Site identified for this project are either low use, or already closed sites. This decommissioning and removal is part of the recreation and facilities master plan and will decrease the back log of deferred maintenance.
Location
Forest Wide
Project timeline
1
Scoping Start
09/21/2016
2
Decision
04/2017 (Estimated)
3
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Dispersed Recreation Mgmt.; Facility Maintenance |
| Decision Decided Date | 04/06/2017 |
| Forests | Rogue River-Siskiyou National Forest |
| Districts | Rogue River-Siskiyou National Forest All Units |
| Legal Land Description | Not Applicable |