The project would address several deferred maintenance items to the Union Creek Water System, including: replacement of the waterline, replacement of components at the Union Creek and Farewell Bend campgrounds, and the USFS Administrative Compound.
Location
Union Creek Campground, Farewell Bend Campground, and USFS Administrative Compound at Union Creek
Project timeline
1
Scoping Start
08/01/2015
2
Decision
10/2015 (Estimated)
3
Implementation
03/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Decision Decided Date | 10/01/2015 |
| Forests | Rogue River-Siskiyou National Forest |
| Districts | High Cascades Ranger District |
| Legal Land Description | sec. 34 and 35, Township 30 South, Range 3 East, of the Willamette Meridian |