AT&T proposing to install a fiber optic line at Highway 140 near Fish Lake for 4.3 miles to the top of Robinson Butte communications site. The fiber optic line will be placed in conduit and will follow an existing, authorized electrical right-of-way
Location
Near Fish Lake and along Highway 140
Project timeline
1
Scoping Start
12/27/2018
2
Decision
05/2020 (Estimated)
3
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Robinson Butte/AT&T Fiber Optic Installation | Decision Signed Date: 05/21/2020 |
| Forests | Rogue River-Siskiyou National Forest |
| Districts | High Cascades Ranger District |
| Legal Land Description | Township 37S, Range 4E, Section 8 |