BLM submitted a special use permit request for use of a 317 ft section of road on FS land.
Location
SMRD
Project timeline
1
Scoping Start
09/16/2016
2
Decision
09/2016 (Estimated)
3
Implementation
09/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Nedsbar Special Use Permit for BLM | Decision Signed Date: 09/16/2016 |
| Forests | Rogue River-Siskiyou National Forest |
| Districts | Siskiyou Mountains Ranger District |
| Legal Land Description | Not Applicable |