J. Herbert Stone Nursery plans to construct a 156foot long 30 foot wide greenhouse, which would provide 23,400 square feet of added capacity. This will help with reforestation efforts.
Location
The greenhouse will be constructed west of current greenhouses.
Project timeline
1
Scoping Start
08/31/2022
2
Decision
03/2024 (Estimated)
3
Implementation
07/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| J. Herbert Stone Nursery Greenhouse Project DM | Decision Signed Date: 03/06/2024 |
| Forests | Rogue River-Siskiyou National Forest |
| Districts | J. Herbert Stone Nursery |
| Legal Land Description | Not Applicable |