As part of a grant from Department of Energy the Forest Service proposes to construct a 500.5-kilowatt solar array, covering approx. 1.2 acres, at the nursery site. The life expectancy of the array exceeds 20 years.
Location
J. Herbert Stone Nursery
Project timeline
1
Scoping Start
07/12/2016
2
Comment Period
11/01/2016
3
Objection Period Start
12/15/2016
4
Decision
02/2017 (Estimated)
5
Implementation
03/2017 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction |
| J. Herbert Stone Nursery Solar Array | Decision Signed Date: 02/06/2017 |
| Forests | Rogue River-Siskiyou National Forest |
| Districts | J. Herbert Stone Nursery |
| Legal Land Description | Not Applicable |