Decision Memo On Hold

Port Orford Cedar Roadside Sanitation

Rogue River-Siskiyou National Forest Curry, Oregon Rogue River-Siskiyou National Forest All Units

Remove POC along FSR 5520 on either side of the road for 10 miles.

Location

South Ford Coquille River, FSR 5520

Project timeline

1
Scoping Start
11/09/2018
2
Decision
01/2019 (Estimated)
3
Implementation
01/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements; Road Maintenance
ForestsRogue River-Siskiyou National Forest
DistrictsPowers Ranger District
Legal Land DescriptionNot Applicable
Vegetation management (other than forest products)Road management