Site testing and replacement of the Rohn 45G guided tower currently located on Iron Mountain with a new three-legged freestanding tower.
Location
Iron Mountain
Project timeline
1
Scoping Start
11/01/2021
2
Decision
02/2022 (Estimated)
3
Implementation
05/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Iron Mountain Communication Site | Decision Signed Date: 02/01/2022 |
| Forests | Rogue River-Siskiyou National Forest |
| Districts | Powers Ranger District |