Supplemental EIS. To amend the Forest Plan to modify the Eastside Screens wildlife standard at 6d. (2) (a) to define both live and dead trees. This amendment applies to, and only for the duration, of School Fire Salvage Recovery Project
Location
School Fire Salvage Recovery Project Area
Project timeline
1
NOI in Federal Register
02/26/2007
2
DEIS NOA in Federal Register
03/09/2007
3
FEIS NOA in Federal Register
05/11/2007
4
Decision
06/2007 (Estimated)
5
Implementation
07/2007 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Salvage) |
| School Fire Salvage Recovery Project (Supplemental EIS) | Decision Signed Date: 06/11/2007 Legal Notice Date: 06/12/2007 |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |