Previously known as Tracy Placer Mining Project (#9992). Prepare Supplemental EIS and environmental review of proposed Plan of Operations for placer mining less than 5 acres in the Sucker Creek watershed.
Location
South bank of Sucker Creek, about 11 miles southeast of Cave Junction, Oregon. Within Riparian Reserve and Late Successional Reserve.
Project timeline
1
NOI in Federal Register
07/12/2011
2
DEIS NOA in Federal Register
10/2015 (Estimated)
3
FEIS NOA in Federal Register
02/2016 (Estimated)
4
Objection Period Start
02/2016 (Estimated)
5
Decision
06/2016 (Estimated)
6
Implementation
07/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Rogue River-Siskiyou National Forest |
| Districts | Wild Rivers Ranger District |
| Legal Land Description | T40S, R06W, Section 19 |