Environmental Assessment Completed

Mount Avery Spur Road Project

Rogue River-Siskiyou National Forest Curry, Oregon Powers Ranger District

Construct about 330 feet of new road on Forest Service lands from the end of Forest Service Road 5201-200 to the private parcel in T32S, R13W, Section 16. Applicant requests permission to use and maintain the road for perpetual timber management.

Location

Sixes River and South Fork Sixes River watersheds approximately 15 miles east of Port Orford, Oregon.

Project timeline

1
Scoping Start
11/22/2011
2
Comment Period
11/10/2014
3
07/28/2016
4
Objection Period Start
06/03/2016
5
Decision
07/2016 (Estimated)
6
Implementation
09/2016 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Improvements/Construction
Mount Avery Spur Road Special Use Permit RequestDecision Signed Date: 07/28/2016
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionT32S, R13W, Section 22
Road managementSpecial use management