungeness River, Lower Gray Wolf River, and McDonald Creek.
Project timeline
1
Scoping Start
04/01/2016
2
Comment Period
07/03/2018
3
Objection Period Start
05/24/2019
4
Decision
10/2019 (Estimated)
5
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Trail Management; Road Improvements/Construction; Watershed Improvements |
| Dungeness Watershed Roads Management Project | Decision Signed Date: 10/25/2019 |
| Forests | Olympic National Forest |
| Districts | Hood Canal Ranger District / Quilcene |
| Legal Land Description | T29N, R04W, Sec 19-23, 25-28, 32-36; T29N, R3W, Sec 32, 33; T28N, R3W, Sec 7, 18, 29, 30, 32; T28N, R4W, Sec 25, Willamette Meridian. |