Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 4/15/2026
Applegate Lake · Jackson, Oregon

Upgrades and maintenance on the water and wastewater systems at Hart-Tish Recreation Site adjacent to Applegate Lake.

Recreation managementFacility management
Scoping Start
11/07/2018
Decision
09/2022 (Estimated)
Implementation
03/2024 (Estimated)
Project documents
Jennifer Sanborn · jennifer.sanborn@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (22), 36 Cfr 220.6(E)(22)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Facility Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Wild Rivers Ranger District · updated 1/14/2026
About 11 miles south of Cave Junction, Oregon, within Del Norte County, California. · Del Norte, California

Place large wood, construct a 1500-foot side channel, and revegetate about 7 miles of stream to improve fish habitat and water quality.

Wildlife, fish, rare plantsVegetation management (other than forest products)Watershed management
Scoping Start
10/10/2014
Comment Period
08/14/2015
Objection Period Start
09/19/2015
Decision
11/2015 (Estimated)
Implementation
06/2016 (Estimated)
Project documents
Jamie Krezelok · jkrezelok@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityForest Vegetation Improvements; Species Habitat Improvements; Watershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT18N-R5E-Sec. 1, 2, 4, 12; T19N-R5E-Sec. 33-35. Humboldt Meridian.
Environmental Assessment · Powers Ranger District · updated 1/14/2026
The project is located in Curry and Coos Counties, Oregon, approximately 5 miles east of Port Orford, Oregon, on the Powers Ranger District. · Coos; Curry, Oregon

This project proposes to: improve or maintain the quality of unique forest habitats; accelerate late seral conditions; improve or restore aquatic and riparian habitats; promote quality sustainable recreational opportunities; and reduce fuels.

Land management planningRecreation managementWildlife, fish, rare plantsVegetation management (other than forest products)Fuels managementWatershed management
Scoping Start
06/2018 (Estimated)
Comment Period
10/2018 (Estimated)
Objection Period Start
01/2019 (Estimated)
Decision
04/2019 (Estimated)
Implementation
10/2019 (Estimated)
Project documents
Jessie Berner · jberner@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Watershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Wild Rivers Ranger District · updated 1/14/2026
In the vicinity of Onion Mountain, approximately 15 miles west of Grants Pass, Oregon. · Josephine, Oregon

Salvage trees over 12 inches DBH that were killed in the Onion Mountain Fire of September 2014 on approximately 120 acres.

Forest products
Scoping Start
06/08/2015
Decision
07/2015 (Estimated)
Implementation
09/2015 (Estimated)
Project documents
Wesley Crum · whcrum@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (13), 36 Cfr 220.6(E)(13)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTimber Sales (Salvage)
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionTownship 36 S, Range 8 W, Sections 2, 10, 11, and 15 Willamette Meridian
Decision Memo · Gold Beach Ranger District · updated 1/14/2026
Lower Rogue R (from Lobster Creek upriver to the pool below Blossom Bar Rapids) and Lower Illinois River (from confluence with Rogue River to mouth of Nancy Creek)- nearest town is Agnes OR · Curry, Oregon

Re-issuance of up to 63 special use permits (SUPs) to outfitter/guides providing tour boat (motorized jet boat), fishing (motorized and drift boat), kayaking, livery services and raft trips on Lower Rogue & Illinois, Lobster-Blossom B & Confl - Nancy

Recreation managementSpecial area managementSpecial use management
Scoping Start
01/11/2016
Decision
12/2016 (Estimated)
Implementation
12/2016 (Estimated)
Project documents
Barbara Cisneros · bcisneros@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (10); 32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Special Area Management
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Gold Beach Ranger District · updated 12/16/2025
About 8 miles ESE of Gold Beach, Oregon, in the area known as Red Flat within the Hunter Creek and North Fork Pistol River watersheds. Access is via Hunter Creek Road (NFS 3680) to NFS 1703 road. · Curry, Oregon

Red Flat Nickel Corp. plans to drill 35 3-inch diameter holes to a depth of 50 feet to obtain core samples of minerals adjacent to existing roads. No new roads would be constructed. About 1200 feet of road would be brushed.

Minerals and geology
Scoping Start
07/15/2013
Decision
12/2014 (Estimated)
Implementation
01/2015 (Estimated)
Project documents
NEPA / regulatory detail
Categorical Exclusion32.2 (8), 36 Cfr 220.6(E)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionTownship 37 South - Range 13 West - Sections 18, 19, 30, 31, and 32. Willamette Meridian.
Decision Memo · Wild Rivers Ranger District · updated 7/30/2025
Backpackers will backpack along the Illinois River starting at Briggs Creek Trailhead. They will continue along the trail for 2.5 miles and come back the same way. · Josephine, Oregon

Provide backpacking trips for youth in groups of 12 along the Illinois River. From Briggs Creek Trailhead groups will backpack downstream for 2.5 miles, camp along the river and beaches (2 days), and return to trailhead on same route (2 days).

Special use management
Scoping Start
03/2018 (Estimated)
Decision
01/1970 (Estimated)
Implementation
05/2018 (Estimated)
Project documents
Brian Long · bplong@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Decision Decided Date07/02/2026
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT. 37 S., R.9 W. Sec. 6 and T. 37S., R 10. W. Sec1 and 2 Willamette Meridian
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 7/29/2025
Wild Rivers Ranger District FSR 2402 Mile Post 1.2 and 2.3; Siskiyou Mountains Ranger District FSR 2040 Mile Post 6.7; High Cascades Ranger District FSR 6510-700 Mile Post 7.9. · Jackson; Josephine, Oregon

Repair four roads on Siskiyou Mountains, Wild Rivers, and High Cascades Ranger Districts.

Road management
Scoping Start
06/18/2024
Decision
02/2025 (Estimated)
Implementation
11/2025 (Estimated)
Project documents
Paul Podesta · paul.podesta@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (24), 36 Cfr 220.6(E)(24)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
2023 ERFO (Emergency Relief for Federally Owned Roads Program)Decision Signed Date: 02/26/2025
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 3/31/2025
Township 40 S, Range 1 East Section 21 · Jackson, Oregon

The rope tow will be installed on Mt. Ashland, along the northern edge of the Tempest Run. The rope tow will allow users of the Terrain Park quick access back to the top for increased use.

Special use management
Scoping Start
01/03/2025
Decision
03/2025 (Estimated)
Implementation
10/2025 (Estimated)
Project documents
Tabitha Olson · tabitha.olson@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Special Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
2023 ERFO Project Completed
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 2/27/2025
Gold Beach, Powers, Wild Rivers, Siskiyou Mountains and High Cascades Ranger Districts · Coos; Curry; Jackson; Josephine, Oregon

Repair 9 damaged road sites. The repair work proposed, ranges from surface road repair and replacement of culverts to re-alignmnet of roads.

Road management
Scoping Start
06/18/2024
Decision
08/2024 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
Paul Podesta · paul.podesta@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (24), 36 Cfr 220.6(E)(24)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance; Road Improvements/Construction
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 10/2/2024
Units near the Winchuck River, Chetco River, or Rogue River. · Curry, Oregon

101 acres of sudden oak death treatment (hack and squirt, core Area treatment, outer boundary treatment) on the Gold Beach Ranger District.

Vegetation management (other than forest products)
Scoping Start
05/13/2024
Decision
10/2024 (Estimated)
Implementation
10/2024 (Estimated)
Project documents
Charles Grell · charles.grell@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.3 (5)
Special AuthorityHfra Title Vi: Insect And Disease Projects
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
Sudden Oak Death Treatment 2024 - "SOD 2024_GBRD_CE_DM_FINAL.pdf"Decision Signed Date: 10/02/2024
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · High Cascades Ranger District · updated 9/10/2024
T. 37S, R. 04E, Section 8. The site is located approximately 16 air-miles northwest of the city of Butte Falls, Jackson County, Oregon. · Jackson, Oregon

US Cellular requests to remove their property from the multi-user Robinson Butte Communication Site. The on-site transformer that services PacifiCorp will continue to serve the other facility there.

Special use managementFacility management
Scoping Start
07/17/2024
Decision
09/2024 (Estimated)
Implementation
09/2024 (Estimated)
Project documents
Brian White · brian.white2@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (21), 36 Cfr 220.6(E)(21)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Special Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · High Cascades Ranger District · updated 7/22/2024
The site is located on High Cascades Ranger District, approximately 16 air-miles northwest of the city of Butte Falls, Jackson County, Oregon. · Jackson, Oregon

This project is to upgrade the existing tower and other equipment to build out the radio infrastructure for the public safety agencies in Jackson County. The communication facility will enable emergency services to support public safety.

Facility managementSpecial use management
Scoping Start
04/25/2024
Decision
07/2024 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
Brian White · brian.white2@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Special Use Authorizations; Facility Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionSec. 16, T34S, R4E, WM
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 3/20/2024
The greenhouse will be constructed west of current greenhouses. · Jackson, Oregon

J. Herbert Stone Nursery plans to construct a 156foot long 30 foot wide greenhouse, which would provide 23,400 square feet of added capacity. This will help with reforestation efforts.

Vegetation management (other than forest products)Facility management
Scoping Start
08/31/2022
Decision
03/2024 (Estimated)
Implementation
07/2026 (Estimated)
Project documents
Jason McNeal · jason.mcneal@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (21), 36 Cfr 220.6(E)(21)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
J. Herbert Stone Nursery Greenhouse Project DMDecision Signed Date: 03/06/2024
ForestsRogue River-Siskiyou National Forest
DistrictsJ. Herbert Stone Nursery
Legal Land DescriptionNot Applicable
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 10/5/2023
Wild Rivers Ranger District. The project area runs south of the community of Takilma, west of Sucker Creek, and east of Oregon State Highway 199. · Josephine; Del Norte; Siskiyou, California; Oregon

Restore safe public and employee access on arterial roads that were affected by the Slater Fire. Publicly accessible roads impacted by the Slater Fire are now exposed to an elevated risk from danger trees along affected roadways

Vegetation management (other than forest products)Watershed managementRoad managementFuels management
Scoping Start
07/12/2022
Comment Period
04/07/2023
Objection Period Start
06/14/2023
Decision
10/2023 (Estimated)
Implementation
10/2023 (Estimated)
Project documents
Scott Blower · scott.blower@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage)
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 8/4/2023
East of Lobster Creek · Curry, Oregon

37 acres of sudden oak death treatment (hack and squirt only) on the Gold Beach Ranger District

Vegetation management (other than forest products)
Scoping Start
06/12/2023
Decision
08/2023 (Estimated)
Implementation
09/2023 (Estimated)
Project documents
Charles Grell · charles.grell@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.3 (5)
Special AuthorityHfra Title Vi: Insect And Disease Projects
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Siskiyou Mountains Ranger District · updated 2/24/2023
Mount Ashland near the Mount Ashland Ski Area, east of the ski lodge on U.S. Forest Service-administered land. The site is located approximately 8 air-miles south of the city of Ashland. · Jackson, Oregon

The Forest Service received a proposal from Day Wireless to expand an existing tele-communications site on Mount Ashland to increase communication services including essential emergency communications.

Special use management
Scoping Start
09/07/2022
Decision
02/2023 (Estimated)
Implementation
02/2023 (Estimated)
Project documents
Gary Einck · gary.einck@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionTownship 40 South, Range 1 East, northeast corner of Section 21 Willamette Meridian, Oregon
Cathill Thin Completed
Decision Memo · High Cascades Ranger District · updated 2/22/2023
The project includes the following sub-watersheds Upper South Fork Big Butte Creek and Middle Fork Big Butte Creek. Located 11 miles east of the city of Butte Fall, Jackson County, Oregon. · Jackson, Oregon

This project will improve forest health on approximately 400 acres by thinning overstocked trees, reducing ladder fuels, performing prescribed fire and removing off site pine.

Fuels managementForest productsVegetation management (other than forest products)Wildlife, fish, rare plants
Scoping Start
01/06/2022
Decision
02/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
David Palmer · david.palmer@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (25), 36 Cfr 220.6(E)(25)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green)
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT. 34S R. 04E Sections 03, 04, 34; T. 35S R. 0E Sections 09, 10, 15
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 2/13/2023
The Project is located approximately 13.5 miles northeast of the town of Prospect along Highway 62 east of Union Creek approaching Crater Lake National Park (Mile Post 63). · Jackson, Oregon

The proposed action is to expand the existing paved trailhead parking at Thousand Springs Sno-Park by 0.38 acres to accommodate current and anticipated future use levels. Currently there are safety issues as overflow parking occurs on Highway 62.

Recreation management
Scoping Start
02/13/2018
Decision
02/2023 (Estimated)
Implementation
09/2023 (Estimated)
Project documents
Brian White · brian.white2@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (22), 36 Cfr 220.6(E)(22)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Facility Improvements/Construction; Trail Management
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionTownship 30 S, Range 4 E, Section 34
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 1/25/2023
Construction on less than 2 miles on the sixes road · Coos, Oregon

This partial road construction and subsequent 5-year road use permit would authorize the Roseburg Forest Products company to partially reconstruct, access, and maintain the 5201 and 5201-080 NFS roads.

Special area managementLand ownership managementForest products
Scoping Start
12/01/2021
Decision
07/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
Donald Kay · donald.kay@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (24), 36 Cfr 220.6(E)(24)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityHarzardous Waste Compliance Actions; Special Use Authorizations; Road Improvements/Construction
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionSixes- O80 road
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 10/27/2022
Various locations in tanoak stands of the Gold Beach Ranger District - general landmarks are along the following rivers - Pistol, Chetco, and Winchuck · Coos; Curry, Oregon

Rapid treatments of infected tanoak are needed to control immediate impacts and mitigate harm to important natural resources, including critical habit for Endangered Species Act-listed species.

Vegetation management (other than forest products)
Scoping Start
05/02/2022
Decision
08/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
Wade McMaster · wade.mcmaster@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (14), 36 Cfr 220.6(E)(14)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
2022 Sudden Oak Death TreatmentDecision Signed Date: 08/29/2022
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionT38S R13W,Sec8; T39S R12W, Sec 30, 31, 32; and T41S R12W, Sec 5 and 9.
Environmental Impact Statement · Rogue River-Siskiyou National Forest All Units · updated 9/7/2022
Upper Bear Creek; Late Successional Reserve/Restricted Watershed · Jackson, Oregon

Landscape fuels reduction to lower chance of large scale wildfire within Ashland Municipal Watershed

Fuels management
NOI in Federal Register
02/25/2004
DEIS NOA in Federal Register
06/24/2005
FEIS NOA in Federal Register
09/19/2008
Objection Period Start
09/19/2008
Decision
10/2008 (Estimated)
Implementation
06/2009 (Estimated)
Project documents
Donna Mickley · dmickley@fs.fed.us
NEPA / regulatory detail
Special AuthorityHfra Title I: Wildland-Urban Interface; Hfra Title I: Municipal Watersheds
Notice and Comment Regulation218
Project ActivityFuel Treatments (Non-Activity Fuels)
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT 39 S, R 1 E & R 1 W; T 40 S, R 1 E & R 1 W
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 8/29/2022
SOD infestations in multiple units on the Gold Beach Ranger District · Coos; Curry, Oregon

Rapid treatments of infected tanoak are needed to control immediate impacts and mitigate harm to important natural resources, including critical habit for Endangered Species Act-listed species.

Vegetation management (other than forest products)
Scoping Start
02/15/2021
Decision
08/2021 (Estimated)
Implementation
08/2021 (Estimated)
Project documents
Wade McMaster · wade.mcmaster@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (14), 36 Cfr 220.6(E)(14)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Environmental Impact Statement · High Cascades Ranger District · updated 8/16/2022
This area is located north of the town of Prospect, east of the Rogue-Umpqua Divide Wilderness, and south of Rabbit Ears. · Douglas; Jackson, Oregon

The Stella project's objectives are to restore and reestablish forest structure and pattern, vegetation composition, and diversity, and riparian communities to conditions that are more resilient to natural disturbances.

Vegetation management (other than forest products)Fuels managementRoad managementRecreation managementWatershed managementForest productsWildlife, fish, rare plants
NOI in Federal Register
05/12/2018
DEIS NOA in Federal Register
11/27/2020
FEIS NOA in Federal Register
12/17/2021
Objection Period Start
12/17/2021
Decision
08/2022 (Estimated)
Implementation
10/2022 (Estimated)
Project documents
Elizabeth Bly · elizabeth.bly@usda.gov
NEPA / regulatory detail
Special AuthorityStewardship Contract, Consolidated Appropriations Resolution Of 2003
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Developed Site Management; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Dispersed Recreation Mgmt.; Species Habitat Improvements; Trail Management; Special Products Sales; Species Population Enhancements; Rangeland Vegetation Improvements; Scenery Management; Travel Management; Timber Sales (Green); Watershed Improvements
Stella Restoration Project Final ROD for RRSNFDecision Signed Date: 08/15/2022
Stella Restoration Project Final ROD for UNFDecision Signed Date: 08/15/2022
ForestsRogue River-Siskiyou National Forest; Umpqua National Forest
DistrictsHigh Cascades Ranger District; Tiller Ranger District
Legal Land DescriptionNorth of the town of Prospect eat of the Rogue-Umpqua Divide Wilderness and South of Rabbit Ears.
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 8/10/2022
The proposed lift will be installed in the learning center, which is on the East side of the Mt. Ashland ski lodge on Mt. Ashland. · Jackson, Oregon

Mt. Ashland will replace rope tow (existing lift) with a 150' long Sunkid "Magic Carpet" conveyor style surface lift.

Special use managementRecreation management
Scoping Start
07/19/2022
Decision
08/2022 (Estimated)
Implementation
10/2022 (Estimated)
Project documents
Erik Taylor · erik.t.taylor@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 8/10/2022
South Ford Coquille River, FSR 5520 · Curry, Oregon

Remove POC along FSR 5520 on either side of the road for 10 miles.

Vegetation management (other than forest products)Road management
Scoping Start
11/09/2018
Decision
01/2019 (Estimated)
Implementation
01/2019 (Estimated)
Project documents
Peggy Sattler · psattler@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements; Road Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · High Cascades Ranger District · updated 7/20/2022
Fish lake is a reservoir at the headwaters of the North Fork of Little Butte Creek, near the Cascade crest just south of Highway 140. · Jackson, Oregon

The intent of this project is to improve the safety of and extend the season for launching trailered boats into Fish Lake. By expanding the current boat ramp it will make the lake accessible during low water years. The ramp can be paved or rocked.

Recreation management
Scoping Start
04/26/2018
Decision
09/2021 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
Steven Brazier · sbrazier@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT36S R4E sec 35
Environmental Impact Statement · Umpqua National Forest All Units · updated 5/5/2022
Umpqua NF, Rogue River NF, and Winema NF. · Douglas; Jackson; Klamath, Oregon

The Forest Service is proposing to amend the Land and Resource Management Plans (LRMP) for the Umpqua, Rogue River, and Winema National Forests for the proposed Pacific Connector Gas Pipeline.

Land management planning
NOI in Federal Register
06/15/2017
DEIS NOA in Federal Register
04/05/2019
FEIS NOA in Federal Register
11/22/2019
Objection Period Start
11/22/2019
Decision
01/2022 (Estimated)
Implementation
04/2022 (Estimated)
Project documents
David Krantz · dkrantz@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation219 (2012)
Project ActivityPlan Amendment
ForestsFremont-Winema National Forest; Rogue River-Siskiyou National Forest; Umpqua National Forest
DistrictsKlamath Ranger District; High Cascades Ranger District; Tiller Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 4/19/2022
repairing several roads across the Forest in most Districts · Coos; Curry; Douglas; Jackson, Oregon

Proposed action is to repair the multiple sites within the current road prism to restore traffic to the roadway, utilizing support from Emergency Repair of Federally Owned Roads(ERFO).

Road management
Scoping Start
09/29/2021
Decision
04/2022 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
Paul Podesta · paul.podesta@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District; Gold Beach Ranger District; Powers Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 2/3/2022
Iron Mountain · Coos, Oregon

Site testing and replacement of the Rohn 45G guided tower currently located on Iron Mountain with a new three-legged freestanding tower.

Special use management
Scoping Start
11/01/2021
Decision
02/2022 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Special Use Authorizations; Facility Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionTownship 33S Range 12W Section 27
Upper Briggs Creek Completed
Environmental Assessment · Wild Rivers Ranger District · updated 1/7/2022
Upper Briggs Creek watershed, about 15 miles west of Grants Pass, OR. · Josephine, Oregon

Thinning and prescribed burning to promote vegetation diversity, preserve legacy pines and oaks, restore meadow habitat, and provide fire resiliency; decommission or storage of excess roads; fish passage improvement. Approx. 3500 acres affected.

Watershed managementFuels managementWildlife, fish, rare plantsVegetation management (other than forest products)
Scoping Start
05/20/2016
Comment Period
05/02/2018
Objection Period Start
04/18/2019
Decision
08/2019 (Estimated)
Implementation
10/2019 (Estimated)
Project documents
Scott Blower · scott.blower@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green); Watershed Improvements
Final Decision for the Upper Briggs Landscape Restoration ProjectDecision Signed Date: 08/01/2019
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 1/6/2022
The 52,000 acre sixth field watershed is located in the Applegate Valley to the south of Ruch, Oregon. · Jackson, Oregon

Restore biological, physical, and chemical processes and functions to ensure the long-term ecological sustainability of the public lands in the Upper Applegate Watershed. This project is jointly proposed between BLM and FS.

Wildlife, fish, rare plantsRecreation managementVegetation management (other than forest products)Fuels managementWatershed management
Scoping Start
08/02/2017
Comment Period
11/22/2018
Objection Period Start
09/25/2019
Decision
08/2020 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
Jennifer Sanborn · jsanborn@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityForest Vegetation Improvements; Dispersed Recreation Mgmt.; Species Habitat Improvements; Trail Management; Travel Management; Watershed Improvements
Final Decision for the Upper Applegate Watershed Restoration ProjectDecision Signed Date: 08/13/2020
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 12/8/2021
Area south of the community of Takilma, west of Sucker Creek, and east of Oregon State Highway 199. · Josephine; Del Norte; Siskiyou, California; Oregon

Repair and maintenance of heavily used roads including danger tree removal over approx. 146 miles. Post-fire rehab activities on 4194 roadside acres impacted by high-intensity fire with repair of roads and trails, and replanting shrubs and trees.

Fuels managementForest productsRoad managementVegetation management (other than forest products)Watershed management
Scoping Start
01/04/2021
Decision
04/2021 (Estimated)
Implementation
04/2021 (Estimated)
Project documents
Scott Blower · sblower@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (11), 36 Cfr 220.6(E)(11)
Special AuthorityNot Applicable / Other; National Fire Plan - Healthy Forests Initiative Ce
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Trail Management; Road Maintenance; Timber Sales (Salvage); Watershed Improvements
Slater Fire Safe Re-entry Project DMDecision Signed Date: 04/09/2021
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Gold Beach Ranger District · updated 11/16/2021
North Bank Chetco River Road, approximately 10 miles upstream from mouth. · Curry, Oregon

Repair of North Bank Chetco River bridge superstructure and concrete pier

Road management
Scoping Start
05/25/2017
Decision
10/2017 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
David Scovell · dscovell@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Decision Decided Date10/20/2017
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 11/15/2021
Minnow Creek · Josephine, Oregon

The proposed trail would connect the lower portion of the Minnow Creek Trail with the Burnt Timber trail, creating a loop for hikers, trail runners, and mountain bikers. This area has been heavily impacted by fire.

Recreation management
Scoping Start
11/07/2018
Decision
01/2019 (Estimated)
Implementation
01/2019 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 11/12/2021
Robinson Butte · Jackson, Oregon

proposal to replace the existing 80' self-support tower at Robinson Butte with a 150' self-support tower; project will include a shared shelter and generator to minimize impact, provide improved coverage and accommodate multiple wireless carriers

Special use management
Scoping Start
01/09/2020
Decision
08/2020 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (10)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityLand Use Adjustments
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionT37SR4ESection8 W.M.
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 7/13/2021
Mt Ashland Ski Area parking lot · Jackson, Oregon

Adding natural challenge features to the Upper Bull Gap Trail for approximately 1 mile. The trail begins at the Mt Ashland ski area parking lot, and ends at the junction of forest road 2080.

Recreation management
Scoping Start
04/13/2021
Decision
07/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
James Courtright · james.courtright@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 6/4/2021
Special use 0.2 mi, located approximately 7.1 miles along the 3300-090 and 3300-100 roads (Kimball Hill Road). · Curry, Oregon

Using and maintaining an existing non-system road on NFS lands. SouthPort Timber Co. proposes to open, use and maintain 0.2 miles (1,056 feet) of existing road to access their private property. 20-term private road special use permit is recommended.

Special area managementLand ownership management
Scoping Start
06/04/2019
Decision
06/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityHarzardous Waste Compliance Actions; Special Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionSections 19 & 20, T36S, R13, WM.
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 4/21/2021
Forest wide habitat enhancement project. Huckleberry restoration will take place in the Jackson Creek Watershed HUC10-1710030202 & Headwaters Rogue River Watershed HUC10-1710030701). · Curry; Jackson; Josephine; Siskiyou, California; Oregon

The forest wide sensitive plant habitat enhancement project encompasses 8 plant species located at 201 sub-populations totaling 634 acres.

Wildlife, fish, rare plantsVegetation management (other than forest products)
Scoping Start
04/26/2018
Decision
04/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
Stuart Osbrack · sosbrack@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements; Species Habitat Improvements; Species Population Enhancements
Forest Wide Forest Wide Sensitive Plant Habitat Enhancement DMDecision Signed Date: 04/20/2021
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 4/13/2021
Quosatana Creek · Curry, Oregon

SouthPort Timber Co. proposes to open, use and maintain approximately 0.2 miles (1,056 feet) of existing, non-system road to access their private property. No other access exists and this road was most likely used in the past.

Special use management
Scoping Start
11/14/2018
Decision
03/2021 (Estimated)
Implementation
05/2021 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionTownship 36S Range 13W Section 20
Decision Memo · Gold Beach Ranger District · updated 3/16/2021
Boulder Creek culver is located approximately 20 miles east of Brookings off of FSR 1909, near Devil's Backbone. · Curry, Oregon

The proposed action is to remove the 5 foot culvert, and all of the road fill within the floodplain of Boulder Creek and its tributary.

Watershed management
Scoping Start
04/26/2018
Decision
08/2018 (Estimated)
Implementation
08/2018 (Estimated)
Project documents
Lizeth Ochoa · lizethochoa@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
Boulder Creek Culvert Removal Decision MemoDecision Signed Date: 08/02/2018
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionT39S R11W Sec. 7
Environmental Assessment · Powers Ranger District · updated 1/6/2021
Sixes River and South Fork Sixes River watersheds approximately 15 miles east of Port Orford, Oregon. · Curry, Oregon

Construct about 330 feet of new road on Forest Service lands from the end of Forest Service Road 5201-200 to the private parcel in T32S, R13W, Section 16. Applicant requests permission to use and maintain the road for perpetual timber management.

Road managementSpecial use management
Scoping Start
11/22/2011
Comment Period
11/10/2014
07/28/2016
Objection Period Start
06/03/2016
Decision
07/2016 (Estimated)
Implementation
09/2016 (Estimated)
Project documents
Donald Kay · dkay@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Improvements/Construction
Mount Avery Spur Road Special Use Permit RequestDecision Signed Date: 07/28/2016
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionT32S, R13W, Section 22
Environmental Impact Statement · Gold Beach Ranger District · updated 12/29/2020
The project is located in Curry and Josephine County, Oregon, approximately 30 miles northeast of Gold Beach, Oregon, on the Gold Beach and Wild Rivers Ranger District. · Curry, Oregon

Improve or maintain the quality of unique forest habitats, accelerate late seral conditions, improve or restore aquatic and riparian habitat, and promote quality sustainable recreational opportunities; project-specific plan amendment proposed.

Land management planningFuels managementWatershed managementWildlife, fish, rare plantsVegetation management (other than forest products)Road managementRecreation management
NOI in Federal Register
06/14/2016
DEIS NOA in Federal Register
05/25/2019
FEIS NOA in Federal Register
07/14/2020
Objection Period Start
07/15/2020
Decision
12/2020 (Estimated)
Implementation
01/2021 (Estimated)
Project documents
Michelle Calvert · Michelle.Calvert@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Dispersed Recreation Mgmt.; Species Habitat Improvements; Plan Amendment; Trail Management; Road Maintenance; Timber Sales (Green); Watershed Improvements
Shasta Agness Landscape Restoration Project Final Record of DecisionDecision Signed Date: 12/28/2020
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 11/27/2020
across the Gold Beach Ranger District, based on project criteria · Coos; Curry; Josephine, Oregon

Authorizes treatment of sudden oak death for vegetation infected by the non-native pathogen, Phytophthora ramorum. Treatment units that meet the project criteria may occur throughout the GBRD within several land use allocations.

Vegetation management (other than forest products)
Scoping Start
05/29/2020
Decision
11/2020 (Estimated)
Implementation
11/2020 (Estimated)
Project documents
Charles Grell · charles.grell@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (14), 36 Cfr 220.6(E)(14)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Bowen WUI Project Cancelled
Decision Memo · High Cascades Ranger District · updated 9/21/2020
Located in the Big Butte Springs Watershed, about 5 miles east of Butte Falls, Oregon. · Jackson, Oregon

The intent of this project is to reduce fuels, and increase resiliency of the stands through commercial, and mechanical thinning. Activity fuels may be either piled, or loped and scattered.

Fuels management
Scoping Start
05/30/2018
Decision
12/2020 (Estimated)
Implementation
12/2020 (Estimated)
Project documents
Anne Trapanese · atrapanese@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (12), 36 Cfr 220.6(E)(12)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels)
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT35S, R3E, Sec 29 and 30 FS Lands west of Willow Lake
Decision Memo · High Cascades Ranger District · updated 9/21/2020
Located near Fish Lake at the headwaters of the North Fork of Little Butte Creek. The cabin location is Hoyt, Lot 1, Tract H Block B. · Jackson, Oregon

Authorize the installation of a buried cistern and waterline at a recreation residence (Hoyt, Lot1, Tract H, Block B) to provide water for the residence. The system would be buried behind the already permitted outbuilding.

Facility management
Scoping Start
04/26/2018
Decision
07/2020 (Estimated)
Implementation
09/2020 (Estimated)
Project documents
Robert Cochran · rcochran@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT.36S, R.4E, Sec.4
Decision Memo · Siskiyou Mountains Ranger District · updated 7/10/2020
Put in would be just below Applegate Dam where Country Road 859 crosses the River.Take out locations will be on the west side of the river near the Placer Day Use Area, McKee Bridge,and Cowhorn Winery · Jackson, Oregon

Provide 1/2 day, 2/3 day, and full day guided inflatable kayak and raft trips on the Applegate River. Put in would be just below Applegate Dam where Country Road 859 crosses the Applegate River.

Special use management
Scoping Start
03/2018 (Estimated)
Decision
01/1970 (Estimated)
Implementation
05/2018 (Estimated)
Project documents
Brian Long · bplong@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Decision Decided Date07/02/2026
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT 40 S., R 3 W. Sec. 4, 5 and 10, Willamette Meridian
Decision Memo · Wild Rivers Ranger District · updated 7/10/2020
East Fork Illinois Watershed · Josephine, Oregon

Identifying, marking, and removing roadside conifers, in the East Fork Illinois Watershed, to be used for stream restoration. Trees measuring 15" to 30" in diameter, located in over stocked stands near stream projects would be used.

Watershed managementWildlife, fish, rare plants
Scoping Start
04/26/2018
Decision
12/2018 (Estimated)
Implementation
12/2018 (Estimated)
Project documents
Chris Park · cpark@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Watershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT39S, R06W; T40S, R06 07W; T41S, R06 07 08W
Decision Memo · Siskiyou Mountains Ranger District · updated 7/10/2020
Along the Siskiyou Crest on the Pacific Crest Trail and spur trails starting from Mt Ashland and ending at Cook and Green Pass. · Jackson; Siskiyou, California; Oregon

Provide 2 to 4 day guided hiking and running trips along the Siskiyou Crest on the Pacific Crest Trail, starting from Mt Ashland and ending at Cook and Green Pass. Group size will be up to 15 people. Camping will be at existing and dispersed sites.

Special use management
Scoping Start
03/2018 (Estimated)
Decision
01/1970 (Estimated)
Implementation
05/2018 (Estimated)
Project documents
Brian Long · bplong@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Decision Decided Date07/02/2026
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land Description(T 40 S., R 1 E. Sec.21, Willamette Meridian) Cook and Green Pass (T 18 N,. R 11 W., Sec. 8, Diablo Meridian)
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 5/29/2020
Near Fish Lake and along Highway 140 · Jackson, Oregon

AT&T proposing to install a fiber optic line at Highway 140 near Fish Lake for 4.3 miles to the top of Robinson Butte communications site. The fiber optic line will be placed in conduit and will follow an existing, authorized electrical right-of-way

Special use management
Scoping Start
12/27/2018
Decision
05/2020 (Estimated)
Implementation
05/2020 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Robinson Butte/AT&T Fiber Optic InstallationDecision Signed Date: 05/21/2020
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionTownship 37S, Range 4E, Section 8
Decision Memo · J. Herbert Stone Nursery · updated 3/2/2020
J Herbert Stone Nursery, located near Central Point, OR · Jackson, Oregon

Authorize the use of modern pesticides for use in the JHS Nursery's integrated pest management program to improve effectiveness, reduce environmental impacts, and increase worker and public health and safety.

Facility managementVegetation management (other than forest products)
Scoping Start
07/22/2016
Decision
02/2020 (Estimated)
Implementation
03/2020 (Estimated)
Project documents
John Justin · jbjustin@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (3), 36 Cfr 220.6(D)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityNoxious Weed Treatments
ForestsRogue River-Siskiyou National Forest
DistrictsJ. Herbert Stone Nursery
Legal Land DescriptionNot Applicable
Environmental Impact Statement · Rogue River-Siskiyou National Forest All Units · updated 2/18/2020
Illinois River; multiple land allocations · Coos; Curry; Josephine, Oregon

Salvage logging, reforestation and construction of fuel managment zones, meadow restoration, road stabilization and road decommissioning.

Fuels managementForest productsRoad managementSpecial area managementVegetation management (other than forest products)
NOI in Federal Register
03/19/2003
DEIS NOA in Federal Register
11/23/2003
FEIS NOA in Federal Register
06/04/2004
Decision
07/2004 (Estimated)
Implementation
08/2004 (Estimated)
Project documents
Judith McHugh · jmchugh@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Species Habitat Improvements; Roadless Area Management; Road Maintenance; Road Improvements/Construction; Timber Sales (Salvage)
BFRP Matrix Salvage and Planting,...Decision Signed Date: 07/08/2004 Legal Notice Date: 07/08/2004
BFRP Late-Successional Reserve Salvage and PlantingDecision Signed Date: 07/08/2004 Legal Notice Date: 07/08/2004
BFRP Salvage and Planting in Inventoried Roadless AreasDecision Signed Date: 07/08/2004 Legal Notice Date: 07/08/2004
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 2/14/2020
Perk's Cabin · Jackson, Oregon

Proposed treatments to reduce hazardous fuel loadings around Perks Cabin to create a fuel break to protect the historical administrative site, enhancement of wildlife habitat, timbered stands, range conditions, and protect range improvements

Facility managementHeritage resource management
Scoping Start
09/26/2016
Decision
03/2018 (Estimated)
Implementation
05/2018 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (12), 36 Cfr 220.6(E)(12)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityHeritage Resource Management; Facility Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Wild Rivers Ranger District · updated 2/12/2020
About 10 miles WSW of O'Brien, Oregon. Generally between Baldface, Taylor, and Fall Creeks within the North Fork Smith River watershed, Curry County, Oregon. · Curry, Oregon

Red Flat Nickel Corp. plans to drill 59 3-inch diameter holes to a depth of 50 feet to obtain core samples of minerals in Curry County, Oregon. Equipment and personnel would be transported and removed via helicopter.

Minerals and geology
Scoping Start
05/2015 (Estimated)
Comment Period
10/2015 (Estimated)
Objection Period Start
12/2015 (Estimated)
Decision
03/2016 (Estimated)
Implementation
05/2016 (Estimated)
Project documents
Robert Shoemaker · rshoemaker@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityMinerals Or Geology Plans Of Operations
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionPrimarily T41S-R10W-Sections 5-8, 17, 18; T41S-R11W-Sections 1, 12
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 2/12/2020
The road is located on the Gold Beach Ranger District, between the Myrtle Tree trailhead and the confluence of the Pine Grove/Illinois River, 22 miles from Gold Beach. · Curry, Oregon

The goal is to improve safety along Forest Service road 3300 for public and Forest Service employees. Danger trees that have the potential to fall onto the roadway will be felled and removed within approximately 200 feet on either side.

Road management
Scoping Start
06/08/2017
Decision
02/2018 (Estimated)
Implementation
05/2018 (Estimated)
Project documents
Wade McMaster · wmcmaster@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionT. 35 S., R. 13 W., Section 31, 32, 33, 34, 35, 2, 7, & 36, T. 35 S., R. 12 W., Section 31, 30, 29, 20, 21, 16, 15, 11, 14, & 13
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 1/31/2020
Willow Lake · Jackson, Oregon

This is a renewal of an existing special use permit for sewage retention ponds on NFS for willow lake campgrounds and willow lake resort. They are permitted by ODEQ. The permit would be requested for a 20 year term.

Recreation managementFacility management
Scoping Start
11/07/2018
Decision
03/2019 (Estimated)
Implementation
01/2019 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (10)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Facility Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionTownship 36S Range 3E Section 3
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 1/31/2020
Powers Ranger District · Curry, Oregon

Reissuance of a special use permit for a waterline for domestic use. This waterline runs underneath the parking lot of the Powers Ranger District.

Special use managementFacility management
Scoping Start
11/07/2018
Decision
03/2019 (Estimated)
Implementation
01/2019 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (10)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Facility Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Powers Ranger District · updated 1/31/2020
3348 Road (M.P. 17) along the Powers to Glendale route · Curry, Oregon

The project will replace a culvert that is currently a barrier to juvenile anadromous fish on 3348 Road (M.P. 17) along the Powers to Glendale route.

Wildlife, fish, rare plantsWatershed managementRoad management
Scoping Start
01/06/2020
Decision
01/2020 (Estimated)
Implementation
01/2020 (Estimated)
Project documents
Karla Cottom · kcottom@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Road Maintenance; Watershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Siskiyou Mountains Ranger District · updated 1/10/2020
There are 4 allotments within the Siskiyou Mountains Ranger District being evaluated. These 4 allotments cover approximately 166,442 acres and straddle the Oregon/California border. · Jackson; Siskiyou, California; Oregon

Grazing on federal lands will be evaluated. This effort would ensure updated information is provided for the sustained health of rangeland and forest ecosystems.

Grazing management
Scoping Start
02/16/2017
Comment Period
01/2018 (Estimated)
Objection Period Start
01/2018 (Estimated)
Decision
04/2018 (Estimated)
Implementation
04/2018 (Estimated)
Project documents
Mark Hocken · mhocken@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityGrazing Allotment Management
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Cedar Gulch Mine Cancelled
Environmental Impact Statement · Wild Rivers Ranger District · updated 1/10/2020
South bank of Sucker Creek, about 11 miles southeast of Cave Junction, Oregon. Within Riparian Reserve and Late Successional Reserve. · Josephine, Oregon

Previously known as Tracy Placer Mining Project (#9992). Prepare Supplemental EIS and environmental review of proposed Plan of Operations for placer mining less than 5 acres in the Sucker Creek watershed.

Minerals and geology
NOI in Federal Register
07/12/2011
DEIS NOA in Federal Register
10/2015 (Estimated)
FEIS NOA in Federal Register
02/2016 (Estimated)
Objection Period Start
02/2016 (Estimated)
Decision
06/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
Robert Shoemaker · robert.shoemaker@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityMinerals Or Geology Plans Of Operations
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT40S, R06W, Section 19
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 12/10/2019
Approximately 5,216 acres of BLM-managed and revested O&C lands and 95,806 acres of NFS lands within the Hunter Creek and Pistol River Headwaters and the Rough and Ready and Baldface Creek Watersheds. · Curry; Josephine, Oregon

Recommend the Secretary of the Interior withdraw from location and entry under mining laws about 101,022 acres of NFS and BLM lands, subject to valid existing rights, for a period of 5 years in aid of legislation (HR682/S346).

Special area managementWildlife, fish, rare plantsMinerals and geologySpecial use management
Scoping Start
06/29/2015
Comment Period
04/27/2016
Decision
08/2016 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
Roy Bergstrom · rbergstrom@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityLand Use Adjustments; Special Area Management
2015 SW Oregon Mineral Withdrawals - FONSI and RecommendationDecision Signed Date: 07/13/2016
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District; Gold Beach Ranger District
Legal Land DescriptionSee project record for complete legal land description of the withdrawal area as described in the "Southwestern Oregon Watershed and Salmon Protection Act of 2015 "(S. 346 and H.R. 682).
Decision Memo · Gold Beach Ranger District · updated 12/10/2019
T38S R13W, T39S R12W, T40S R12W, and T41S R12W · Curry, Oregon

Authorizes treatment of sudden oak death for vegetation infected by non-native pathogen, Phytophthora ramorum. Treatment includes ~ 8 sites across ~ 122 acres in Pistol R, Wheeler Cr, Little Emily Cr, Winchuck R, Deer Cr, & Little Emily Cr watersheds

Vegetation management (other than forest products)
Scoping Start
08/08/2019
Decision
10/2019 (Estimated)
Implementation
10/2019 (Estimated)
Project documents
Charles Grell · charles.grell@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (14), 36 Cfr 220.6(E)(14)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Timber Sales (Green); Watershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Siskiyou Mountains Ranger District · updated 12/10/2019
Applegate Adaptive Management Area · Jackson; Josephine; Siskiyou, California; Oregon

Thin overcrowded, previously managed stands (plantations) located within the Applegate Adaptive Management Area (AMA) in order to maintain and enhance forest health and terrestrial and aquatic species habitat

Wildlife, fish, rare plantsForest productsFuels management
Scoping Start
05/12/2009
Comment Period
05/25/2010
Decision
09/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
Katie Schubert · kschubert@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green)
Strongarm Pine Plantation Thinning and RestorationDecision Signed Date: 09/28/2012 Legal Notice Date: 09/28/2012
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Environmental Assessment · Siskiyou Mountains Ranger District · updated 12/10/2019
Ashland Creek and Neil Creek watersheds · Jackson, Oregon

Addition of 21.5 miles of existing historic/unapproved trails, 9.4 miles of new trails, and decommission 5.2 miles of trails.

Recreation management
Scoping Start
06/13/2012
Comment Period
12/29/2014
Objection Period Start
11/02/2015
Decision
12/2015 (Estimated)
Implementation
04/2016 (Estimated)
Project documents
Brian Long · bplong@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityTrail Management
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT39S, R1E, Sec.17, 19, 20, 21, 27, 30-32, and 34; T40S, R1E, Sec. 2-9, and 17-19; T40S, R1W, Sec. 1, 12, and 13, W.M., Jackson Co., OR
Decision Memo · High Cascades Ranger District · updated 12/10/2019
Big Elk Cinder Pit · Jackson, Oregon

Oregon Department of Transportation (ODOT) has requested authorization to extract and crush pitrun cinders from approx. 5 acres of an existing quarry for use as a sanding aggregate to improve traction along OR-140, OR-62, and Big Elk Road.

Special use management
Scoping Start
07/25/2013
Comment Period
07/25/2013
Decision
01/2014 (Estimated)
Implementation
09/2014 (Estimated)
Project documents
Scott Blower · sblower@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionW½ SW¼ sec. 17, Township 37 South, Range 4 East, of the Willamette Meridian
Decision Memo · High Cascades Ranger District · updated 12/10/2019
Approximately 8 air miles north of Lost Creek Reservoir (along OR Hwy 62). · Jackson, Oregon

Reconstruct inlet to an off-channel pond to provide consistent flow of water from mainstem Bitter Lick Creek channel. Reconfigure four legacy instream structures that currently impair movement of juvinile anadromous fish.

Wildlife, fish, rare plantsWatershed management
Scoping Start
06/16/2014
Decision
10/2014 (Estimated)
Implementation
05/2015 (Estimated)
Project documents
Steven Brazier · sbrazier@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Watershed Improvements
Bitter Lick Creek RestorationDecision Signed Date: 10/23/2014
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionNortheast 1/4 section 12, Township 32 South, Range 1 East, of Willamette Meridian.
Decision Memo · Wild Rivers Ranger District · updated 12/10/2019
PP&L route southwest of O'Brien, OR · Josephine, Oregon

Construction of 3.6 miles of an aerial fiber interconnect on forest lands within an existing Pacific Power and Light (PP&L) easement.

Special use management
Scoping Start
09/07/2012
Comment Period
10/13/2012
Decision
11/2012 (Estimated)
Implementation
12/2012 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Charter CommunicationDecision Signed Date: 11/14/2012 Legal Notice Date: 11/17/2012
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land Descriptionsec. 27 and 37, T. 40 S., R. 9 W., and sec. 4, 8, and 17, T. 41 S., R. 9 W., of the Willamette Meridian
Environmental Assessment · Gold Beach Ranger District · updated 12/10/2019
East of Brookings in Curry County, Oregon. The project area is contained to parts of the Chetco and Pistol River 5th field watershed. · Curry, Oregon

The proposed project focuses on salvage within the 13,626 acres of matrix that incurred 50-100% canopy cover loss during the Chetco Bar Fire.

Forest productsVegetation management (other than forest products)
Scoping Start
01/05/2018
Comment Period
04/16/2018
Decision
06/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
Jessie Berner · jberner@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityTimber Sales (Salvage)
Chetco Fire Salvage Decision Notice and Finding of No Significant ImpactDecision Signed Date: 06/26/2018
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Gold Beach Ranger District · updated 12/10/2019
Along the Chetco River about 11 miles northeast of Brookings, Oregon in Curry County. · Curry, Oregon

Permit to conduct guided kayaking trips on the Chetco River between Boulder Creek and S. Fork Chetco River. Authorizes 80 priority-use days per year; limits group size to 8 clients plus 2 guides per trip.

Recreation managementSpecial use management
Scoping Start
09/01/2014
Decision
09/2014 (Estimated)
Implementation
10/2014 (Estimated)
Project documents
Bob Hemus · bhemus@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDispersed Recreation Mgmt.; Special Area Management
Special use authorization for outfitting and guiding on the Chetco RiverDecision Signed Date: 09/18/2014
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · High Cascades Ranger District · updated 12/10/2019
Approximately 5 miles east of Butte Falls, Oregon along County Highway 821 · Jackson, Oregon

Prescribed burning (some Spring prep burning, with all units burned in fall) on up to 6,450 acres to improve wildlife habitat (improve quantity and quality of forage) and maintain current low fuel loading in project areas.

Wildlife, fish, rare plantsFuels management
Scoping Start
06/09/2014
Decision
08/2014 (Estimated)
Implementation
10/2014 (Estimated)
Project documents
Jeff VonKienast · jvonkienast@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Species Habitat Improvements
Clarks Fork Wildlife Enhancement and Fuels Treatment ProjectDecision Signed Date: 08/14/2014
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionTownship 35 & 36 South, Range 3 & 4, East, Willamette Meridian, Jackson County, Oregon
Decision Memo · Gold Beach Ranger District · updated 12/10/2019
Within Curry Co.on Forest Service lands adjacent to the Rogue River from approx. Foster Bar west to the USFS boundary, and adjacent to the Illinois River from Oak Flat north to Rogue River. · Curry, Oregon

Renewal of existing Coos-Curry Electric Cooperative, Inc. power line special use permits and incorporation of amendments into one authorization, including an operations and maintenance plan. No new construction or ground disturbance would occur.

Special use management
Scoping Start
12/10/2013
Decision
07/2014 (Estimated)
Implementation
08/2014 (Estimated)
Project documents
Holly Witt · hfwitt@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations
Coos-Curry Electric Cooperative,Inc. Power Line Special Use Permit RenewalDecision Signed Date: 07/14/2014 Legal Notice Date: 07/14/2014
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 12/10/2019
Approximately 12 air miles west of Grants Pass, Oregon, in the Shan Creek drainage. · Josephine, Oregon

A collaborative partnership between Forest Service, BLM, USFWS and ODA to introduce Fritillaria gentneri into oak habitat in the Shan Ck area. A total of 4-8 plots, planted with pickaxe or shovel. No vegetation will be removed in planting.

Wildlife, fish, rare plants
Scoping Start
08/04/2014
Decision
12/2014 (Estimated)
Implementation
07/2015 (Estimated)
Project documents
Stuart Osbrack · sosbrack@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Population Enhancements
Fritillaria Gentneri ReintroductionDecision Signed Date: 12/05/2014
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionTownship 36S.,R.7W.,Willamette Meridian, Sections 4 and 9
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 12/10/2019
J. Herbert Stone Nursery · Jackson, Oregon

As part of a grant from Department of Energy the Forest Service proposes to construct a 500.5-kilowatt solar array, covering approx. 1.2 acres, at the nursery site. The life expectancy of the array exceeds 20 years.

Facility management
Scoping Start
07/12/2016
Comment Period
11/01/2016
Objection Period Start
12/15/2016
Decision
02/2017 (Estimated)
Implementation
03/2017 (Estimated)
Project documents
Sitka Pence · sitkapence@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFacility Improvements/Construction
ForestsRogue River-Siskiyou National Forest
DistrictsJ. Herbert Stone Nursery
Legal Land DescriptionNot Applicable
Kimball Thin Completed
Environmental Assessment · Gold Beach Ranger District · updated 12/10/2019
Approximately 6 miles NE of Gold Beach, Oregon · Curry, Oregon

Variably thin up to 350 acres of dense, naturally-regenerated conifer forest, that is 50 to 80 years old. The goal is to enhance the development of late-successional conditions for the benefit of old-growth related species.

Wildlife, fish, rare plantsForest productsVegetation management (other than forest products)
Scoping Start
12/24/2014
Comment Period
05/11/2016
Objection Period Start
08/24/2016
Decision
12/2016 (Estimated)
Implementation
04/2017 (Estimated)
Project documents
Barbara Cisneros · bcisneros@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityForest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green)
Final Decision Notice and Finding of No Significant Impact for Kimball ThinDecision Signed Date: 12/15/2016
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionT36S-R13W, Willamette Meridian
Environmental Impact Statement · Rogue River-Siskiyou National Forest All Units · updated 12/10/2019
All Rogue River-Siskiyou National Forest · Coos; Curry; Douglas; Jackson; Josephine; Klamath; Del Norte; Siskiyou, California; Oregon

Supplement to the Motorized Vehicle Use on the Rogue River-Siskiyou National Forest EIS.

Land management planning
NOI in Federal Register
08/02/2010
DEIS NOA in Federal Register
10/07/2011
FEIS NOA in Federal Register
09/17/2015
Objection Period Start
09/17/2015
Decision
06/2016 (Estimated)
Implementation
08/2016 (Estimated)
Project documents
Peggy Okeefe · pokeefe@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityPlan Creation/Revision
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionAll Rogue River-Siskiyou National Forest
Decision Memo · Siskiyou Mountains Ranger District · updated 12/10/2019
SMRD · Jackson, Oregon

BLM submitted a special use permit request for use of a 317 ft section of road on FS land.

Special use management
Scoping Start
09/16/2016
Decision
09/2016 (Estimated)
Implementation
09/2016 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · High Cascades Ranger District · updated 12/10/2019
The distribution line runs from Prospect approximately 13 miles along Highway 62 to Union Creek. · Jackson, Oregon

Renewal of a permit for an existing distribution feeder line and single phase distribution line for a 50 year term. There will be no ground disturbance associated with this renewal.

Special use management
Scoping Start
05/06/2013
Comment Period
09/16/2013
Decision
10/2013 (Estimated)
Implementation
11/2013 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (10)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
PacifiCorp Powerline RenewalDecision Signed Date: 10/31/2013 Legal Notice Date: 11/08/2013
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land Descriptionsec. 5, 8, 9, 17, 20, 29, 30, T32S, R3E; sec. 3, 4, 9, 10, 15, 16, 20, 21, 29, 32, 33, T31S, R3E; sec. 34, T30S, R3E, WM
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 12/10/2019
The parcel of National Forest land on the north side of L Street, bounded by Judson Street on the east, J Street on the north and the lot line boundary with private on the west (approximately 3 acres) · Josephine, Oregon

Seven buildings constructed by the Civilian Conservation Corps on L Street in Grants Pass, Oregon. This compound operated as the Siskiyou National Forest Supervisor's office warehouse. This property became underutilized in 2007.

Facility management
Scoping Start
11/10/2014
Decision
09/2015 (Estimated)
Implementation
12/2015 (Estimated)
Project documents
Roy Bergstrom · rbergstrom@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (7), 36 Cfr 220.6(D)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityLand Use Adjustments
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land Description1012 S.W. L Street; S 1/2 of section 18, T. 36 S., R. 5 W., Willamette Meridian, Josephine County, Oregon.
Decision Memo · J. Herbert Stone Nursery · updated 12/10/2019
J. Herbert Stone Nursery · Jackson, Oregon

A decision memo is being prepared to authorize renewal of 4 existing special use authorizations: 2 power lines, 1 natural gas line, and 1 telephone line at the J. Herbert Stone Nursery. The permit would be issued for a 20 year term.

Special use management
Scoping Start
01/01/2013
Comment Period
01/15/2013
Decision
05/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Special Use Permit Renewals at J. Herbert Stone Nursery Decision MemoDecision Signed Date: 05/09/2013
ForestsRogue River-Siskiyou National Forest
DistrictsJ. Herbert Stone Nursery
Legal Land DescriptionT. 37 S., R. 2 W., Sec. 15 and 16, Willamette Meridian
Environmental Assessment · Wild Rivers Ranger District · updated 12/10/2019
Sucker Creek 5th field watershed · Josephine, Oregon

Decommissioning, stormproofing and stream crossing upgrades to legacy roads and trails within the Sucker Creek 5th field watershed.

Watershed managementRoad management
Scoping Start
10/01/2013
Comment Period
11/19/2014
Objection Period Start
02/13/2015
Decision
04/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
Chris Park · cpark@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Road Maintenance; Road Improvements/Construction; Watershed Improvements
Sucker Creek Legacy Roads and Trails Decision NoticeDecision Signed Date: 04/13/2015
Sucker Creek Legacy Roads and Trails Decision Notice and FONSIDecision Signed Date: 04/13/2015
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT. 39 S., R. 6 W., T. 39 S. R. 5 W., T. 40 S., R. 6 W., T. 40 S., R. 5 W., T. 41 S., R. 6 W., of the Willamette Meridian
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 9/19/2019
Located on the Frog Lake (3313100) and Quosatana (3313) road systems. · Curry, Oregon

Install a trail bridge across Frog Lake Creek on road 3313.100. The bridge would be approximately 42 feet long and 68 inches wide which would be wide enough for all-terrain-vehicles as well as non-motorized users but not full-sized vehicles.

Recreation management
Scoping Start
04/26/2018
Decision
06/2019 (Estimated)
Implementation
09/2019 (Estimated)
Project documents
David Sheehan · dsheehan@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management; Travel Management
Frog Lake Creek Off-road Vehicle BridgeDecision Signed Date: 06/17/2019
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Wild Rivers Ranger District · updated 11/26/2018
Miami Bar to Lower Oak Flat (confluence with Rogue River). · Josephine, Oregon

Guided commercial outfitter/guiding service for rafting/paddling use on the Illinois River from March 1 thru June 30. Put in site is at Miami Bar below McCaleb's Ranch. Take out will be at the confluence of the Rogue River at Lower Oak Flat.

Recreation management
Scoping Start
09/26/2016
Decision
11/2018 (Estimated)
Implementation
11/2018 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDispersed Recreation Mgmt.; Wilderness Management
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Siskiyou Mountains Ranger District · updated 11/2/2018
West side of Applegate Lake located in Jackson County, Oregon. · Jackson, Oregon

DaKuBeTeDe trail, west side of Applegate lake needs to be rerouted. Total reroutes would be approximately 200%u2019 in length and would follow Forest Service Trail Design Parameters for a class 2 trail with a tread width of approximately 24 inches.

Recreation management
Scoping Start
06/05/2017
Decision
10/2018 (Estimated)
Implementation
11/2018 (Estimated)
Project documents
Brian Long · bplong@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionSection 36. T. 40 S., R. 4 W. Willamette Meridian.
Decision Memo · High Cascades Ranger District · updated 11/1/2018
Access via Forest Service Road 6540-435, within the Foster Creek drainage of the Upper Rogue Watershed. · Douglas, Oregon

Foster Creek Quarry is an existing quarry that the Forest Service is proposing to authorize a new operator to remove 4,000 cubic yards of clay per year for up to five years.

Special use managementMinerals and geology
Scoping Start
09/22/2018
Decision
11/2018 (Estimated)
Implementation
11/2018 (Estimated)
Project documents
Robert Shoemaker · rshoemaker@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Minerals Or Geology Plans Of Operations
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT 29 South R 3 East S 13
Decision Memo · Siskiyou Mountains Ranger District · updated 9/17/2018
Mount Ashland Lodge, Jackson County, Oregon. The trail would start at the lodge and would terminate near the summit. · Jackson, Oregon

Incorporate approximately .9 mile of trail on Mount Ashland as part of the National Forest System trail network by signing the trail and adding the trail to maps, using existing ski runs, old road beds and the existing trail bed where possible.

Recreation management
Scoping Start
06/05/2017
Decision
09/2018 (Estimated)
Implementation
09/2018 (Estimated)
Project documents
Brian Long · bplong@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNW ? and NE ? Section 21. T. 40 S., R. 1 E. Willamette Meridian.
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 8/9/2018
Forest Wide · Curry; Jackson; Josephine, Oregon

Site identified for this project are either low use, or already closed sites. This decommissioning and removal is part of the recreation and facilities master plan and will decrease the back log of deferred maintenance.

Recreation managementFacility management
Scoping Start
09/21/2016
Decision
04/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Dispersed Recreation Mgmt.; Facility Maintenance
Decision Decided Date04/06/2017
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Gold Beach Ranger District · updated 8/9/2018
Locations spread-out throughout the Gold Beach District. · Curry, Oregon

Renewal of nine existing expired special use permits. Re-authorization includes following uses: water transmission lines, tramways, driveways, and water storage facilities. No new construction or ground disturbance would occur.

Special use management
Scoping Start
03/13/2015
Decision
09/2015 (Estimated)
Implementation
09/2015 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 8/9/2018
T. 40 S., R. 3 W., Sec: 7 · Jackson, Oregon

The project would remove a legacy channel spanning diversion dam (~3inch in height) at Palmer Creek, Siskiyou Mountains Ranger District. The dam is not currently used for water diversion.

Watershed management
Scoping Start
09/26/2016
Decision
07/2017 (Estimated)
Implementation
07/2017 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Gold Beach Ranger District · updated 7/19/2018
Road is located in the north 1/2 Sec. 6, T39S, R12W, W.M. · Jackson, Oregon

Because the 1407-150 is closed due to a large slide, South Coast Lumber is requesting access their land for fire salvage through an alternate route. This is in T39S R12W in the north half of sec 6. Used only during dry periods. Not considered public.

Special use managementRoad management
Scoping Start
06/01/2018
Decision
07/2018 (Estimated)
Implementation
07/2018 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Road Maintenance; Road Improvements/Construction
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionN 1/2 Sec. 6, T39S, R12W, W.M
Decision Memo · Siskiyou Mountains Ranger District · updated 5/29/2018
Location is in the Whiskey Creek drainage 3-4 miles west of Applegate Lake . · Jackson, Oregon

Murphy Timber Investments is proposing to build approximately 850 feet of temporary road and a landing to facilitate salvage of fire-damaged trees from their lands.

Special use management
Scoping Start
02/01/2018
Decision
04/2018 (Estimated)
Implementation
05/2018 (Estimated)
Project documents
Donald Boucher · dboucher@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · High Cascades Ranger District · updated 5/17/2018
Big Butte Springs Watershed, Willow Creek Subwatershed, 171003070403. · Jackson, Oregon

Provide volunteer service for basic maintenance and repairs at the Willow Prairie Horse Camp. Maintenance repairs would include maintenance and repairs to the horse camp and associated authorized trail systems.

Special use management
Scoping Start
04/02/2018
Decision
05/2018 (Estimated)
Implementation
05/2018 (Estimated)
Project documents
Robert Cochran · rcochran@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8); 32.12 (10)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT. 36S, R.4E, Sec.30
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 4/2/2018
Rogue River-Siskiyou NF · Curry; Jackson; Josephine; Del Norte; Siskiyou, California; Oregon

Renewal of 32 special use permits to maintain and operate water transmission pipelines on the Rogue River-Siskiyou NF.

Special use management
Scoping Start
09/21/2016
Decision
04/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 3/12/2018
4 on High Cascades Ranger District, 1 on Wild Rivers Ranger District, 1 on Siskiyou Mountains Ranger District, 1 on Gold Beach Ranger District and 1 on Powers Ranger District. · Curry; Jackson; Josephine, California; Oregon

The permit renewal authorizes the holders special use permits for operating and maintaining existing water pipelines, for up to a 20 year term.

Special use management
Scoping Start
08/01/2017
Decision
03/2018 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 3/8/2018
There are multiple locations spread across the forest. · Jackson; Josephine; Del Norte, California; Oregon

Four existing or expired special use permits for powerlines are up for renewal. These expired permits would be authorized for 20-year renewal terms. No new construction or additional ground disturbance is being authorized with this action.

Special use management
Scoping Start
06/20/2017
Decision
02/2018 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District; Wild Rivers Ranger District; High Cascades Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 3/8/2018
High Cascades Ranger District (near fish lake) and Siskiyou Mountains Ranger District (near mount Ashland). · Jackson, California; Oregon

reissuance of three permits: two located on High Cascades, one for a 4-wire suspension fence and the other for maintaining precipitation gauges. And one for maintenance of multiple weather station/SNOTEL sites across the forest.

Special use management
Scoping Start
02/12/2018
Decision
03/2018 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 3/8/2018
Fish Lake Resort, Fish Lake, Oregon. Fire Lookout Tower located in T.32S., R.2E., Sec.23, W.M. · Jackson, Oregon

Two expired special use permits for buildings are up for reauthorization. Expired permits would be reauthorized for 20-year renewal terms. No new construction or additional ground disturbance is being authorized with this action.

Special use management
Scoping Start
06/08/2017
Decision
02/2018 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 3/8/2018
SMRD, Jackson County. T.39S., R.1W., Sec. 26, W.M. · Jackson, Oregon

Reauthorization of a permit for using and maintaining an existing road that crosses NFS lands to allow access to private property.

Special use management
Scoping Start
02/12/2018
Decision
03/2018 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 3/8/2018
WRRD, Josephine County. T.38S., R.9W., Sec. 12, W.M.; HCRD, Jackson County. T.38S., R.9W., Sec. 12, W.M. · Jackson; Josephine, Oregon

Re-issuance of two special use permits for access roads. The roads are already existing and access private property.

Special use management
Scoping Start
02/12/2018
Decision
03/2018 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District; High Cascades Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 2/9/2018
Rogue River Siskiyou National Forest Road System affected by fires in 2017 · Curry; Douglas; Jackson; Josephine, Oregon

Danger Tree removal along roadsides that were affected by 2017 fires.

Road management
Scoping Start
11/29/2017
Decision
02/2018 (Estimated)
Implementation
04/2018 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Decision Decided Date02/09/2018
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Environmental Assessment · High Cascades Ranger District · updated 10/13/2017
About 18 miles north of Prospect, OR · Douglas, Oregon

The project would authorize mining a sulfur enriched clay mineral deposit (epithermal argillite) on approximately 5 acres of land for up to 10 years. There would be no vegetation removal.

Minerals and geology
Scoping Start
06/21/2012
Comment Period
04/2013 (Estimated)
Decision
06/2013 (Estimated)
Implementation
08/2013 (Estimated)
Project documents
Karla Gallegos · kgallegos@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityMinerals Or Geology Plans Of Operations
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionW½, NW¼, Sec. 13, T. 29 N., R. 4 E., W.M., Douglas Co., OR.
Decision Memo · Gold Beach Ranger District · updated 8/21/2017
T 39 S, R 12 W, T 40 S, R. 12 W, T 40 S, R. 13 W, T 41 S, R. 12 W, and T 40 S, R. 12 W. Gold Beach Ranger District. · Curry, Oregon

SOD eradication treatments at six confirmed sites. Treatment entails injecting herbicide into tanoak to prevent tanoak sprouts on approximately 80 acres. Additional treatment entail cutting, piling, and burning known infected and adjacent tanoaks.

Vegetation management (other than forest products)
Scoping Start
06/06/2017
Decision
08/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
Tina Lanier · tclanier@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (14), 36 Cfr 220.6(E)(14)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Siskiyou Mountains Ranger District · updated 8/2/2017
Hartish Boat Ramp of Applegate Lake. · Jackson, Oregon

Replace the existing 450 foot long steel guide beam; current boat dock attaches to with a 2-foot by 4-foot concrete guide that a new ADA accessible boat dock will attach to. All work will occur on existing concrete boat ramp during low water period.

Recreation management
Scoping Start
06/08/2017
Decision
08/2017 (Estimated)
Implementation
07/2017 (Estimated)
Project documents
Donna Mickley · dmickley@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management
Decision Decided Date08/02/2017
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · High Cascades Ranger District · updated 7/28/2017
Stands adjacent to Hwy 62 between Prospect and Union Cr, and adjacent to Hwy 230 from its junction with Hwy 62 up approx 5 miles. · Jackson, Oregon

Variable density and radial thinning to remove encroaching Douglas-fir, white fir, and dense understory around large old trees, followed by underburning.

Forest productsFuels management
Scoping Start
10/28/2009
Comment Period
03/07/2017
Objection Period Start
05/04/2017
Decision
07/2017 (Estimated)
Implementation
08/2017 (Estimated)
Project documents
Jeff VonKienast · jvonkienast@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityBiomass; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green)
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Siskiyou Mountains Ranger District · updated 7/20/2017
Near Condrey Mountain along Siskiyou Crest in an area known as Alex Hole. · Siskiyou, California

A fence (exclosure) will be placed at Alex Hole to exclude livestock access to the riparian area. An exclosure will improve riparian and watershed conditions. The exclosure will be designed using let-down features and will be placed seasonally.

Grazing management
Scoping Start
06/08/2017
Decision
07/2017 (Estimated)
Implementation
07/2017 (Estimated)
Project documents
Donna Mickley · dmickley@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Structural Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNESE Sec 11 of T47N, R10W
Decision Memo · Siskiyou Mountains Ranger District · updated 7/20/2017
Township 40 S, Range 1 East, NW 1/4 of NE 1/4 of Section 21, Jackson County, Oregon. · Jackson, Oregon

Mt. Ashland Ski Area proposes to remodel the main ski lodge. Changes to the exterior include enclosing the Poma and Juliet decks, remodeling the inside of the lodge to accommodate the increasing number of guests. No new ground disturbing activities

Recreation management
Scoping Start
05/22/2017
Decision
06/2017 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 7/18/2017
Forest Service road 25 also called Bear Camp Road · Curry, Oregon

Mitigation of identified danger trees along Forest Service road 23, for public and employee safety. Trees that are identified and mitigation may be removed, where management direction allows and it is done in an environmentally responsible manner

Road management
Scoping Start
09/28/2016
Decision
05/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · High Cascades Ranger District · updated 6/1/2017
Abbott Creek, Kiter Creek, Needle Creek, and Woodruff Creek · Jackson, Oregon

Install instream log and boulder structures remove fish passage barriers to improve habitat quality for resident trout.

Wildlife, fish, rare plantsWatershed management
Scoping Start
06/08/2016
Decision
06/2017 (Estimated)
Implementation
07/2017 (Estimated)
Project documents
Steven Brazier · sbrazier@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Watershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 5/12/2017
Forest-wide · Curry; Jackson; Josephine, Oregon

Reauthorization of current existing special use permits to use and maintain access roads for access to private property or for commercial use.

Special use management
Scoping Start
09/26/2016
Decision
05/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District; High Cascades Ranger District; Gold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 4/6/2017
T. 37 S., R. 2 W., Sec: 16 & 24 · Jackson, Oregon

Purpose is to re-issue a special use permit for operating and maintain a sewage collection system across the J. Herbert Stone Nursery.

Special use management
Scoping Start
09/21/2016
Decision
04/2017 (Estimated)
Implementation
04/2017 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsJ. Herbert Stone Nursery
Legal Land DescriptionNot Applicable
Decision Memo · Tiller Ranger District · updated 3/16/2017
Pacific Connector Gas Pipeline right-of-way · Douglas; Jackson; Klamath, Oregon

Renew existing special use permit to facilitate continued study/analysis on proposed Pacific Connector Gas Pipeline right-of-way. No new improvements outside existing survey areas are authorized with permit renewal.

Special use management
Scoping Start
01/12/2017
Decision
03/2017 (Estimated)
Implementation
03/2017 (Estimated)
Project documents
David Krantz · dkrantz@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
SUP Renewal Site Survey and Testing Pacific Connector Gas PipelineDecision Signed Date: 03/15/2017
ForestsFremont-Winema National Forest; Rogue River-Siskiyou National Forest; Umpqua National Forest
DistrictsKlamath Ranger District; High Cascades Ranger District; Tiller Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 3/3/2017
Gold Beach Ranger Station · Curry, Oregon

This project includes replacement of the existing water distribution system at the Gold Beach Ranger Station.

Facility management
Scoping Start
09/21/2016
Decision
03/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
Gretchen Smith · gretchensmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (3), 36 Cfr 220.6(D)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Maintenance
Decision Decided Date03/03/2017
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 12/5/2016
Forest-wide plan amendment authorizes no treatments, but allows projects to consider using an additional herbicide with fewer environmental effects. · Coos; Curry; Douglas; Jackson; Josephine; Klamath; Del Norte, California; Oregon

Amend the Rogue River and Siskiyou Forest Land and Resource Management Plans by adding aminopyralid to the list of approved herbicides that may be considered for use in projects to control invasive plants.

Land management planning
Scoping Start
06/27/2015
Comment Period
02/18/2016
Objection Period Start
08/03/2016
Decision
11/2016 (Estimated)
Implementation
12/2016 (Estimated)
Project documents
Wayne Rolle · wrolle@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (16), 36 Cfr 220.6(E)(16)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation219 (2012)
Project ActivityPlan Amendment
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Powers Ranger District · updated 9/1/2016
The Elk River watershed about 5 miles southeast of Port Orford, Oregon. · Curry, Oregon

Place large wood into and adjacent to ~2 miles of stream to improve habitat for fish and other aquatic species. Thin(non-commercial)~500 acres of previously harvested and dense stands to stimulate the development of mature forest near streams.

Vegetation management (other than forest products)Wildlife, fish, rare plantsWatershed management
Scoping Start
10/2014 (Estimated)
Decision
11/2014 (Estimated)
Implementation
12/2014 (Estimated)
Project documents
Karla Cottom · kcottom@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Watershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 9/1/2016
Corridor along State HWY 140; near Latgawa Camp, Willow Lake, Propspect, and Fish Lake. · Jackson, Oregon

Renew 1 existing, expired, powerline permit for PacifiCorp, Willow Lake, Fish Lake, and Robinson Butte areas AND Renew and combined into 1 telephone line permit CenturyLink%u2019s four existing expired permits.

Special use management
Scoping Start
09/18/2015
Decision
09/2016 (Estimated)
Implementation
09/2016 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · High Cascades Ranger District · updated 8/16/2016
High Cascades Ranger District · Jackson, Oregon

Thinning of established plantations across the High Cascades Ranger District

Forest productsVegetation management (other than forest products)
Scoping Start
01/29/2007
Comment Period
11/17/2008
Decision
05/2009 (Estimated)
Implementation
05/2009 (Estimated)
Project documents
Jason Herron · jherron@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityForest Vegetation Improvements
Cascade Managed StandsDecision Signed Date: 05/11/2009
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Decision Memo · High Cascades Ranger District · updated 8/9/2016
Corridor along State Highway 140;near Latgawa Camp, Willow Lake, Prospect, and Fish Lake. · Jackson, Oregon

Operations and maintenance fiber optic telecom line. Installation of new fiber optic line (10.4 miles). 5.4 miles current utility poles will be used. For 5 miles new pole installation will take place. No new access roads are proposed.

Special use management
Scoping Start
09/18/2015
Decision
07/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · High Cascades Ranger District · updated 7/22/2016
Adjacent to State Highway 140, approximately 8 miles west of Fish Lake. · Jackson, Oregon

Allow use of 1/3 mile of maintenance level 1 NFS road and skid processed logs over 250 feet of NFS lands.

Special use management
Scoping Start
09/18/2015
Decision
07/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT 37 S., R 3 E., NE 1/4 of NE 1/4, Sec. 3, W.M.
Decision Memo · Siskiyou Mountains Ranger District · updated 10/2/2015
Approximately 6.5 miles south of Ashland, Oregon, and approximately 6 miles north of the California border. · Jackson, Oregon

Renewal of a permit for a 50-year term for an existing underground electrical distribution line near Mt. Ashland Ski Resort on USDA Forest Service lands. No new construction or ground disturbance would occur.

Special use management
Scoping Start
09/16/2014
Decision
11/2014 (Estimated)
Implementation
12/2014 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations
Mt. Ashland Special Use Permit RenewalDecision Signed Date: 11/21/2014
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT40S-R01E-Sections 16, 20, 21, and 22. Willamette Meridian.
Decision Memo · Gold Beach Ranger District · updated 10/2/2015
Forest Service roads from Galice to Foster Bar on the Rogue River, and FS Road 1376 along the Chetco River. · Curry, Oregon

Proposed issuance of up to 15 special use permits for shuttling of people and cars from Galice to Foster Bar on the Rogue River via several routes and for shuttles along FS Road 1376 along the Chetco River.

Special use managementRecreation management
Scoping Start
04/01/2015
Decision
05/2015 (Estimated)
Implementation
05/2015 (Estimated)
Project documents
Bob Hemus · bhemus@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDispersed Recreation Mgmt.; Special Area Management; Wilderness Management
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · High Cascades Ranger District · updated 10/1/2015
Union Creek Campground, Farewell Bend Campground, and USFS Administrative Compound at Union Creek · Jackson, Oregon

The project would address several deferred maintenance items to the Union Creek Water System, including: replacement of the waterline, replacement of components at the Union Creek and Farewell Bend campgrounds, and the USFS Administrative Compound.

Recreation management
Scoping Start
08/01/2015
Decision
10/2015 (Estimated)
Implementation
03/2016 (Estimated)
Project documents
Leslie Moscoso · lmoscoso@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management
Decision Decided Date10/01/2015
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land Descriptionsec. 34 and 35, Township 30 South, Range 3 East, of the Willamette Meridian
Environmental Assessment · Siskiyou Mountains Ranger District · updated 8/12/2015
Elliott Creek, approximatley 10 miles south of Oregon/California border · Siskiyou, California

Placer mine, removing mineral deposit from an ancient channel (underground). Project would remove approximately 40 cubic yards of material per year. Removal process would primarily pick and shovel, using a winch to move material mid-slope.

Minerals and geology
Scoping Start
07/2012 (Estimated)
Comment Period
12/2012 (Estimated)
Decision
01/2013 (Estimated)
Implementation
03/2013 (Estimated)
Project documents
Karla Gallegos · kgallegos@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityMinerals Or Geology Plans Of Operations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT. 48 N., R. 10 W., Section 22, SW 1/4, Mt. Diablo Meridian, Siskiyou County, California
Decision Memo · Gold Beach Ranger District · updated 8/11/2015
East of Brookings, Oregon, on the Chetco River within US Forest Service lands. · Curry, Oregon

Re-issuance of 26 special-use permits for outfitting and guiding on the Chetco River.

Special use managementRecreation management
Scoping Start
03/01/2015
Decision
06/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
Bob Hemus · bhemus@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDispersed Recreation Mgmt.; Special Area Management; Wilderness Management
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Wild Rivers Ranger District · updated 8/10/2015
Wild Rivers Ranger District · Curry; Josephine; Del Norte, California; Oregon

Restoration of aquatic ecosystems and water quality across the Wild Rivers RD.

Wildlife, fish, rare plantsWatershed management
Scoping Start
04/2012 (Estimated)
Decision
07/2012 (Estimated)
Implementation
09/2012 (Estimated)
Project documents
Ian Reid · ireid@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Watershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Environmental Assessment · High Cascades Ranger District · updated 2/25/2015
Stands adjacent to Hwy 62 between Prospect and Union Cr, and adjacent to Hwy 230 from its junction with Hwy 62 up approx 5 miles. · Jackson, Oregon

Apply recommended stand density reduction thinning to ponderosa pine dominated stands to sustain large ponderosa and sugar pine trees, increase stand vigor, and promote pine regeneration.

Vegetation management (other than forest products)
Scoping Start
04/01/2010
Comment Period
08/2015 (Estimated)
Decision
09/2015 (Estimated)
Implementation
09/2015 (Estimated)
Project documents
Craig Davis · cddavis@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityTimber Sales (Green)
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT. 32 S., R. 3 E., Sec. 4,5,8,9,16,17,20,29. T. 31 S., R. 3 E., Sec. 3,10,15,16,21,28,29,32. T. 30 S., R. 3 E., Sec. 13,24,25,26,35. T. 30 S., R. 4 E., Sec. 6,7,18
Decision Memo · Siskiyou Mountains Ranger District · updated 12/23/2014
Upper Applegate 5th field watershed · Jackson, Oregon

Precommercial thinning and fuels treatments on 55 acres of the 25-year-old Strongarm Plantation consisting of mixed conifer and hardwoods which range from 1 to 12 inches in diameter, with a focus on pine/oak restoration.

Vegetation management (other than forest products)
Scoping Start
05/15/2009
Decision
09/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
Michael Hackett · mmhackett@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements
Strongarm Pine Thinning and RestorationDecision Signed Date: 09/28/2012 Legal Notice Date: 09/28/2012
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land Descriptionsec. 2, T. 40 S., R. 3 W., of the Willamette Meridian
Environmental Assessment · Wild Rivers Ranger District · updated 12/23/2014
Section of Sucker Creek, approximately 1 mile upstream of Grayback Campground. · Josephine, Oregon

Reconstruction of portions of the Sucker Cr mainstem channel, placement of large wood structures, est. of riparian forest community, and tree acquisition for large wood structures.

Watershed management
Scoping Start
02/10/2010
Comment Period
02/10/2010
Decision
06/2010 (Estimated)
Implementation
09/2010 (Estimated)
Project documents
Chris Park · cpark@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT. 39 S., R. 6 W., Sec 5, 31; T. 39 S., R. 7 W., Sec. 36; T. 41 S., R. 8 W., Sec. 15
Briggs Valley Cancelled
Environmental Assessment · Wild Rivers Ranger District · updated 12/17/2014
Upper Briggs Valley Watershed · Josephine, Oregon

Partial cut exisiting stands to promote large-diameter trees and maintain pine-oak habitat on approximately 985 acres;no regen harvest or new system road construction; objective is to increase vigor and growth of mid-seral stands.

Forest productsVegetation management (other than forest products)
Scoping Start
11/2014 (Estimated)
Comment Period
06/2015 (Estimated)
Project documents
Don Bellville · dbellville@fs.fed.us
NEPA / regulatory detail
Notice and Comment Regulation219 (2012)
Project ActivityTimber Sales (Green)
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT36S, R8W including General Forest, Partial Retention, and Special Wildlife Areas (meadows)
Environmental Impact Statement · Powers Ranger District · updated 9/22/2014
Approximately four (4) air miles southeast of the city of Powers, Oregon within the area known as Eden Ridge. · Coos, Oregon

Commercial thinning, root disease treatments and planting on approx. 3,736 acres of candidate stands regenerated in the 1920s-40s and located on Matrix under NWFP. Includes 72 treatment units using ground-based and aerial logging systems.

Forest productsVegetation management (other than forest products)
NOI in Federal Register
04/26/2010
DEIS NOA in Federal Register
03/30/2012
FEIS NOA in Federal Register
03/20/2014
Objection Period Start
03/20/2014
Decision
09/2014 (Estimated)
Implementation
10/2014 (Estimated)
Project documents
Wesley Crum · whcrum@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Forest Vegetation Improvements; Road Maintenance; Road Improvements/Construction; Timber Sales (Green)
Eden Ridge Timber Sales Record of DecisionDecision Signed Date: 09/17/2014
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionT. 31 S., R. 10 W., Sec. 9, 15, 16, 17, 18, 19, 20, 21, 29, and 30; T. 31 S., R. 11 W., Sec. 24, 25, 26, and 27, W.M.
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 6/18/2014
Approximately 3 miles southwest of Selma, OR · Josephine, Oregon

Construct 150ft tower (19x19 ft base) and ice bridge connecting new tower to communications shelter; utilize 2 previously disturbed staging areas; replace 93 ft of an existing underground electric distribution line; coverage for 5 existing lines.

Special use management
Scoping Start
09/16/2013
Decision
04/2014 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
Gary Einck · geinck@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Special Use Authorizations; Facility Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land Descriptionsec. 17, Township 38 South, Range 8 West, of the Willamette Meridian
Decision Memo · Siskiyou Mountains Ranger District · updated 10/22/2013
Siskiyou Mountains Ranger District · Jackson, Oregon

Restoration of aquatic ecosystems and water quality across the Siskiyou Mountains RD.

Watershed managementWildlife, fish, rare plants
Scoping Start
02/16/2012
Comment Period
08/03/2012
Decision
09/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
Ian Reid · ireid@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecies Habitat Improvements; Watershed Improvements
Siskiyou Mountains Aquatic Restoration Decision MemoDecision Signed Date: 09/28/2012 Legal Notice Date: 09/28/2012
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land Descriptionsec. 4, 5, 7, 8, 18, 19, 30, T. 40 S., R. 3 W.; sec. 28, T. 39 S., R. 3 W., of the Willamette Meridian
Environmental Assessment · High Cascades Ranger District · updated 9/20/2013
Approx. west of Crater Lake NP, east of Hwy. 230, north of Hwy. 62, and south of FS Road 6535900 · Jackson, Oregon

This project is designed to improve stand conditions, diversity, density, and structure to increase forest resiliency and overall forest health; provide a sustainable supply of timber products; and reduce the risk to forest resources from wildfire.

Vegetation management (other than forest products)Forest productsFuels management
Scoping Start
04/15/2010
Comment Period
01/29/2013
Decision
09/2013 (Estimated)
Implementation
01/2014 (Estimated)
Project documents
Sasha Fertig · sashafertig@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Noxious Weed Treatments; Road Maintenance; Timber Sales (Green)
Bybee Vegetation Management ProjectDecision Signed Date: 09/17/2013 Legal Notice Date: 09/20/2013
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT. 30 S., R. 3 E., Sec. 13, 24, 25, 26, 35, and 36; T. 30 S., R. 4 E., Sec. 7-30 and 33-36; T. 30 S., R. 5 E., Sec. 7 and 18; and T. 31 S., R. 4 E., Sec. 1 and 2, Willamette Meridian
Decision Memo · Wild Rivers Ranger District · updated 9/16/2013
Along Josephine Creek, about 3.5 miles from Josephine Campground · Josephine, Oregon

Placer mining Plan of Operations for exploration and sampling.

Minerals and geology
Scoping Start
10/06/2011
Comment Period
10/10/2012
Decision
09/2013 (Estimated)
Implementation
10/2013 (Estimated)
Project documents
Robert Shoemaker · rshoemaker@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (8), 36 Cfr 220.6(E)(8)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityMinerals Or Geology Plans Of Operations
Governor Davis Mining Decision MemoDecision Signed Date: 09/11/2013 Legal Notice Date: 09/15/2013
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT. 38 S., R. 8 W., Sections 30 and 31
Environmental Assessment · Gold Beach Ranger District · updated 3/20/2013
Near Brookings, Curry County, Oregon. Forest Service lands in Chetco Wild & Scenic River designation, downstream from the Kalmiopsis Wilderness. · Curry, Oregon

Request the Secretary of the Interior withdraw from location and entry under mining laws about 5,610 acres of FS land within the Chetco Wild and Scenic River, subject to valid existing rights, for a period of 5 years in aid of legislation.

Minerals and geologySpecial use managementWildlife, fish, rare plantsRecreation managementSpecial area management
Scoping Start
05/03/2012
Comment Period
12/06/2012
Decision
01/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
Holly Witt · hfwitt@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityLand Use Adjustments; Special Area Management
FONSI for Chetco Wild and Scenic River Mineral Withdrawal EADecision Signed Date: 01/25/2013
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionT. 38 S., R. 11 W., secs. 5-7, 18; T. 38 S., R. 12 W., secs. 9-16, 21, 27-29, 32-33; T. 39 S., R. 12 W., secs. 4, 5, 8, 9, 16, 17, 20, 29, 30, 31.
Decision Memo · Gold Beach Ranger District · updated 3/11/2013
Hike Chetco Pass to junction of Chetco River & Slide Cr. Kayak Chetco River to T38S, R12W, Sec. 28 or 11. · Curry, Oregon

Commercially guided kayaking trips on the Wild & Scenic Chetco River and through the Kalmiopsis Wilderness. Trips are up to 12 people for 5 days and 1-4 trips per year between June and Sept. No pack animals & leave-no-trace ethics apply.

Special use managementRecreation management
Scoping Start
05/14/2012
Comment Period
01/09/2013
Decision
03/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
Nancy Schwieger · nschwieger@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDispersed Recreation Mgmt.; Special Area Management; Wilderness Management
Chetco River Kayaking Permit Decision MemoDecision Signed Date: 03/01/2013 Legal Notice Date: 03/06/2013
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionFrom T38S, R10W, Sec. 12 to T38S, R12W, Sec. 28
Environmental Assessment · Powers Ranger District · updated 1/31/2013
Copper Salmon Wilderness: Approximately 12 miles east of Port Orford, Oregon in Curry and Coos Counties. · Coos; Curry, Oregon

Decommission or convert to hiking trails up to 16 miles of existing roads within the wilderness. Identify locations for future hiking trails. Relocate gravel stockpiled in the wilderness to outside of the wilderness.

Special area managementRecreation managementWildlife, fish, rare plantsRoad management
Scoping Start
01/28/2011
Comment Period
08/29/2012
Decision
12/2012 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
Holly Witt · hfwitt@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Species Habitat Improvements; Trail Management; Watershed Improvements; Wilderness Management
Copper Salmon Wilderness Legacy Roads Project Decision Notice and FONSIDecision Signed Date: 12/11/2012 Legal Notice Date: 12/18/2012
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionTownships 22 & 23 south; Ranges 12 & 13 west; Willamette Meridian
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 11/13/2012
Parcel of National Forest land on E. side of Laurel Ave. between South St. and Butte Falls Fish Lake Rd. Street Address: 705 Laurel Ave. · Jackson, Oregon

Sale of the property under the Forest Service Facility Realignment and Enhancement Act of 2005 (P.L. 109-54).

Facility management
Scoping Start
07/28/2010
Decision
03/2012 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
Jon Hall · jehall02@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (7), 36 Cfr 220.6(D)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Maintenance
Administrative Site Disposal Butte Falls District RangerDecision Signed Date: 03/30/2012
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionS ½ NE ¼ of Section 10, T. 35 S., R. 2 E.
Environmental Impact Statement · Gold Beach Ranger District · updated 8/28/2012
Chetco River, +/- River Mile 39 · Curry, Oregon

Environmental review of a Proposed Plan of Operations for placer mining up to 71 acres along the main stem of the Chetco River.

Minerals and geology
NOI in Federal Register
03/2011 (Estimated)
DEIS NOA in Federal Register
03/2012 (Estimated)
FEIS NOA in Federal Register
10/2012 (Estimated)
Decision
08/2012 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
Kevin Johnson · kljohnson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityMinerals Or Geology Plans Of Operations
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionT. 38 S., R. 11 W., Sec. 2, 11
Environmental Impact Statement · WO - Washington Office - National headquarters · updated 7/10/2012
11 contiguous Western States (Arizona, California, Colorado, Idaho, Montana, New Mexico, Nevada, Oregon, Utah, Washington, and Wyoming) and Alaska. · Bonner; Aleutians East; La Paz; Columbia; Coos; Colusa; Denver; Douglas, Alaska; Arizona; California; Colorado; District of Columbia; Idaho; Kansas; Montana; North Dakota; Nebraska; New Mexico; Nevada; Oklahoma; Oregon; South Dakota; Texas; Utah; Washington; Wyoming

The Forest Service was a cooperating agency, assisting the Bureau of Land Management (BLM) in that Agency's geothermal leasing analysis and decision. The BLM issued a record of decision on 12/17/2008.

Regulations, directives, orders
NOI in Federal Register
06/13/2007
DEIS NOA in Federal Register
06/13/2008
FEIS NOA in Federal Register
10/24/2008
Decision
02/2010 (Estimated)
Implementation
03/2010 (Estimated)
Project documents
Tracy Parker · tparker03@fs.fed.us
NEPA / regulatory detail
Special AuthorityNepa Document Prepared By Another Federal Agency
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRegulation Creation/Modification
ForestsBeaverhead-Deerlodge National Forest; Bitterroot National Forest; Clearwater National Forest; Custer National Forest; Custer Gallatin National Forest; Helena National Forest; Lewis And Clark National Forest; Lolo National Forest; Nez Perce-Clearwater National Forest; Grand Mesa, Uncompahgre and Gunnison National Forests; Medicine Bow-Routt National Forest; Rio Grande National Forest; Arapaho and Roosevelt National Forests; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands; San Juan National Forest; White River National Forest; Apache-Sitgreaves National Forests; Carson National Forest; Cibola National Forest; Coronado National Forest; Gila National Forest; Lincoln National Forest; Santa Fe National Forest; Tonto National Forest; Boise National Forest; Bridger-Teton National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Payette National Forest; Salmon-Challis National Forest; Sawtooth National Forest; Caribou-Targhee National Forest; Humboldt-Toiyabe National Forest; Uinta-Wasatch-Cache National Forest; Angeles National Forest; Cleveland National Forest; Eldorado National Forest; Inyo National Forest; Klamath National Forest; Lassen National Forest; Los Padres National Forest; Mendocino National Forest; Modoc National Forest; Plumas National Forest; San Bernardino National Forest; Sequoia National Forest; Shasta Trinity National Forest; Sierra National Forest; Tahoe National Forest; Deschutes National Forest; Fremont-Winema National Forest; Gifford Pinchot National Forest; Malheur National Forest; Mt Baker-Snoqualmie National Forest; Mt. Hood National Forest; Ochoco National Forest; Rogue River-Siskiyou National Forest; Umatilla National Forest; Umpqua National Forest; Wallowa-Whitman National Forest; Okanogan-Wenatchee National Forest; Willamette National Forest; R10 - Alaska Region All Units; WO - Washington Office - National headquarters
DistrictsBeaverhead-Deerlodge National Forest All Units; Bitterroot National Forest All Units; Clearwater National Forest All Units; Custer National Forest All Units; Custer Gallatin National Forest; Custer Gallatin National Forest All Units; Helena National Forest All Units; Lewis And Clark National Forest All Units; Lolo National Forest All Units; Nez Perce-Clearwater National Forest All Units; Grand Mesa Uncompahgre and Gunnison National Forest All Units; Medicine Bow-Routt National Forest All Units; Rio Grande National Forest All Units; Arapaho and Roosevelt National Forests All Units; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands All Units; San Juan National Forest All Units; White River National Forest All Units; Apache-Sitgreaves National Forests All Units; Carson National Forest All Units; Cibola National Forest All Units; Coronado National Forest All Units; Gila National Forest All Units; Lincoln National Forest All Units; Santa Fe National Forest All Units; Tonto National Forest All Units; Boise National Forest All Units; Bridger-Teton National Forest All Units; Dixie National Forest All Units; Fishlake National Forest All Units; Manti-La Sal National Forest All Units; Payette National Forest All Units; Salmon-Challis National Forest All Units; Sawtooth National Forest All Units; Caribou-Targhee National Forest All Units; Humboldt-Toiyabe National Forest All Units; Uinta-Wasatch-Cache All Units; Angeles National Forest All Units; Cleveland National Forest All Units; Eldorado National Forest All Units; Inyo National Forest All Units; Klamath National Forest All Units; Lassen National Forest All Units; Los Padres National Forest All Units; Mendocino National Forest All Units; Modoc National Forest All Units; Plumas National Forest All Units; San Bernardino National Forest All Units; Sequoia National Forest All Units; Shasta Trinity National Forest All Units; Sierra National Forest All Units; Tahoe National Forest All Units; Deschutes National Forest All Units; Fremont-Winema National Forest All Units; Gifford Pinchot National Forest All Units; Malheur National Forest All Units; Mt Baker-Snoqualmie National Forest All Units; Mt. Hood National Forest All Units; Ochoco National Forest All Units; Rogue River-Siskiyou National Forest All Units; Umatilla National Forest All Units; Umpqua National Forest All Units; Wallowa-Whitman National Forest All Units; Okanogan-Wenatchee National Forest All Units; Willamette National Forest All Units; R10 - Alaska Region All Units; WO - Washington Office - National headquarters
Environmental Assessment · Gold Beach Ranger District · updated 4/18/2012
Within the area known as Wildhorse Ridge. Located in the Illinois River-Lawson Creek, Lower Roque River, and Pistol River 5th field watersheds. · Curry, Oregon

Commercially thin approximately 600 acres of natural stands less than 110 years of age that are located within lands designated as matrix and riparian reserve.

Forest productsVegetation management (other than forest products)
Scoping Start
10/20/2010
Comment Period
02/08/2012
Decision
04/2012 (Estimated)
Implementation
08/2012 (Estimated)
Project documents
David Zimmerman · dlzimmerman@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityForest Vegetation Improvements; Noxious Weed Treatments; Road Maintenance; Timber Sales (Green)
Equine Thin Project - Decision Notice and Finding of No Significant ImpactDecision Signed Date: 04/13/2012 Legal Notice Date: 04/18/2012
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionT36S; R12 W; sec 7 and 18; T36S; R121/2W; sec 13, 25 and 36;T37S; R121/2W; sec 1; T36S; R13W; sec 35 and 36; T37 S; R13W; sec 1, 2 and 3; WM
Decision Memo · Gold Beach Ranger District · updated 4/13/2012
Salvage of blowdown in two areas: Too Wild (vicinity of FSR 3318/3680) and Indigo (vicinity of FSR 2308). · Curry, Oregon

Planned removal of blowdown material over approximately 235 acres.

Forest products
Scoping Start
08/13/2008
Decision
05/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
David Zimmerman · dlzimmerman@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (13), 36 Cfr 220.6(E)(13)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTimber Sales (Salvage)
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionT36S, R12W, section 7, 8, 18, 19 and 30; T36S, R121/2W, section 24, 25 and 36; T35S, R101/2W, section 18, 19 and 30; and T35S, R11W, sections 13 and 25.
Decision Memo · Gold Beach Ranger District · updated 4/13/2012
Accessed via NFS 3318-000 road. On Wildhorse Ridge in the Rogue River watershed, Curry County, Oregon. T36S, R12W, Section 7. · Curry, Oregon

Install a self-contained vault toilet near the Wildhorse Lookout site in Curry County, Oregon, T36S, R12W, Section 7. Building will be historically appropriate to match Lookout structures.

Recreation management
Scoping Start
04/18/2011
Decision
01/2012 (Estimated)
Implementation
06/2012 (Estimated)
Project documents
Holly Witt · hfwitt@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
Wildhorse Toilet Installation - Decision MemoDecision Signed Date: 01/29/2012
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionTownship 36 South; Range 12 West; Section 07; Willamette Meridian, Curry County, Oregon
Decision Memo · Siskiyou Mountains Ranger District · updated 4/4/2012
1 mile up an unnamed skid road from Thompson/Carberry Creek Road · Josephine, Oregon

Environmental review of a Proposed Plan of Operations for developing a mining adit.

Minerals and geology
Scoping Start
10/03/2011
Decision
12/2011 (Estimated)
Implementation
01/2012 (Estimated)
Project documents
Karla Gallegos · kgallegos@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
Skat Mining OperationsDecision Signed Date: 12/08/2011
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT. 40 S., R 4 W, Sec. 18
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 2/15/2012
Forest-wide · Coos; Curry; Douglas; Jackson; Josephine; Klamath; Del Norte; Siskiyou, California; Oregon

Project would provide NEPA analysis of various aquatic restoration activities that are contained within the existing Aquatic Restoration Biological Opinion (ARBO).

Wildlife, fish, rare plants
Scoping Start
01/2011 (Estimated)
Comment Period
04/2011 (Estimated)
Decision
05/2011 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
Steven Brazier · sbrazier@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecies Habitat Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionForest-wide
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 1/31/2012
Includes High Cascades, Siskiyou Mountains and Wild Rivers Ranger Districts · Coos; Curry; Douglas; Jackson; Josephine; Klamath; Del Norte; Siskiyou, California; Oregon

Treatment of meadows through fire and cutting to remove or girdle encroaching trees

Watershed managementVegetation management (other than forest products)
Scoping Start
06/11/2009
Comment Period
11/2012 (Estimated)
Decision
01/2012 (Estimated)
Implementation
02/2012 (Estimated)
Project documents
Wayne Rolle · wrolle@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecies Habitat Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District; Wild Rivers Ranger District; High Cascades Ranger District
Legal Land Descriptionforest-wide
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 1/31/2012
National forest sytem lands in Coos and Curry Counties, Oregon · Coos; Curry, Oregon

Proposal to use any of four herbicides to control invasive plants on approximately 95 acres within the Gold Beach and Powers Ranger Districts.

Vegetation management (other than forest products)
Scoping Start
10/01/2007
Comment Period
01/15/2008
Decision
08/2009 (Estimated)
Implementation
10/2009 (Estimated)
Project documents
Wayne Rolle · wrolle@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityNoxious Weed Treatments
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District; Powers Ranger District
Legal Land DescriptionNational forest sytem lands in Coos and Curry Counties, Oregon
Environmental Impact Statement · Rogue River-Siskiyou National Forest All Units · updated 1/31/2012
Upper Bear; Late Successional Reserve · Jackson, Oregon

Authorization under Special Use Permit per recommendations of Master Plan Record of Decision

Facility managementSpecial use management
NOI in Federal Register
04/01/2002
DEIS NOA in Federal Register
07/25/2003
FEIS NOA in Federal Register
09/2004 (Estimated)
Decision
09/2004 (Estimated)
Implementation
05/2005 (Estimated)
Project documents
Steven Johnson · srjohnson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT 40 S, R 01 E, WM
Decision Memo · Wild Rivers Ranger District · updated 1/31/2012
Waters Creek and Round Prairie Creek watersheds · Josephine, Oregon

Reduction of understory (non-commercial) vegetation (shrubs and small trees) in natural and managed conifer stands using mechanical slashing treatments and underburning.

Vegetation management (other than forest products)Fuels management
Scoping Start
01/10/2005
Comment Period
08/01/2006
Decision
12/2006 (Estimated)
Implementation
04/2007 (Estimated)
Project documents
Don Bellville · dbellville@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (10)
Special AuthorityNational Fire Plan - Healthy Forests Initiative Ce
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels)
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT 36 S; R 07 W; Sec. 28, 29, 30, 31, 32, and 33; W.M.
Decision Memo · Wild Rivers Ranger District · updated 1/19/2012
Eight Dollar Mtn: off HWY 199 near Selma. Onion Mtn: off HWY 199 near Grants Pass. Bolan Pk: off FS Road 48 near Cave Junction. Fiddler Mtn: off HWY 199 near Selma and west of Eight Dollar Mtn · Josephine, Oregon

Renewal of seven existing special use authorization leases for communication uses on Eight Dollar Mountain, Onion Mountain, Bolan Peak, and Fiddler Mountain.

Special use management
Scoping Start
08/01/2011
Decision
01/2012 (Estimated)
Implementation
01/2012 (Estimated)
Project documents
David Krantz · dkrantz@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Comm Sites SUP Lease Renewals and Lease Amendment on the WRRDDecision Signed Date: 01/18/2012
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT. 38 S., R. 8 W., Sec. 20;T. 36 S., R. 8 W., Sec. 11;T. 41 S., R. 6 W., Sec. 7; T. 38 S., R. 9 W., Sec 28
Decision Memo · High Cascades Ranger District · updated 12/21/2011
Hall Point is located off HWY 62 near Prospect. Robinson Butte is located off HWY 140 near Fish Lake. Rustler Peak is located off Forest Road 32 near Parker Meadows Campground. · Jackson, Oregon

Renewal of four existing special use authorization leases for communication uses on Robinson Butte, Halls Point, and Rustler Peak.

Special use management
Scoping Start
07/01/2011
Decision
11/2011 (Estimated)
Implementation
11/2011 (Estimated)
Project documents
David Krantz · dkrantz@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Robinson Butte, Rustler Peak, and Halls Point Comm. Lease SUP RenewalsDecision Signed Date: 11/01/2011
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT. 37 S., R. 4 E., Sec. 8;T. 32 S., R. 2 E., Sec. 11; T. 34 S., R. 4 E., Sec. 16
BB#3 Placer Mine Completed
Decision Memo · Wild Rivers Ranger District · updated 12/7/2011
Approximately 5 air miles northwest of Cave Junction, Oregon. · Josephine, Oregon

Sampling 3 sites by digging out existing ponds then processing and testing the materials on site, on a project footprint <1 acre.

Minerals and geology
Scoping Start
04/02/2011
Decision
12/2011 (Estimated)
Implementation
02/2012 (Estimated)
Project documents
Karla Gallegos · kgallegos@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (8), 36 Cfr 220.6(E)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
BB#3 Placer Mining OperationsDecision Signed Date: 12/06/2011
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionSection 36, T. 38 S., R. 9 W., Willamette Meridian, Josephine County, Oregon
Decision Memo · Wild Rivers Ranger District · updated 12/7/2011
Approximately 13 air miles SE of Cave Junction, Oregon · Josephine, Oregon

Placer mining and lode mining within Johnson and Silver Gulches and other unnamed smaller tributaries using a suction dredge.

Minerals and geology
Scoping Start
04/02/2011
Decision
11/2011 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
Karla Gallegos · kgallegos@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (8), 36 Cfr 220.6(E)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT. 41 S., R. 7 W., Sec. 10 and 15, W.M.
Decision Memo · Wild Rivers Ranger District · updated 12/7/2011
Near Run Creek on the Wild Rivers Ranger District · Josephine, Oregon

Plan of Operations for a placer mine.

Minerals and geology
Scoping Start
04/02/2011
Decision
11/2011 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
Karla Gallegos · kgallegos@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (8), 36 Cfr 220.6(E)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
Runwet Placer Mining OperationsDecision Signed Date: 11/18/2011
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT. 40 S., R. 7 W., Sec. 26
Decision Memo · Gold Beach Ranger District · updated 9/26/2011
Gold Beach Ranger District · Curry, Oregon

Habitat restoration activities in 14 strategic fire buffer areas totaling 592 acres and 8 adjoining meadow, savannah, and oak woodland areas totaling 503 acres.

Fuels managementVegetation management (other than forest products)
Scoping Start
11/19/2010
Decision
05/2011 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
Jessie Dubuque · jdubuque@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
The LRIVS 2010 Meadow Restoration & Fuels Treatments ProjectDecision Signed Date: 05/13/2011
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land DescriptionT34S, R11W, Sec. 5, 6, 7, 8, 18, 19, 30, 31; T34S, R12W, Sec. 24, 25, 26; T35S, R11W, Sec. 5, 6, 7, 18, 19, 20, 28, 29, 32; T35S, R12W, Sec. 11, 12, 13, 14
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 9/9/2011
National Forest land situated above the right (north) bank of the Rogue River, just W. of Curry County Road 375. · Curry, Oregon

Sale of the property under the Forest Service Facility Realignment and Enhancement Act of 2005 (P.L. 109-54).

Facility management
Scoping Start
08/04/2010
Decision
09/2011 (Estimated)
Implementation
10/2011 (Estimated)
Project documents
Jon Hall · jehall02@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (7), 36 Cfr 220.6(D)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Maintenance
Administrative Site Disposal Old Agness Guard Station CompoundDecision Signed Date: 09/09/2011
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionSW ¼, Sec. 7, T. 35 S., R. 11 W.
Decision Memo · High Cascades Ranger District · updated 9/7/2011
Aspen stands located on the High Cascades Ranger District · Jackson, Oregon

Vegetation management treatments designed to maintain and restore health and vigor of aspen stands. Does not include commercial timber harvest.

Vegetation management (other than forest products)
Scoping Start
05/05/2009
Decision
08/2011 (Estimated)
Implementation
09/2011 (Estimated)
Project documents
Wayne Rolle · wrolle@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements; Species Population Enhancements
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT30S, R4W, Sec. 28 and 30; T31S, R4E, Sec. 12; T32S, R3E, Sec. 1; T32S, R4E, Sec. 7; T33S, R4E, Sec. 8; T35S, R4E, Sec. 10 and 11; and T37S, R4E, Sec. 9, 16, and 32, W.M.
Decision Memo · Wild Rivers Ranger District · updated 8/18/2011
National Forest land on N. side of “L” Street, bounded by Judson St. on E., “J” St. on N., and lot line boundary with private property on W. Street address: 1012 SW L St. · Josephine, Oregon

Sale of the property under the Forest Service Facility Realignment and Enhancement Act of 2005 (P.L. 109-54).

Facility management
Scoping Start
04/18/2007
Comment Period
09/09/2010
Decision
08/2011 (Estimated)
Implementation
12/2010 (Estimated)
Project documents
Jon Hall · jehall02@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (7), 36 Cfr 220.6(D)(7)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFacility Maintenance
Site Disposal of "L" Street Compound in Grants PassDecision Signed Date: 08/18/2011
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionS ½ of Section 18, T. 36 S., R. 5 W.
Environmental Assessment · Wild Rivers Ranger District · updated 8/4/2011
Butcherknife Creek and Slate Creek area; Applegate AMA; near Wonder/Wilderville, OR · Josephine, Oregon

Treatment of approximately 5,000 acres of forest stands to reduce density of stems, decrease vegetative fuels and increase stand vitality.

Fuels managementForest productsWildlife, fish, rare plantsVegetation management (other than forest products)Watershed management
Scoping Start
12/12/2007
Objection Period Start
03/13/2009
Decision
09/2009 (Estimated)
Implementation
10/2009 (Estimated)
Project documents
Don Bellville · dbellville@fs.fed.us
NEPA / regulatory detail
Special AuthorityHfra Title I: Wildland-Urban Interface
Notice and Comment Regulation218
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Timber Sales (Green)
Butcherknife Slate Hazardous Fuel Reduction ProjectDecision Signed Date: 09/10/2009
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT.36S, R.8W.; T.37S., R.8W.; WM
Environmental Impact Statement · Wild Rivers Ranger District · updated 6/22/2011
Sucker Creek; Riparian Reserve, Late Successional Reserve · Josephine, Oregon

Environmental review of proposed Plan of Operations for placer mining <5 acres in the Sucker Creek watershed.

Minerals and geology
NOI in Federal Register
04/21/2006
DEIS NOA in Federal Register
03/20/2009
FEIS NOA in Federal Register
07/2009 (Estimated)
Decision
09/2009 (Estimated)
Implementation
09/2009 (Estimated)
Project documents
David Krantz · dkrantz@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityMinerals Or Geology Plans Of Operations
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT 40 S, R 06 W, Section 19
Environmental Impact Statement · High Cascades Ranger District · updated 6/7/2011
Big Butte watershed; matrix/Managed Watershed · Jackson, Oregon

Multiple commercial timber sales and other actions to address ecosystem objectives

Road managementForest productsVegetation management (other than forest products)Wildlife, fish, rare plantsFuels management
NOI in Federal Register
04/12/2004
DEIS NOA in Federal Register
03/18/2005
FEIS NOA in Federal Register
12/23/2005
Decision
11/2005 (Estimated)
Implementation
07/2006 (Estimated)
Project documents
James Fiorelli · jfiorelli@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Special Products Sales; Road Improvements/Construction; Timber Sales (Salvage); Timber Sales (Green)
Big Butte Springs Timber Sa;esDecision Signed Date: 11/30/2005 Legal Notice Date: 12/29/2005
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionT 35-36 S, R 3-4 E., WM
Environmental Assessment · Siskiyou Mountains Ranger District · updated 6/7/2011
Upper Applegate/Upper Illinois · Jackson; Josephine, Oregon

An allotment management plan update for the Big Grayback C&H Allotment.

Grazing management
Scoping Start
09/24/2003
Comment Period
10/04/2007
Decision
09/2005 (Estimated)
Implementation
04/2008 (Estimated)
Project documents
Mark Hocken · mhocken@fs.fed.us
NEPA / regulatory detail
Special AuthorityGrazing, Rescissions Act Of 1995
Notice and Comment Regulation215
Project ActivityGrazing Allotment Management; Grazing Authorizations
Big Grayback Allotment Management Plan UpdateDecision Signed Date: 02/22/2008 (FS Withdrawn) Legal Notice Date: 03/01/2008
Big Grayback Allotment Management Plan Update I (FY06)Decision Signed Date: 09/30/2005 Legal Notice Date: 10/17/2005
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District; Wild Rivers Ranger District
Legal Land DescriptionT39S, R6W; T40S R4,5&6W; T41S, R5W WM
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 6/7/2011
Siskiyou National Forest - Matrix, LSR, Riparian Reserves · Coos; Curry; Josephine, Oregon

Thinning of established plantations across Chetco, Gold Beach and Powers Districts.

Fuels managementForest products
Scoping Start
05/11/2005
Comment Period
12/27/2006
Decision
05/2007 (Estimated)
Implementation
05/2007 (Estimated)
Project documents
David Zimmerman · dlzimmerman@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityForest Vegetation Improvements; Timber Sales (Green)
Coastal Healthy Forest TreatmentsDecision Signed Date: 05/25/2007 Legal Notice Date: 05/30/2007
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Fire Use Amendment Completed
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 6/7/2011
Forest-wide · Coos; Curry; Jackson; Josephine; Klamath; Del Norte; Siskiyou, California; Oregon

An administrative action involving the modification of wording for management direction and S&Gs regarding management response to fires, including refinement of S&Gs, removal of limitations on responses and clarifications of language.

Fuels management
Scoping Start
02/26/2008
Comment Period
03/05/2008
Objection Period Start
10/30/2009
Decision
10/2010 (Estimated)
Implementation
11/2010 (Estimated)
Project documents
Robert Budge · rbudge@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation219 (2005)
Project ActivityPlan Amendment
Fire AmendmentDecision Signed Date: 10/22/2010 Legal Notice Date: 10/29/2010
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Environmental Assessment · Gold Beach Ranger District · updated 6/7/2011
Several sites on the Gold Beach and Powers Ranger Districts that will be determined during scoping. · Coos; Curry, Oregon

Herbicide treatment through cut and paint and wiping methods on specific high priority sites that have proven impossible to treat by other more standard means. The project proposes to use the most environmentally safe herbicides on the market.

Vegetation management (other than forest products)
Scoping Start
01/30/2008
Comment Period
06/17/2009
Decision
08/2009 (Estimated)
Implementation
10/2009 (Estimated)
Project documents
29279 Ellensburg Ave · cemerson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityNoxious Weed Treatments
Gold Beach and Powers Ranger District Invasive Plant Treatment ProjectDecision Signed Date: 08/31/2009 Legal Notice Date: 09/09/2009
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District; Powers Ranger District
Legal Land DescriptionMany legals depending on what is determined in scoping.
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 6/7/2011
Meadows on each of the Districts of the Forest · Coos; Curry; Douglas; Jackson; Josephine, Oregon

Meadow restoration activities in 89 meadows on approx. 2,675 acres on all Districts: including 1,421 acres of conifer and brush removal, 841 acres of handpile and burning of slash, 1,869 acres of broadcast burning, and 442 acres seeding/planting veg.

Vegetation management (other than forest products)
Scoping Start
12/18/2001
Comment Period
10/08/2005
Decision
11/2005 (Estimated)
Implementation
05/2006 (Estimated)
Project documents
Wayne Rolle · wrolle@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityForest Vegetation Improvements
Meadow Restoration & EnhancementDecision Signed Date: 11/10/2005 Legal Notice Date: 11/12/2005
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Decision Memo · Powers Ranger District · updated 6/7/2011
Powers Ranger District · Curry, Oregon

Hazard tree removal with trees to be used for offsite enhancement and restoration work or sold for commercial uses.

Recreation managementRoad management
Scoping Start
12/01/2010
Decision
01/2011 (Estimated)
Implementation
02/2011 (Estimated)
Project documents
David Zimmerman · dlzimmerman@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (12), 36 Cfr 220.6(E)(12)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Road Maintenance
South Fork Coquille Roadside/Recreation Hazard Tree RemovalDecision Signed Date: 01/21/2011
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionT31S, R10W; T31S, R11W; T32S, R10W; T32S, R11W; T32S, R12W; T33S, R11W; T33S, R12W
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 6/7/2011
Upper Applegate; Adaptive Management Area/Riparian Reserve · Jackson, Oregon

Fuels reduction along Upper Applegate Road from Star Gulch to Applegate Lake Dam

Fuels managementForest products
Scoping Start
11/10/2004
Objection Period Start
05/03/2008
Decision
06/2008 (Estimated)
Implementation
07/2008 (Estimated)
Project documents
Donald Boucher · dboucher@fs.fed.us
NEPA / regulatory detail
Special AuthorityHfra Title I: Wildland-Urban Interface
Notice and Comment Regulation218
Project ActivityFuel Treatments (Non-Activity Fuels); Special Products Sales; Timber Sales (Green)
Upper Applegate Road Hazardous Fuel Reduction ProjectDecision Signed Date: 06/11/2008
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT 39 S, R 03 W, T 40 S, R 03 W, WM
Decision Memo · Siskiyou Mountains Ranger District · updated 6/6/2011
Along Applegate River between Applegate Lake and the Forest Service Boundary; north of Squaw Lakes · Jackson, Oregon

Renewal of 5 existing special use authorizations: 4 water lines with additional improvements and 1 private driveway permit.

Special use management
Scoping Start
09/01/2010
Decision
05/2011 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
David Krantz · dkrantz@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT. 40 S., R. 3 W., Sec. 5, 8, 18, and 35, Willamette Meridian
Decision Memo · Siskiyou Mountains Ranger District · updated 6/6/2011
Along Carberry Creek between Thompson Creek and confluence with Applegate Lake · Jackson, Oregon

Renewal of 5 existing special use authorizations: 4 water lines with additional improvements and 1 material storage site.

Special use management
Scoping Start
09/01/2010
Decision
05/2011 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
David Krantz · dkrantz@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT. 40 S., R. 4 W., Sec. 18, 19, 20, and 27, Willamette Meridian
Environmental Assessment · Siskiyou Mountains Ranger District · updated 6/2/2011
Applegate-McKee Bridge fifth field watershed · Jackson, Oregon

Decommissioning, stormproofing and stream crossing upgrades to legacy roads and trails located on NFS lands within the Applegate-McKee watershed.

Watershed managementRoad management
Scoping Start
05/29/2009
Comment Period
10/10/2009
Decision
12/2009 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
Griffith Berg · gqberg@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Road Maintenance; Road Improvements/Construction; Watershed Improvements
Applegate McKee Road DecommissioningDecision Signed Date: 12/18/2009 Legal Notice Date: 12/22/2009
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionTownships 39 and 40 South, Ranges 2,3, and 4 West
Decision Memo · Wild Rivers Ranger District · updated 6/2/2011
Buckhorn Ridge, southeast of Elder Mtn. along a north/south-oriented crest extending from Happy Camp Rd (south) to the Forest Bdry (north). · Josephine, Oregon

Vegetation management and prescribed burning to establish and maintain a defensible location for suppressing or stopping wildfires.

Fuels management
Scoping Start
12/31/2008
Decision
03/2010 (Estimated)
Implementation
09/2010 (Estimated)
Project documents
Don Bellville · dbellville@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels)
Buckhorn Ridge Fuel BreakDecision Signed Date: 03/10/2010
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionT40S, R7W, Sec 20, 21, 28, 29, 32 & 33, WM
Environmental Assessment · Wild Rivers Ranger District · updated 6/2/2011
Althouse Cr., E. Fk. Illinois River, W. Fk. Illinois River and Sucker Cr. watersheds. · Josephine, Oregon

Within managed stands (forest plantations), total tree numbers would be decreased through partial cutting to leave the pattern, size and species of trees needed to further stand development objectives associated with 3 land management allocations.

Forest productsVegetation management (other than forest products)
Scoping Start
03/30/2006
Comment Period
05/17/2007
Decision
08/2007 (Estimated)
Implementation
10/2007 (Estimated)
Project documents
Robert Barnhart · rdbarnhart@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityTimber Sales (Green)
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land Descriptionmany sections w/in T39S, R5W; T39S, R6W; T40S, R5W; T40S, R6W; T40S, R7W; T40S, R8W, WM
Environmental Assessment · Gold Beach Ranger District · updated 6/2/2011
Lower Chetco River and Quosatana Ck.: Matrix/Special Wildlife Site MA-9; · Curry, Oregon

Removing commercial-sized conifers that have encroached on meadows and white oak/black oak stands over the years. In vicinity of Forest Roads 1917and 3318.

Vegetation management (other than forest products)Wildlife, fish, rare plants
Scoping Start
09/14/2005
Comment Period
02/14/2007
Decision
06/2007 (Estimated)
Implementation
09/2007 (Estimated)
Project documents
David Zimmerman · dlzimmerman@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityForest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green)
Long Ridge / Sorrel Meadow Restoration ProjectDecision Signed Date: 06/18/2007 Legal Notice Date: 06/27/2007
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionT38S, R12W, Sections 23, 26, 27, 34; W.M. and T36S, R12W, sections 13,19,24; W.M.
Environmental Impact Statement · Siskiyou Mountains Ranger District · updated 6/2/2011
The Mt. Ashland Ski Area, located south of Ashland, Oregon. · Jackson, Oregon

Supplement to the Mt. Ashland Ski Area Expansion EIS.

Recreation management
NOI in Federal Register
03/11/2010
DEIS NOA in Federal Register
03/11/2010
FEIS NOA in Federal Register
05/27/2011
Decision
04/2011 (Estimated)
Implementation
08/2011 (Estimated)
Project documents
Steven Johnson · srjohnson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management
Mt. Ashland Ski Area ExpansionDecision Signed Date: 04/22/2011 Legal Notice Date: 06/01/2011
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT. 40 S, R 1 E, Sections 15, 16, 17, 20, 21, 22, W.M.
Environmental Assessment · Wild Rivers Ranger District · updated 6/2/2011
Throughout the former Siskiyou National Forest. · Coos; Curry; Josephine, Oregon

Thinning of overstocked plantations on approximately 44,000 acres to improve vigor and reduce hazardous fuels resulting from this project as well as from previous management activities.

Fuels managementVegetation management (other than forest products)
Scoping Start
12/02/2001
Comment Period
04/18/2002
Decision
06/2002 (Estimated)
Implementation
09/2002 (Estimated)
Project documents
Don Bellville · dbellville@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
Plantation Thinning and Fuels ReductionDecision Signed Date: 06/07/2002 Legal Notice Date: 06/13/2002
ForestsRogue River-Siskiyou National Forest
DistrictsWild Rivers Ranger District
Legal Land DescriptionThroughout the former Siskiyou National Forest.
Environmental Assessment · High Cascades Ranger District · updated 3/21/2011
West of Rustler Peak in the Rancheria Creek drainage · Jackson, Oregon

Vegetation management projects to provide commodities, reduce natural fueloading, and to provide for stand diversity

Fuels managementForest productsVegetation management (other than forest products)
Scoping Start
06/10/2008
Comment Period
11/30/2010
Decision
03/2011 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
James Fiorelli · jfiorelli@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Noxious Weed Treatments; Road Maintenance; Timber Sales (Green)
Rustler Vegetation Management Decision NoticeDecision Signed Date: 03/18/2011
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Decision Memo · Siskiyou Mountains Ranger District · updated 3/18/2011
Between FS Road 1050 and Elliott Creek on the Siskiyou Mountains RD. · Siskiyou, California

Restoration of Harlow Cabin and other historic elements on the site, and elimination of encroaching conifers and other unwanted vegetation into the adjacent meadow

Heritage resource management
Scoping Start
09/27/2010
Decision
03/2011 (Estimated)
Implementation
03/2011 (Estimated)
Project documents
David Knutson · dknutson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (12), 36 Cfr 220.6(E)(12)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityHeritage Resource Management
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionSection 22/23 line, T. 48 N., R. 11 W., Mt. Diablo Meridian
Decision Memo · Rogue River-Siskiyou National Forest All Units · updated 2/25/2011
Compound on E. side of Coos County Road 219, on S. edge of the town of Powers · Coos, Oregon

Sale of the property under the Forest Service Facility Realignment and Enhancement Act of 2005 (P.L. 109-54).

Facility management
Scoping Start
04/18/2007
Comment Period
04/18/2007
Decision
02/2011 (Estimated)
Implementation
03/2011 (Estimated)
Project documents
Jon Hall · jehall02@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (7), 36 Cfr 220.6(D)(7)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFacility Maintenance
Administrative Site Disposal South Powers CompoundDecision Signed Date: 02/25/2011
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionSE ¼ of Section 13, T. 31 S., R. 12 W.
Environmental Assessment · High Cascades Ranger District · updated 2/3/2011
Along the Upper Rogue River about 11 miles north of Prospect on Hwy. 62 · Jackson, Oregon

Repair and expansion of paved parking area, replacement of toilet, and refurbished interpretive trail.

Recreation management
Scoping Start
08/05/2010
Comment Period
12/14/2010
Decision
01/2011 (Estimated)
Implementation
02/2011 (Estimated)
Project documents
Eric Grim · egrim@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionNE ¼, Sec. 9, T. 31 S., R. 3 E., W.M.
Environmental Assessment · High Cascades Ranger District · updated 2/3/2011
Along the Upper Rogue River approximately 11 miles north of Prospect on Hwy. 62 · Jackson, Oregon

Repair and expand paved parking area, replacement of existing toilet, refurbished trail, and trail extension to Farewell Bend.

Recreation management
Scoping Start
08/05/2010
Comment Period
12/14/2010
Decision
01/2011 (Estimated)
Implementation
02/2011 (Estimated)
Project documents
Eric Grim · egrim@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management
ForestsRogue River-Siskiyou National Forest
DistrictsHigh Cascades Ranger District
Legal Land DescriptionSW ¼, Sec. 35, T. 30 S., R. 3 E., W.M.
Environmental Assessment · Rogue River-Siskiyou National Forest All Units · updated 11/9/2010
Pistol River; Matrix/Timber suited 1 · Curry, Oregon

Commercial thinning of natural pole stands in matrix, app. 351 acres

Forest products
Scoping Start
06/06/2007
Comment Period
06/24/2009
Decision
09/2009 (Estimated)
Implementation
11/2009 (Estimated)
Project documents
David Zimmerman · dlzimmerman@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Products Sales; Timber Sales (Green)
Pyramid Thin ProjectDecision Signed Date: 11/07/2007 (FS Withdrawn) Legal Notice Date: 11/07/2007
Pyramid Thin Project 2008Decision Signed Date: 05/05/2008 (FS Withdrawn) Legal Notice Date: 05/07/2008
Pyramid Thin Project 2009Decision Signed Date: 09/29/2009 Legal Notice Date: 10/07/2009
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District
Legal Land DescriptionT 37 S, R 13 W, s. 17, 20,29,31; T 38 S, R 13 W, s. 6. WM
Environmental Impact Statement · Rogue River-Siskiyou National Forest All Units · updated 9/14/2010
Entire Rogue River-Siskiyou National Forest · Coos; Curry; Douglas; Jackson; Josephine; Klamath; Del Norte; Siskiyou, California; Oregon

The purpose of this project is to enact the Travel Management Rule and to identify roads, trals, and areas open to motorized use.

Road managementLand management planning
NOI in Federal Register
08/26/2008
DEIS NOA in Federal Register
03/28/2009
FEIS NOA in Federal Register
01/22/2010
Decision
09/2009 (Estimated)
Implementation
12/2009 (Estimated)
Project documents
Steven Johnson · srjohnson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDispersed Recreation Mgmt.; Plan Amendment; Trail Management; Travel Management; Watershed Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsRogue River-Siskiyou National Forest All Units
Legal Land Descriptionforest-wide
Decision Memo · Siskiyou Mountains Ranger District · updated 3/27/2007
Portions of riparian reserves adjacent to Applegate River and fish-bearing tributaries (Star, Palmer, Beaver, Mule, Hanley & Pete's Camp Creeks) · Jackson, Oregon

Riparian vegetation management - thinning & blackberry removal

Vegetation management (other than forest products)Wildlife, fish, rare plants
Scoping Start
12/11/2006
Comment Period
12/11/2006
Decision
03/2007 (Estimated)
Implementation
03/2007 (Estimated)
Project documents
Ian Reid · ireid@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityForest Vegetation Improvements; Species Habitat Improvements
ForestsRogue River-Siskiyou National Forest
DistrictsSiskiyou Mountains Ranger District
Legal Land DescriptionT 39 & 40 S, R 2-4 W
Environmental Impact Statement · Rogue River-Siskiyou National Forest All Units · updated 9/28/2005
Rogue/Illinois Rivers; Congressionally Reserved/WIld River; Scenic-recreation River · Curry, Oregon

Re-issue 63 Special Use Permits for outfitter-guide operation on the Lower Rogue and Lower Illinois Rivers and for boat docks at three lodges within WIld section of Rogue Wild and Scenic River.

Special use management
NOI in Federal Register
09/04/2003
DEIS NOA in Federal Register
11/17/2004
FEIS NOA in Federal Register
04/22/2005
Decision
04/2005 (Estimated)
Implementation
05/2005 (Estimated)
Project documents
Jerry Darbyshire · jdarbyshire@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Special Use Permits for Outfitter/Guide Operations Rogue and Lower Illinois Rivers RODDecision Signed Date: 04/13/2005 Legal Notice Date: 04/20/2005
ForestsRogue River-Siskiyou National Forest
DistrictsGold Beach Ranger District