The amendment of an existing Verizon Wireless communication site lease for a 11-foot extension to the existing 100-foot monopole to accommodate the installation of additional antennas at the North Point Communication Site.
Location
Approximately 12 miles NW of Forks Washington, along HWY 101.
Project timeline
1
Scoping Start
03/01/2021
2
Decision
05/2021 (Estimated)
3
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| North Point Communications Site Tower Height Extension and New Facility | Decision Signed Date: 05/24/2021 |
| Forests | Olympic National Forest |
| Districts | Pacific Ranger District / Forks |
| Legal Land Description | T30N R11W Sec 27 |