Categorical Exclusion · North Fork John Day Ranger District · updated 1/27/2026
T7S R31E Sec 5&6 · Grant; Umatilla, Oregon
In accordance with the National Forest Management Act of 1976, this project proposes to replant trees in areas burned by the 2024 Bone Point Fire, where stocking levels have fallen below Umatilla National Forest Plan requirements.
Vegetation management (other than forest products)
NEPA Start Date
11/7/2025
Finding/Decision Date
1/26/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-03d-NRCS |
| Decision Signed Date | 1/26/2026 |
Categorical Exclusion · North Fork John Day Ranger District · updated 1/27/2026
T6S R34E Sec 29 & 30 · Umatilla, Oregon
The proposed action is to plant ponderosa pine, Douglas-fir, western larch, and western white pine seedlings by hand on 107 acres of the Double Snag fire burn scar. This will be non-RHCA planting.
Vegetation management (other than forest products)
NEPA Start Date
11/7/2025
Finding/Decision Date
1/26/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-03d-NRCS |
| Decision Signed Date | 1/26/2026 |
Decision Memo · Umatilla National Forest All Units · updated 6/23/2025
The project is within the existing Special Use Permit boundary of Bluewood Ski Area. · Columbia, Washington
Bluewood proposes to enhance their user experience through replacement of an aging lift, lodge renovations, overnight lodging development, mountain bike trail development, ski run improvements and construction, and snowmaking installation.
Recreation management
Comment Period
08/22/2024
Decision
12/2024 (Estimated)
Implementation
11/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Umatilla National Forest All Units · updated 6/11/2025
14.5 miles south of Pomeroy, WA · Columbia, Washington
There is a need to complete repairs initiated after the 2020 flood and resurfacing the existing 8 miles of asphalt pavement to provide a smooth-running surface for the portion of NFSR 47 that accesses the Forest Service land.
Road management
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction; Watershed Improvements |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | T9N, R41E, Sec. 2-3, 10-11, 15-16, 20-21, 29-30 |
Decision Memo · Pomeroy Ranger District · updated 6/11/2025
The project is located between Forest roads 4000 (Mountian Road) and 4200 (Iron Springs. · Garfield, Washington
Up to 3600 acres of non-commerical thinning and 7300 acres of prescribed fire.
Fuels management
Decision
12/2024 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | T. 8 N, R. 42 E, sec. 4-5. T. 9 N, R. 42 E, sec. 1-4, 9-12, 14-17, 20-22, 27-29, 32-33. |
Decision Memo · Umatilla National Forest All Units · updated 6/11/2025
The fuelbreak runs along the boundary of the Umatilla National Forest, Bureau of Land Management, and the private lands of the Top Road Firewise Community. The project intersects County Road 670. · Grant, Oregon
Top Road Fuelbreak Project is located in the Lower Big Wall Creek and Cupper Canyon-North Fork John Day River watersheds. The constructed fuelbreak will run along roadways and existing fire break on National Forest Service lands.
Fuels management
Decision
06/2025 (Estimated)
Implementation
08/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Walla Walla Ranger District · updated 6/5/2025
The project area is located approximately 9 miles West of Elgin, Oregon and encompasses 14.6 miles of Forest Service Road 31 known as Summit Road. · Umatilla; Wallowa; Columbia; Walla Walla, Oregon; Washington
The project would reduce fuels and improve forest health along the strategic control features of Forest Roads 31 (Summit Road) and 32 (Dry Creek).
Vegetation management (other than forest products)Fuels management
Decision
06/2025 (Estimated)
Implementation
10/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (9) |
| Special Authority | Ira - Inventoried Roadless Area Activities Requiring Chief's Approval; Hfra Title Vi: Insect And Disease Projects; Hfra Title Vi: Wildfire Resilience Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Roadless Area Management; Road Maintenance; Special Area Management; Scenery Management; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T1S R37E Sec1; T1S R38E Sec6,7;T1N R38E Sec5,6,18,19,30,31; T1N R37E Sec1,2,13-15,22-24,25-26, 36; T2N R37E Sec 13,14,23,24,25,26,35,36; T2N R38E Sec 9,18,19,30,31 |
Decision Memo · Umatilla National Forest All Units · updated 4/9/2025
Project is located along NFSR-54 from milepost 0.0 to milepost 11.0 within Pearson Creek/East Birch Creek, Pilot Rock, Oregon · Umatilla, Oregon
Repair, realign, and stabilize the 54 Road in response to past flooding and human activities to restore access to/from the National Forest on impacted sections of the 54 road.
Wildlife, fish, rare plantsRoad management
Decision
04/2025 (Estimated)
Implementation
04/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Road Improvements/Construction |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · North Fork John Day Ranger District · updated 4/4/2025
1.5 miles southwest of Dale, OR · Grant, Oregon
Modification of the Central Desolation Allotment boundary to divide the incorporated project area into several different pastures the Central Desolation Allotment. The existing term grazing permits will be modified to reflect new ownership.
Grazing managementLand ownership management
Decision
04/2025 (Estimated)
Implementation
04/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Land Use Adjustments; Boundary Adjustments; Grazing Allotment Management; Grazing Authorizations |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · North Fork John Day Ranger District · updated 3/13/2025
On USFS Road 55 at Township 06S Range 32E Section 32 · Umatilla, Oregon
An approximately 25 foot portion of the 55 Road shoulder failed during above average precipitation, resulting in a public safety hazard. The proposed action will widen the existing road by excavating into the hillslope approximately 8 to 10 feet.
Road management
Decision
03/2025 (Estimated)
Implementation
05/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · North Fork John Day Ranger District · updated 3/13/2025
Vinegar Hill, Desolation Butte, Tower Mountain, Summit Camp · Grant; Umatilla, Oregon
Protection of Whitebark Pine stands from wildfire, disease, and insect infestation by pruning, thinning, and creating a 500ft buffer around extant stands. Promote species recovery by planting WBP seedlings in optimal NFJD RD habitat locations.
Vegetation management (other than forest products)
Decision
03/2025 (Estimated)
Implementation
03/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (25), 36 Cfr 220.6(E)(25) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · North Fork John Day Ranger District · updated 10/2/2024
Pearson Recreation Residence Tract, Township 6S, Range 33E · Umatilla, Oregon
Restore area, which has been negatively affected by unauthorized alteration of terrain, to desired natural conditions by selective contouring, pipe removal and reseeding with native plants and grasses.
Watershed management
Decision
10/2024 (Estimated)
Implementation
10/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Pearson Pond Removal Decision Memo | Decision Signed Date: 10/02/2024 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Heppner Ranger District · updated 7/30/2024
Approxitmenatly 40 miles south of Heppner Oregon. Grant and Morrow County's. · Grant; Morrow, Oregon
This project proposes improving stand conditions, reducing the risk and increase resilience to insect and disease infestations, and improve wildlife habitat .
Forest productsFuels management
Comment Period
03/08/2023
Decision
07/2024 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.3(11) |
| Special Authority | Not Applicable / Other; 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Green) |
| Parkers Mill Decision Memo | Decision Signed Date: 07/26/2024 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Umatilla National Forest All Units · updated 12/14/2023
Approximately five miles south of Ukiah, Oregon. Continuing south along Forest Service Road 52 to the junction of Forest Service Road 51. · Grant; Umatilla, Oregon
The P52 Fuel Break includes the FSR 52 from the northern district boundary of the North Fork John Day Ranger District and runs south to the junction of FSR 51. It also includes the roads and trails surrounding the Pearson Recreation residences.
Fuels management
Decision
12/2023 (Estimated)
Implementation
04/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| P52 Fuel Break Decision Memo | Decision Signed Date: 12/13/2023 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T 6 S, R 32 E, Sec. 4, 5, and 9-12; T 6 S, R 33 E, Sec. 7, 17, 18, 20-22, 25-27; T 6 S, R 34 E, Sec. 28-30, 33-36; T 7 S, R 35 E, Sec. 1-6, 12, 13, and 24. |
Decision Memo · North Fork John Day Ranger District · updated 11/9/2023
North of 5300 rd adjacent to existing open road (5314 road) · Morrow, Oregon
Relocating fence that crosses Matlock Prairie currently located on private lands onto Forest Service land. Fence is a pasture division fence needed to manage livestock on the F.G. Whitney Allotment.
Grazing management
Decision
11/2023 (Estimated)
Implementation
03/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · North Fork John Day Ranger District · updated 11/9/2023
southeast corner of the HW244 intersection with forest road 5160 (Lat, Long: 45.183679, -118.530170) · Union, Oregon
Special Use Permit to allow the installation and continued maintenance of a roadside weather station to gather real-lime weather and traffic condition information to improve safety for the traveling public.
Special use management
Decision
11/2023 (Estimated)
Implementation
12/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Pomeroy Ranger District · updated 7/31/2023
The planning area is located in the northwesternmost portion of the Pomeroy Ranger District, with WA Department of Fish and Wildlife land to the north, northeast and east. · Columbia, Washington
Improve forest health and resilience to insects, diseases, and wildfire by managing vegetation densities, forest structures, and species compositions.
Vegetation management (other than forest products)Climate change adaptationForest productsFuels management
Comment Period
06/22/2022
Decision
07/2023 (Estimated)
Implementation
04/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Portions of: T. 8N R. 40E, Section 1, 2,11, 12, 13, 14; T. 8N R. 41E, Section 5, 6, 7, 33; T. 9N R. 40E, Sections 24, 25, 26, 35, 36; and T. 9N R. 41E, Sections 3-10, 16-21, 29-32 |
Decision Memo · Umatilla National Forest All Units · updated 6/20/2023
Various steep slopes in Umatilla and Union Counties in the Umatilla National Forest, Walla Walla District · Umatilla; Union, Oregon
Propose to change steep slope logging system activities previously analyzed for skyline logging to a cable assist system for the identified harvest units.
Forest products
Scoping Start
05/2023 (Estimated)
Decision
03/2024 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Pomeroy Ranger District · updated 2/8/2023
T. 8N, R. 42E, Section 5; T. 7N, R. 40E, Section 10; T. 7N, R. 43E, Section 2, and T. 8N, R. 43E, Section 35 · Asotin; Columbia; Garfield, Washington
Rectify deferred maintenance and conduct necessary improvements to historic structures currently used as rental cabins, with a focus on retaining their features and using similar construction materials.
Facility management
Decision
02/2023 (Estimated)
Implementation
08/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Ochoco National Forest All Units · updated 2/1/2023
National Forests in Oregon, east of the Cascade Mountain Range. · Baker; Crook; Deschutes; Grant; Harney; Klamath; Lake; Malheur; Umatilla; Union; Wallowa; Asotin; Columbia; Garfield; Walla Walla, Oregon; Washington
The USFS will evaluate alternatives to the wildlife standard of the Eastside Screens that limits harvest of trees greater than 21 inches for the Umatilla, Wallowa-Whitman, Malheur, Ochoco, Deschutes, and Fremont-Winema National Forests.
Vegetation management (other than forest products)Wildlife, fish, rare plants
Comment Period
08/11/2020
Decision
01/2021 (Estimated)
Implementation
01/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Deschutes National Forest; Fremont-Winema National Forest; Malheur National Forest; Ochoco National Forest; Umatilla National Forest; Wallowa-Whitman National Forest |
| Districts | Bend/Fort Rock Ranger District; Crescent Ranger District; Sisters Ranger District; Bly Ranger District; Lakeview Ranger District; Paisley Ranger District; Silver Lake Ranger District; Chiloquin Ranger District; Malheur National Forest All Units; Ochoco National Forest All Units; Umatilla National Forest All Units; Wallowa-Whitman National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Assessment · Pomeroy Ranger District · updated 8/17/2022
Approx. 20 miles south of Pomeroy, WA; in the area northeast of the Wenaha-Tucannon Wilderness · Asotin; Columbia; Garfield, Washington
Post-fire roadside danger & hazard tree abatement, area salvage, reforestation, & scientific research
Road managementRecreation managementVegetation management (other than forest products)ResearchForest products
Comment Period
03/24/2022
Decision
08/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Forest Vegetation Improvements; Road Maintenance; Research And Development; Timber Sales (Salvage) |
| Pomeroy Danger Tree & Fire Salvage EA/FONSI/DN | Decision Signed Date: 08/15/2022 |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Portions of Townships 7, 8, and 9 North, Ranges 41-44 East, Willamette Meridian |
Decision Memo · Heppner Ranger District · updated 7/28/2022
Black Mountain Communication Site, located at T 4S R 28E Sect. 14 SW/SE. Madison Butte Lookout, located at T 5S R 27E Sect. 29 NE/NE. · Morrow, Oregon
This project is designed to increase site distance of the Madison fire detection lookout and reduce the risk of loss of improvements (lookout tower and communication systems) at the Madison and Black Mountain Communication Sites due to wildfire.
Forest productsFuels management
Decision
02/2020 (Estimated)
Implementation
02/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3); 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Heppner Ranger District · updated 5/4/2022
Located approximately 32 miles south of Heppner, Oregon. · Morrow, Oregon
The Lovlett Corral Fire burned 137 acres on the Heppner Ranger District in the summer of 2021. This project proposes a fire salvage within the fire perimeter. Approximately 64 acres burned with moderate and high severity,
Vegetation management (other than forest products)Forest products
Decision
03/2022 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (11), 36 Cfr 220.6(E)(11); 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other; National Fire Plan - Healthy Forests Initiative Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Salvage) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Pomeroy Ranger District · updated 3/31/2022
Northwest portion of the Pomeroy Ranger District · Columbia, Washington
Improve forest health and resilience to insects, diseases, and wildfire by managing vegetation densities, forest structures, and species compositions.
Fuels managementForest productsVegetation management (other than forest products)
Scoping Start
10/2021 (Estimated)
Decision
01/2022 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Pomeroy Ranger District · updated 3/4/2022
Where the Wenaha River Trail #3106 crosses Crooked Creek in T6N R42E S22, Wallowa County, Oregon. · Wallowa, Oregon
Cancelled. Authorized under Forestwide Aquatic Restoration EA (https://www.fs.usda.gov/project/?project=47428)
Recreation managementProjects that may affect wilderness (for mailing list contacts)
Comment Period
04/09/2021
Decision
03/2022 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Wilderness Management |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | T6N R42E S22 |
Decision Memo · Walla Walla Ranger District · updated 1/27/2022
The bridge will be replaced where Burnt Cabin Trail #3226 crosses the South Fork Walla Walla River. · Umatilla, Oregon
This project will replace in kind the damaged Burnt Cabin Trail Bridge, removed in October 2020 due to imminent safety concerns. The replacement bridge will cross the SF Walla Walla River in the same footprint.
Recreation management
Decision
11/2021 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N, R38E, S9 |
Environmental Assessment · Walla Walla Ranger District · updated 10/18/2021
West of Andies Prairie off of OR-204 (Tollgate Highway) and Forest Road 31 (Summit Road). · Umatilla; Union, Oregon
Timber harvest, non-commercial thinning, and prescribed burning in the vicinity of Horseshoe Prairie, Ninemile Ridge, and Buck Mountain.
Forest productsVegetation management (other than forest products)Fuels management
Comment Period
03/05/2020
Objection Period Start
06/17/2021
Decision
10/2021 (Estimated)
Implementation
10/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Road Improvements/Construction; Timber Sales (Green) |
| High Buck Vegetation Management Project Decision Notice | Decision Signed Date: 10/18/2021 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Portions of T3N R37E Sec 36, T3N R38E Sec 21-23,26-34, T2N R37E Sec 1,2,11,12, T2N R38E Sec 3-10,15-16,21,22. |
Decision Memo · Pomeroy Ranger District · updated 10/14/2021
West Patit: in the Maloney Mtn. area. Mt. Horrible: east of Saddle Spring & south of Mt. Horrible. Tucannon: so. of Willow Springs between Salter Trail & Sheep Cr. Ables: in the Ables Ridge area. Charley: between Iron Springs Rd & Charley Cr. Rd. · Asotin; Columbia; Garfield, Washington
NCT and Prescribed fire will be used in areas of previous treatment and/or wildfire in order to maintain vegetation characteristics and disturbances that would be expected to occur under natural disturbance regimes.
Vegetation management (other than forest products)Fuels management
Comment Period
04/07/2021
Decision
05/2021 (Estimated)
Implementation
05/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | T9N R43E S 4, 5, 6, 7, 6, 9, 17. T7N R43E S 8, 9, 16, 17, 21, 22. T9N R41E S 32, 33, 34, 35. T8N R41E S 1, 2, 3, 4, 5, 11, 12. T9N R42E S 6, 7, 8, 17, 18, 19. T8N R41E S 12. T9N R42E S 11, 12, 13, 14, 22, 23, 24. T9N R43E S 4, 5, 6, 7, 8, 9, 18. |
Decision Memo · North Fork John Day Ranger District · updated 8/9/2021
11 miles north of Granite, Oregon and 34 miles southeast of Ukiah, Oregon · Grant, Oregon
Project within area designated in section 602(b)/(c) of HFRA, within Condition Class 2 and 3 Fire Regime Group I and III. Project would reduce the risk and extent of insect/disease infestation, and increase forest stand resiliency.
Forest products
Decision
08/2021 (Estimated)
Implementation
10/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T. 7 S., R. 35 E., Sections 1, 2, 11-13; T. 7 S., R. 35 E., Sections 21, 22, 27 and 28, E.W.M |
Environmental Impact Statement · Blue Mountain Ranger District · updated 7/14/2021
The planning area is located in Grant County approximately 9 miles north of Prairie City, Oregon. · Grant, Oregon
The project includes a suite of activities to restore forest resiliency and function, including: upland restoration activities; watershed, fisheries, and wildlife restoration; prescribed burning; road activities; and recreation system changes.
Recreation managementWatershed managementFuels managementVegetation management (other than forest products)Forest productsRoad managementWildlife, fish, rare plants
NOI in Federal Register
03/24/2017
DEIS NOA in Federal Register
11/02/2018
FEIS NOA in Federal Register
09/25/2019
Objection Period Start
09/25/2019
Decision
12/2020 (Estimated)
Implementation
12/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Trail Management; Road Maintenance; Road Improvements/Construction; Timber Sales (Green); Watershed Improvements |
| Forests | Malheur National Forest; Umatilla National Forest |
| Districts | Blue Mountain Ranger District; North Fork John Day Ranger District |
| Legal Land Description | T10S, R33E, sec 7-10, 13, and 15-36; T10S, R34E, sec 9-24 and 27-33; T11S, R33E, sec 1-5, 9-15, and 23-26; and T11S, R34E, sec 5-9, 16-21, and 28-30, W.M. |
Decision Memo · North Fork John Day Ranger District · updated 5/10/2021
Township 08 S, Range 32 East, Sections 5, 8, and 17 · Grant, Oregon
Improve efficiency of gathering livestock and improve livestock distribution by splitting the pasture into 2 separate pastures by constructing 3-mile division fence. No changes to the permitted livestock numbers, or the season of use proposed.
Grazing management
Decision
05/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Township 08 S, Range 32 East, Sections 5, 8, and 17 |
Decision Memo · Heppner Ranger District · updated 4/7/2021
The HK Complex is approximately 20 miles southeast of Heppner, OR · Morrow, Oregon
This project will restore trees on 150 acres of forested lands that were denuded of vegetation in the 2019 HK Fire. The fire killed trees within portions of the fire that burned at moderate to high severity. This has reduced the diversity of habita
Vegetation management (other than forest products)
Decision
03/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (11), 36 Cfr 220.6(E)(11) |
| Special Authority | Not Applicable / Other; National Fire Plan - Healthy Forests Initiative Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Township 6 South, Range 28 E, sections 5, 7, 8, and 18 |
Decision Memo · North Fork John Day Ranger District · updated 3/29/2021
TS5, R28E Sec.28. Trucks and rock crushing equipment will access the pit on NF-010 via 2104 (Morrow County Road 799) · Morrow, Oregon
The Ditch Creek expansion would cover approximately three acres extending in a NNW direction, growing the pit from 6.5 to approximately 10 acres. Trucks and rock crushing equipment will access the pit on NF-010 via 2104 (Morrow County Road 799)
Minerals and geology
Decision
03/2021 (Estimated)
Implementation
05/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Pomeroy Ranger District · updated 3/17/2021
Forest Roads 40, 4016, 4018, 4022, 4030, 41, 42, 43, 44, 46, 4620, 4625, 4600300, 4600301 · Asotin; Columbia; Garfield, Washington
Thinning, pruning, and/or prescribed burning within 100 feet of either side of select roads to reduce ladder fuels, thereby reducing potential fire severity and facilitating suppression actions.
Fuels managementRoad management
Decision
03/2020 (Estimated)
Implementation
06/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Road Maintenance |
| 10-Year Pomeroy Roadside Vegetation Management | Decision Signed Date: 03/19/2020 |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Pomeroy Ranger District · updated 3/17/2021
The project area is located in the northwest corner of the Pomeroy Ranger District. Private properties surround two sides and Washington Department of Fish and Wildlife borders part of the third. · Columbia, Washington
Commercial thinning, noncommercial thinning, and fuels reduction to create healthy and resilient stands.
Vegetation management (other than forest products)Fuels managementForest products
Scoping Start
05/2020 (Estimated)
Decision
09/2021 (Estimated)
Implementation
07/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Portions of T. 7N R. 40E, T. 7N R. 41E, T. 8N R. 40E, T. 8N R. 41E, T. 9N R. 40E, and T. 9N R. 41E. |
Decision Memo · Walla Walla Ranger District · updated 3/16/2021
9 miles west of Troy, Oregon · Wallowa, Oregon
Thinning of over dense stands by commercial harvest and non commercial thinning to lower potential risk of insect mortality.
Vegetation management (other than forest products)
Decision
03/2021 (Estimated)
Implementation
05/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Walla Walla Ranger District · updated 2/25/2021
Ski Bluewood · Columbia, Washington
Ski Bluewood is proposing to install a snow making system in their base area so they can make snow to cover those lowest elevation ski runs when natural snow is not adequate.
Special use management
Decision
03/2017 (Estimated)
Implementation
07/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T7N, R40E, Section 18 |
Decision Memo · North Fork John Day Ranger District · updated 2/23/2021
T. 4 S., R. 30 E., section 21 · Umatilla, Oregon
The Tombstone commercial thinning project consists of five thinning units totaling approximately 70 acres, and proposes to reduce stocking levels by using mechanical harvest methods.
Forest products
Decision
05/2015 (Estimated)
Implementation
09/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Decision Memo Decision Memo Tombstone Commercial Thinning Project | Decision Signed Date: 05/12/2015 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T. 4 S., R. 30 E., section 21 (south half) Willamette Meridian surveyed, Umatilla County, Oregon |
Decision Memo · Walla Walla Ranger District · updated 2/18/2021
5 miles West of Troy, Oregon. · Wallowa, Oregon
Construction of wildlife and livestock exclusion fencing around aspen stands that are regenerating after being damaged by the 2015 Grizzly Bear Complex fire.
Wildlife, fish, rare plantsVegetation management (other than forest products)
Decision
04/2020 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T 5N R 42E, T 6N R 42E |
Decision Memo · Heppner Ranger District · updated 11/2/2020
T5S, R28E, Sections 26 & 35; T6S, R29E, Sections 1, 10, 11, 12, 13, 14, & 28 · Morrow, Oregon
This project proposes harvesting up to 250 acres of dead and dying trees from a blowdown event that happened earlier this spring (2020). Logging operations will include ground-based logging systems with whole-tree yarding in proposed cutting units.
Forest products
Decision
10/2020 (Estimated)
Implementation
10/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Salvage) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Walla Walla Ranger District · updated 9/30/2020
20 Miles south of Dayton Washington. Including all of the area within the permit boundary of the Ski Bluewood Resort and adjacent lands to the north. · Columbia, Washington
Vegetation management with commercial and non-thinning, prescribed burning and recreation area management treatments to protect values at risk including forest resiliency, human safety, and infrastructure protection
Vegetation management (other than forest products)Recreation managementFuels management
Comment Period
05/31/2019
Objection Period Start
01/24/2020
Decision
04/2020 (Estimated)
Implementation
06/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Scenery Management |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | 22 miles southeast of Dayton WA. T7, R 39E S12, 13 and R40E S2, 3, 7, 8, 17, 18, 19, 20 |
Decision Memo · Walla Walla Ranger District · updated 8/19/2020
The installation would occur at the Spout Springs Recreation Residence Tract Lot 8. · Union, Oregon
The cabin owner at Spout Springs Recreation Residence Tract, Lot #8 has requested to install a new septic tank. The old tank is leaking and requires decommission.
Special use management
Decision
01/2019 (Estimated)
Implementation
06/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N, R38E, Section 10 |
Decision Memo · Heppner Ranger District · updated 8/10/2020
28 miles southwest of Heppner, Oregon · Wheeler, Oregon
Project within area designated in section 602(b)/(c) of HFRA, within WUI, and Condition Class 2 or 3 Fire Regime Groups I or III. Project would reduce the risk and extent of insect/disease infestation, and increase forest stand resiliency.
Vegetation management (other than forest products)Forest products
Decision
08/2020 (Estimated)
Implementation
09/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Salvage); Timber Sales (Green) |
| West End Farm Bill Decision Memo | Decision Signed Date: 08/06/2020 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T. 7 S., R. 23 E., Sections 11-14; R. 24 E., Sections 4-5, 7-9, E.W.M. |
Environmental Impact Statement · Pomeroy Ranger District · updated 6/8/2020
Project is approx. 16 linear miles southwest of Asotin, WA. Project is primarily bounded by 44 Rd (Smoothing Iron), 41 Rd (Upper Lick Rd), and portion of 42 Rd (Iron Springs). · Asotin; Garfield, Washington
Timber harvest, other tree cutting activities and fuels treatments to move conditions to desired levels and/or ranges. Utilize existing road system except, 11 miles of temp road, of which utilizes 9 miles on existing road templates.
Forest productsFuels managementVegetation management (other than forest products)
NOI in Federal Register
11/28/2014
DEIS NOA in Federal Register
06/01/2018
FEIS NOA in Federal Register
12/28/2018
Objection Period Start
12/28/2018
Decision
05/2019 (Estimated)
Implementation
05/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Road Maintenance; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Heppner Ranger District · updated 3/2/2020
Along or adjacent to FS roads 21 (Morrow County 603), 2107, 2107-020, 2100-122, and 2100-119 and within the HK Complex burn area on the Heppner Ranger District of the Umatilla National Forest · Morrow, Oregon
Salvage harvest up to 250 acres in the HK Complex burn area, may include FS roads 21 (Morrow County 603), 2107, 2107-020, 2100-122, and 2100-119, for adjacent stands, haul routes, and danger tree removal.
Forest products
Decision
02/2020 (Estimated)
Implementation
05/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Salvage) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T5S, R27E, Section 35; T5S, R28E, Section 36; T6S, R27E, Sections 1, 12, & 13; T6S, R28E, Sections 5-8, 17, & 18 |
Decision Memo · Walla Walla Ranger District · updated 2/19/2020
Tollgate Recreation Residence Tract, Cabin #1. · Umatilla, Oregon
Cabin owners have requested to build a storage shed on their lot to store firewood, maintenance supplies and other materials including snow mobiles. Shed would be 10-ft X 13-ft.
Special use management
Decision
06/2016 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T.4N., R.38E., portion of section 33 |
Decision Memo · Walla Walla Ranger District · updated 2/12/2020
The legal location is T6N R38E Sections 22, 23, 27, 28 and 35 with a central Latitude and Longitude of 45.9653185352018 X -118.023555504282 (Decimal Degrees). · Umatilla, Oregon
The purpose of the proposed project is to increase the ability to effectively suppress wildfire and reduce risks to wildland firefighters within the project area, as well as reduce the risk of undesirable impacts to the Mill Creek Watershed.
Fuels managementVegetation management (other than forest products)Wildlife, fish, rare plants
Decision
02/2020 (Estimated)
Implementation
07/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Umatilla National Forest All Units · updated 1/31/2020
High Ridge area, immediately south of the North Fork Umatilla Wilderness, North of the 31 Road, immediately west of the NineMile Trail Head. · Umatilla; Union, Oregon
Amendment of F3 High Ridge Evaluation Management Area to E2 Timber and Big Game Management Area
Land management planning
Comment Period
08/06/2019
Objection Period Start
10/15/2019
Decision
12/2019 (Estimated)
Implementation
01/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (16), 36 Cfr 220.6(E)(16) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Plan Amendment |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Pomeroy Ranger District · updated 1/31/2020
The project is located 20 miles southeast of Pomeroy, WA in the Pataha Creek sub-watershed. · Garfield, Washington
The Upper Pataha Project proposes to reduce risk and mitigate insects and disease infestation in the Pataha Creek Sub-Watershed by lowering densities and altering species composition through commercial and non-commercial harvest.
Vegetation management (other than forest products)Fuels management
Decision
11/2019 (Estimated)
Implementation
11/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | T 9 N, R 42 E, Sections 1, 2, 3, 4, 9, 10, 11, 12, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 27, 28, 29, 32, 33, T 8 N, R 42 E, Sections 4, 5 |
Decision Memo · Walla Walla Ranger District · updated 12/10/2019
Unit is located between Forest Roads 6200-500 and 6200-531. Near the top of Jarboe grade. · Union, Oregon
Project proposes to improve forest health and stand growth/vigor. The project consist of one treatment unit approximately 68 acres in size. The proposal calls for the stand to receive an improvement cut. Harvest would be by ground based equipment.
Forest products
Comment Period
08/24/2012
Decision
11/2012 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N.; R39E.; Section 25 and T4N; R40E: Section 30 |
Decision Memo · Heppner Ranger District · updated 12/10/2019
This project is located in stands across the entire Heppner Ranger District · Grant; Morrow; Wheeler, Oregon
The Heppner Ranger District proposes to use supplemental planting of tree seedlings in previously managed stands to promote diversity in species composition and structure and increase stand resiliency.
Vegetation management (other than forest products)
Comment Period
08/03/2012
Decision
02/2013 (Estimated)
Implementation
04/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements |
| Heppner District Wide Planting | Decision Signed Date: 02/01/2013 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | All townships, ranges, and sections within the Heppner Ranger District - for specific stand locations please contact district |
Environmental Assessment · Walla Walla Ranger District · updated 12/10/2019
Approximately 24 miles to the northeast of Elgin, OR · Wallowa, Oregon
Project would reauthorize grazing activities within the Eden Cattle and Horse allotment. The Eden C&H allotment is approximately 34,000 acres in size.
Grazing management
Comment Period
07/19/2013
Decision
09/2013 (Estimated)
Implementation
10/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Grazing, Rescissions Act Of 1995 |
| Notice and Comment Regulation | 215 |
| Project Activity | Grazing Allotment Management; Grazing Authorizations; Grazing Structural Improvements |
| Eden Cattle & Horse Allotment Project | Decision Signed Date: 09/16/2013 Legal Notice Date: 09/19/2013 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
Decision Memo · Heppner Ranger District · updated 12/10/2019
Approximately ¬¬30 aerial miles south of Heppner, and consist of .06 acres. This area is within the Heppner Ranger District (Umatilla National Forest), · Umatilla, Oregon
Re-issuing this permit would allow the continued use and existence of a spring box development and approximately 302 ft of pipeline at Death Peak Springs. This also includes a 10%u2019 wide right-of-way for maintenance and access.
Grazing management
Decision
08/2014 (Estimated)
Implementation
12/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T. 7., R. 26., Sec. 35 of the Willamette Principle Meridian |
Environmental Assessment · Walla Walla Ranger District · updated 12/10/2019
16 miles N of Elgin, OR, 30 miles NE of Mission, OR, spanning three subwatersheds: Upper Lookingglass, Little Lookingglass, and Jarboe Creek. The main access roads include Forest Road 64 and 63 · Umatilla; Union, Oregon
Approximately 2,308 acres of commercial mechanical treatments are proposed, along with 2,755 acres of small diameter hand thinning. All treatments would have a restoration focus and both lumber and chip materials would be produced.
Forest productsVegetation management (other than forest products)Fuels managementWatershed management
Comment Period
08/10/2018
Objection Period Start
12/11/2018
Decision
07/2019 (Estimated)
Implementation
07/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Portions of T3N R39E sect.3,4,5,6; T4N R38E sect.12,13,14,22,23,24,25,26,27,34,35,36; T4N R39E sect. 1,2,4-34; T4N R40E sect.4,5,6,7,8,9,17,18,19,20,28,29,30,31,32,33 |
Decision Memo · Pomeroy Ranger District · updated 12/10/2019
The project is approximately 28 road miles SE of Dayton, Washington. · Columbia, Washington
Godman Thin project consists of several young stands (35-60 years old) where high-densities are increasing the likelihood of insect and disease infestations. Godman Thin proposes to commercially thin these stands to make them less susceptible.
Vegetation management (other than forest products)
Decision
07/2018 (Estimated)
Implementation
09/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Portions of T 7 N, R 40 E, Sections 2, 3, 10, 11; T 8 N, R 40 E, Sections 2, 11, 12, 13, 14, 23, 24, 26; and T 9 N, R 40 E, Sections 24, 25, 26, 27, 35. |
Decision Memo · Walla Walla Ranger District · updated 12/10/2019
Site is located on the 3719-040 spur. More locally known as Coyote Ridge, about 3/4 miles before the trailhead to the North Fork Umatilla River Trail. · Umatilla, Oregon
This project proposal if for a weather monitoring station to be placed on National Forest System Lands to survey the weather conditions around huckleberry brush (Vaccinium membranaceum).
Research
Decision
10/2019 (Estimated)
Implementation
10/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Research And Development |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T3N, R38E, Section 7, SE/NE |
Decision Memo · Walla Walla Ranger District · updated 12/10/2019
Tollgate Quad, within the vicinity of Langdon Lake 1.10 acres · Umatilla, Oregon
The project would involve the issuance of a new 20-year special use permit for the use of the existing improvements. There would be no ground disturbing activities associated with the implementation of this project, other than routine maintenance.
Special use management
Decision
01/2015 (Estimated)
Implementation
02/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Facility Maintenance |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T.4N., R.38E., Section 32 |
Decision Memo · Walla Walla Ranger District · updated 12/10/2019
There are 2 SNOTEL sites on each of the Pomeroy, North Fork John Day and Heppner Ranger Districts, and 3 SNOTEL sites on the Walla Walla Ranger District. · Grant; Morrow; Umatilla; Union; Wallowa; Columbia; Garfield; Grant; Walla Walla, Oregon; Washington
Issue a new forest-wide special use permit to the Natural Resource Conservation Service for a term of 30 years for nine SNOTEL sites on the Umatilla National Forest.
Special use management
Comment Period
10/31/2013
Decision
12/2013 (Estimated)
Implementation
01/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| NRCS SNOTEL Sites SUP Project | Decision Signed Date: 12/17/2013 Legal Notice Date: 12/20/2013 |
| Forests | Umatilla National Forest |
| Districts | Umatilla National Forest All Units |
| Legal Land Description | T5S,R27E,Sec30; T4S,R29E,Sec30; T2S, R35E,Sec29; T2S,R37E,Sec28; T8N,R42E,Sec 9; T9N,R43E,Sec 23; T3N,R38E,Sec 31; T7N,R40E,Sec 32; T6N,R39E,Sec 21 |
Decision Memo · Pomeroy Ranger District · updated 12/10/2019
District-wide · Wallowa; Asotin; Columbia; Garfield, Oregon; Washington
Non-commercial thinning to reduce stocking levels in timbered stands. Work will be done by hand using chainsaws.
Vegetation management (other than forest products)
Comment Period
08/08/2013
Decision
11/2013 (Estimated)
Implementation
04/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
Decision Memo · Walla Walla Ranger District · updated 12/10/2019
Along Oregon 204 in upper Little Phillips Cr; Andies Prairie Rock Pit; & Spout Springs Rock Pit. Size is 6 Acres. · Union, Oregon
The proposed action would issue a special use permit to replace an expired one for a 20-year term for the operations and maintenance of the existing improvements (storage areas).
Special use management
Decision
01/2015 (Estimated)
Implementation
03/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Road Maintenance |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T2N, R38E, Sec 11, SE, SE; T3N, R38E, Sec 26 SW 1/4; T3N, R38E, Sec 9, S 1/2, SE 1/4. |
Decision Memo · Walla Walla Ranger District · updated 12/10/2019
The Unit is located between the 6200, 6200-390 and 6200-391 roads and is approx. 70 acres. · Union, Oregon
The Pinical Project proposes to reduce stocking levels by using a commercial timber sale. This project consists of one thinning unit totaling approximately 70 in size located between the 6200, 6200-390 and 6200-391 roads.
Forest products
Decision
03/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N; R40E; Section 9 and 10 |
Decision Memo · Walla Walla Ranger District · updated 12/10/2019
Walla Walla Ranger District, Spout Springs vicinity · Union, Oregon
The project would consist of issuing 5 new Special Use Permits to Oregon State Patrol, Oregon Dept. of Forestry, Oregon Dept. of Transportation, Oregon Dept. of Corrections, and the Federal Bureau of Investigation to replace their expiring permits.
Special use management
Comment Period
10/31/2013
Decision
12/2013 (Estimated)
Implementation
01/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Spout Springs Administrative Communications Site SUP | Decision Signed Date: 12/17/2013 Legal Notice Date: 12/20/2013 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Township 3 North, Range 38 East, Section 10, NE quarter |
Decision Memo · North Fork John Day Ranger District · updated 12/10/2019
The project area is approximately 4,761 acres. Proposed stands in the project area are located in Townships 4, 5 and 6, Ranges 29 and 30 East, in multiple sections, Willamette Meridian surveyed. · Umatilla, Oregon
This project includes thinning 4,654 acres for the purpose of promoting stand health, large tree development, and reducing fire intensity to minimize the chance of catastrophic fire events.
Vegetation management (other than forest products)
Decision
07/2018 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Western Route Thinning (Part A) | Decision Signed Date: 05/25/2017 |
| Western Route Thinning Project (PART B) | Decision Signed Date: 07/30/2018 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | The project area is approximately 4,654 acres. Proposed stands in the project area are located in Townships 4, 5 and 6 South, Ranges 29 and 30 East, in multiple sections, Willamette Meridian surveyed |
Environmental Assessment · Walla Walla Ranger District · updated 11/15/2019
East of Highway 204 and south of Forest Road 3100000, within the vicinity of Phillips Creek, Dry Creek and other associtaed drainages. · Union, Oregon
Approximately 1,663 acres of mechanical treatments are proposed, along with 975 acres of small diameter hand thinning. Mechanical treatments would have a restoration focus and both lumber and chip materials would be produced.
Forest products
Comment Period
07/16/2015
Objection Period Start
04/29/2016
Decision
09/2016 (Estimated)
Implementation
03/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Portions of T1N R37E sec. 1,2,12, T1N R38E sec. 1,2,3,4,5,6,7,8,9,10,11 and 12, T2N R37E sec. 12,3,14,15,22,23,24,25,26 and 36, T2N R38E sec. 5,7,8,9,16,17,18,19,20,21,27,28,29,30,31,32,33,34 and 35. |
Decision Memo · Heppner Ranger District · updated 10/8/2019
Black Mountain Communication Site: Upper Willow Creek HUC6 Madison Butte Lookout & Communications Site: Rhea Creek, Wall Creek, and Upper Rock Creek HUC6 · Umatilla, Oregon
The purpose of this project is to adjust the Administrative Site boundaries to allow for ongoing and future management in and around Madison Butte Lookout and Black Mountain Communication Site.
Fuels managementFacility managementLand management planning
Decision
03/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (16), 36 Cfr 220.6(E)(16) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Plan Amendment |
| Heppner Administrative Site Adjustments | Decision Signed Date: 03/22/2016 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Madison Butte Lookout & Communications Site: T5S-R27E-Sec 29 NE/NE Black Mountain Communication Site: T4S-R28E-Sec 14 SW/SE Willamette Meridian Surveyed |
Decision Memo · Walla Walla Ranger District · updated 9/16/2019
Near Long Meadows Guard station approximately 13 miles east of Troy, OR. · Wallowa, Oregon
Salvage of dying trees within the footprint of the Grizzly Bear Fire near Long Meadows Guard Station, approximately 13 miles west of Troy, Oregon.
Forest products
Decision
09/2019 (Estimated)
Implementation
10/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Salvage) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Heppner Ranger District · updated 8/5/2019
Surrounding Bull Prairie Campground and adjacent to Morrow County OHV Park. On the Heppner Ranger District of the Umatilla National Forest. · Grant; Wheeler, Oregon
Reduce fuel loading and improve stand conditions in the area surrounding Bull Prairie Campground and adjacent to Morrow County OHV Park. Proposal includes one 70 acre timber sale, small diameter thinning, and up to 4,300 acres of prescribed fire.
Fuels managementForest products
Decision
08/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Bull Prairie Hazardous Fuels Reduction Project | Decision Signed Date: 08/02/2019 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Not Applicable |
Environmental Impact Statement · Wallowa-Whitman National Forest All Units · updated 6/25/2019
the project area lies within the Blue Mountains ecoregion of northeast Oregon and southeast Washington. It covers 13 counties and includes shared boundaries with private, tribal, state and other lands · Baker; Crook; Grant; Malheur; Morrow; Umatilla; Union; Wallowa; Wheeler; Asotin; Columbia; Garfield; Walla Walla, Oregon; Washington
The Blue Mountains Forest Resiliency Project will propose thinning and prescribed burning on approximately 610,000 acres on the Ochoco, Umatilla and Wallowa-Whitman National Forests.
Vegetation management (other than forest products)Fuels management
NOI in Federal Register
02/05/2016
DEIS NOA in Federal Register
02/06/2016
FEIS NOA in Federal Register
04/2020 (Estimated)
Objection Period Start
01/2020 (Estimated)
Decision
04/2020 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Ochoco National Forest; Umatilla National Forest; Wallowa-Whitman National Forest |
| Districts | Ochoco National Forest All Units; Umatilla National Forest All Units; Wallowa-Whitman National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Heppner Ranger District · updated 6/21/2019
The upper part of Penland Lake campground. Penland Lake is on the eastern part of the Heppner Ranger District of the Umatilla National Forest. · Morrow, Oregon
The upper part of Penland Lake campground has multiple roads to various campsites. This project would grade and rock existing road in the upper campground and better define associated campsites. Excess routes would be rehabilitated.
Road managementRecreation managementFacility management
Scoping Start
04/2019 (Estimated)
Decision
04/2019 (Estimated)
Implementation
06/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Road Improvements/Construction |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · North Fork John Day Ranger District · updated 5/29/2019
This project is located in the Bowman-Camas Creek and Hidaway Creek watersheds on the Umatilla National Forest. · Umatilla, Oregon
The purpose is to provide a safe working environment for firefighters and to improve probability of success in protecting life and property in the event of a wildfire within or threatening the values at risk.
Fuels management
Comment Period
05/22/2018
Objection Period Start
09/20/2018
Decision
05/2019 (Estimated)
Implementation
07/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | The project area is located in Township 5 South, Range 33 East, Sections 4, 8, 9, 10, 14, 15, 20, 21, 22, 23, 28, and 29, Willamette Meridian surveyed, Umatilla County, Oregon. |
Decision Memo · Walla Walla Ranger District · updated 5/15/2019
32 Road · Umatilla, Oregon
A number of trees have been identified under the criteria for danger trees along the 32 Road. These trees must be removed for human safety and protection of infrastructure. Trees will be used on aquatic restoration.
Road management
Decision
05/2019 (Estimated)
Implementation
05/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Walla Walla Ranger District · updated 4/3/2019
Intersection of Forest Road 3734 with Little Phillips Creek, adjacent to highway 204 plus about ¾ mile of 3734 road from that point. · Union, Oregon
Remove the culvert on Forest Road 3734 over Little Phillips Creek. Decommission approx. 0.7 miles of FR 3734, and re-open approx. 1 mile of FR 3734 that is currently closed.
Wildlife, fish, rare plantsRoad managementWatershed management
Comment Period
05/29/2018
Objection Period Start
09/07/2018
Decision
11/2018 (Estimated)
Implementation
05/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Species Habitat Improvements; Road Maintenance; Watershed Improvements |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T2N, R38E S26, NE1/4, SE 1/16 |
Environmental Impact Statement · Walla Walla Ranger District · updated 11/20/2018
Elk Flat to Long Meadow between the Grande Ronde River and the Wenaha-Tucannon Wilderness · Union; Wallowa, Oregon
Vegetation treatments that include 2500 acres of timber harvest and fuels treatments, 8000 acres of landscape prescribed fire, hardwood and meadow restoration, 1900 acres of non-commercial thinning.
Vegetation management (other than forest products)Forest productsFuels management
NOI in Federal Register
02/05/2010
DEIS NOA in Federal Register
04/30/2010
FEIS NOA in Federal Register
10/22/2010
Decision
10/2010 (Estimated)
Implementation
12/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Plan Amendment; Road Improvements/Construction; Timber Sales (Green) |
| Cobbler II Timber Sale and Fuels Reduction Project | Decision Signed Date: 10/08/2010 (FS Withdrawn) Legal Notice Date: 10/27/2010 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N R 40E; T5N R40E; T4N R41 E; T5N R41E; T5N R42E; T6N R41E; T6N R42E. |
Environmental Assessment · North Fork John Day Ranger District · updated 10/12/2018
Hidaway Creek drainage, Umatilla County, Oregon · Umatilla, Oregon
Expansion of current exploration pits to a maximum of 30 ft wide by 25 ft deep using hand tools & limited mechanical equipment. Use of an existing closed road & shelter. Placement of an outhouse. Limited use of a spring for hand-washing of rock.
Minerals and geology
Comment Period
04/10/2018
Objection Period Start
08/17/2018
Decision
10/2018 (Estimated)
Implementation
04/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Hidaway Mine Plan of Operations Decision Notice and FONSI | Decision Signed Date: 10/12/2018 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T5S R33 1/2E Sections 22, 23 |
Environmental Impact Statement · Walla Walla Ranger District · updated 8/9/2018
Elk Flat to Long Meadow between the Grande Ronde River and the Wenaha-Tucannon Wilderness · Union; Wallowa, Oregon
A Supplemental Environmental Impact Statement (SEIS) is being prepared to clarify and revise aspects of the analysis disclosed within the October 2010 Cobbler II Timber Sale and Fuels Reduction Project Final Environmental Impact Statement (FEIS).
Vegetation management (other than forest products)Forest productsFuels management
NOI in Federal Register
05/06/2011
DEIS NOA in Federal Register
08/12/2011
FEIS NOA in Federal Register
05/18/2012
Decision
04/2012 (Estimated)
Implementation
09/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Plan Amendment; Road Improvements/Construction; Timber Sales (Green) |
| Record of Decision for Cobbler II Timber Sale and Fuels Reduction Project | Decision Signed Date: 04/13/2012 Legal Notice Date: 05/18/2012 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N. R40E; T5N R40E; T4N R41E; T5N R41E; T5N R42E; T6N R41E; T6N R42E. |
Environmental Impact Statement · Whitman Ranger District · updated 8/9/2018
Granite Creek Watershed · Baker; Grant, Oregon
Analyze proposed mining plans of operations within the Granite Creek Watershed on the Umatilla and Wallow-Whitman NFs.
Minerals and geology
NOI in Federal Register
10/11/2011
DEIS NOA in Federal Register
02/20/2015
FEIS NOA in Federal Register
03/16/2016
Objection Period Start
03/16/2016
Decision
06/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Minerals Or Geology Plans Of Operations |
| Forests | Umatilla National Forest; Wallowa-Whitman National Forest |
| Districts | North Fork John Day Ranger District; Whitman Ranger District |
| Legal Land Description | T8-10S R34-36 E WM |
Decision Memo · North Fork John Day Ranger District · updated 7/30/2018
Located between borders two private land boundaries along the 53 Road about 14 miles North West of Ukiah, Oregon. · Morrow, Oregon
Reduce over story density in order to promote forage production for big game wildlife and reduce fuels to protect values at risk. Commercially harvest up to 70 acres of all trees less than 21 inches in diameter at breast height
Forest products
Decision
07/2018 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Township 4 South, Range 29 East, and Section 33, Willamette meridian |
Decision Memo · North Fork John Day Ranger District · updated 7/30/2018
This project would be located around the Dale horse barn/pasture. · Grant, Oregon
Reduction of overstory density to promote grass and forage regeneration in the Dale horse pasture.
Forest productsFacility management
Decision
07/2018 (Estimated)
Implementation
09/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Township 7 South, Range 31 East, Section 1; Willamette Principal Meridian |
Decision Memo · Walla Walla Ranger District · updated 6/25/2018
Project area is in Lot #26 of the Spout Spring Recreation Residence, located off Oregon Hwy 204. · Union, Oregon
A recreation resident in Lot #26 of the Spout Springs Tract has requested to replace a leaking septic tank in order to meet the required health and safety standards.
Special use management
Decision
06/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Heppner Ranger District · updated 6/7/2018
Within the Potamus WUI area as identified in the Morrow County Community Wildfire Protection Plan · Grant; Morrow, Oregon
Now Part of Ellis Integrated Vegetation Project: area identified areas to reduce wildfire risk to public and private lands within the Potamus subwatersheds as identified in the Morrow County Community Wildfire Protection Plan.
Fuels management
Objection Period Start
04/2013 (Estimated)
Decision
06/2013 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T5S R28E, T5S R29E, T6S R28E, and T6S R29E |
Decision Memo · Heppner Ranger District · updated 6/7/2018
Umatilla National Forest, Heppner Ranger District. Approximately 16 miles southeast of the town of Heppner, OR. · Morrow, Oregon
The Rhea Thin project proposes to reduce stocking levels by using a commercial timber sale. This project consists of two thinning units totaling approximately 70 acres located along the 2100050 road.
Forest products
Scoping Start
03/2013 (Estimated)
Decision
07/2013 (Estimated)
Implementation
08/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Township 5 S., Range 28 E., Section 7 |
Decision Memo · North Fork John Day Ranger District · updated 4/23/2018
Located in the Central Desolation Allotment on the NFJD Ranger District. Access to the fence will be from USFS road 130. · Grant, Oregon
Remove an existing 1.25 mile fence on the Central Desolation Allotment that has exceeded its life expectancy and is no longer in a condition that it can be maintained. This project proposes to build a shorter fence route to connect with private land
Facility management
Decision
04/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Township 07 South Range 32 East, Sections 4, 5 |
Environmental Impact Statement · North Fork John Day Ranger District · updated 1/2/2018
This project is located within the Granite Creek Watershed on the Umatilla and Wallowa-Whitman National forests · Grant, Oregon
This fuels reduction project is located within the Granite Creek Watershed on the Umatilla and Wallowa-Whitman National forests and is located in Grant County, Oregon.
Fuels management
NOI in Federal Register
08/22/2014
DEIS NOA in Federal Register
10/21/2016
FEIS NOA in Federal Register
06/23/2017
Objection Period Start
06/23/2017
Decision
12/2017 (Estimated)
Implementation
04/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Ten Cent Community Wildfire Protection Project, Record of Decision (PART A) | Decision Signed Date: 12/29/2017 |
| Forests | Umatilla National Forest; Wallowa-Whitman National Forest |
| Districts | North Fork John Day Ranger District; Whitman Ranger District |
| Legal Land Description | The project area is located in Grant County, Oregon, in the: Southeast corner of Township 8, South Range 34 East |
Environmental Assessment · Heppner Ranger District · updated 9/26/2017
Located in the southern portion of the Heppner Ranger District in portions of the Wall Creek and Lower John Day River/Kahler Creek watersheds within Grant and Wheeler counties. · Grant; Wheeler, Oregon
There is a need to continue authorization of livestock grazing consistent with the goals and objectives of the Umatilla National Forest Land and Resource Management Plan (Forest Plan) to maintain or improve resource conditions.
Grazing management
Comment Period
12/20/2016
Objection Period Start
08/01/2017
Decision
09/2017 (Estimated)
Implementation
10/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Grazing, Rescissions Act Of 1995 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management; Grazing Authorizations; Grazing Structural Improvements |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T7S, R25E, Sec 13, 14, & 24-26 T7S, R26E, Sec 21, & 26-36 T8S, R25E, Sec 1, 2, & 11-14 T8S, R26E, Sec 2-11, & 14-22, & 28-30 Willamette Meridian Surveyed |
Decision Memo · Walla Walla Ranger District · updated 9/6/2017
The Morning Sun Cistern is located in Umatilla County, off Hwy 204, near Langdon Lake. · Umatilla, Oregon
The Langdon Lake Water Cooperative is requesting to repair a leaking cistern, located on Forest Service lands near Langdon Lake, Oregon.
Special use management
Decision
09/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N, R38E |
Environmental Assessment · Walla Walla Ranger District · updated 7/20/2017
The project area is approximately 9,550 acres in size and is within the Tiger and Webb Creek drainages of the Middle Mill Creek and North Fork Walla Walla River subwatersheds, on Forest Road 65. · Umatilla, Oregon
Project would have reduced vertical and horizontal fuel loading and continuity to modify potential fire behavior and approach or attain the desired objectives near and along the 6511 roads and MFTPs. Activities proposed were thinning and burning.
Fuels management
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Biomass; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Township 5 North, Range 38 East, Sections 1, 2, 3, 4, 9, 10, 11; and Township 6 North, Range 38 East, Sections 20, 21, 27, 28, 29, 30, 32, 33, 34, 35 |
Decision Memo · Umatilla National Forest All Units · updated 7/18/2017
Umatilla National Forest, Oregon and Washington · Grant; Morrow; Umatilla; Union; Wallowa; Wheeler; Asotin; Columbia; Garfield; Walla Walla, Oregon; Washington
Amend the Forest Plan to include the use of Aminopyralid in herbicide application on the Umatilla NF.
Land management planningVegetation management (other than forest products)Grazing management
Comment Period
11/26/2016
Objection Period Start
03/11/2017
Decision
05/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (16), 36 Cfr 220.6(E)(16) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Forest Vegetation Improvements; Grazing Allotment Management; Plan Amendment; Noxious Weed Treatments |
| Forest Plan Amendment for the Addition of Aminopyralid | Decision Signed Date: 05/11/2017 |
| Forests | Umatilla National Forest |
| Districts | Umatilla National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Pomeroy Ranger District · updated 7/18/2017
Forest Service and WA Dept of Fish and Wildlife land in Garfield and Asotin Counties, WA · Asotin; Garfield, Washington
Implement prescribed fire on approx. 7900 acres of FS land & 2400 acres of WA Dept of Fish and Wildlife land to reduce fuels (ground, ladder, canopy biomass) and rehabilitate grass and shrubs to improve wildlife forage.
Fuels management
Decision
03/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | T9N,R4E, Sections 14-16, 21-23, 24-28 and 35; T9N, R43E Sections 2-4, 9-10 and; T9N, R44E, Sections 16-17, 19-21 and 30. |
Decision Memo · Heppner Ranger District · updated 7/18/2017
Western edge of the Heppner Ranger District of the Umatilla National Forest. · Wheeler, Oregon
Trees are beginning to interfere with radar transmissions between the FAAs Heppner and Fossil radar stations. Proposal is to cut all trees within a sight path 60 feet wide, unclear as to length of the site path at this time (perhaps 1 mile?).
Facility managementForest products
Decision
04/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Heppner Ranger District · updated 7/18/2017
On the Umatilla National Forest Heppner Ranger District. In the Morphine Ridge area on the east side of the district. T6S, R27E, Sections 28 & 33 · Morrow, Oregon
Approximately 17,000 seedlings will be planted in eighty-eight acres within the Morphine Burn fire scar. These acres are within the suitable timber base.
Vegetation management (other than forest products)Fuels management
Decision
03/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · North Fork John Day Ranger District · updated 7/18/2017
Project located in Umatilla County along the Western Route of the North Fork John Day Ranger District. · Umatilla, Oregon
Project designed to improve conditions for aspen stands in order to retain aspen on the landscape, enhance wildlife habitat, and reduce fuels. The project proposes to remove conifer to create openings around existing aspen stands, and reduce fuels.
Fuels managementForest productsVegetation management (other than forest products)
Decision
05/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Township 45 Range 30 East Sections 28, 29, 33, 32, 34; Township 55 Range 30 East Sections 4, 5, 18, 31; and Township 55 Range 29 East Sections 1, 12, 13, 24 |
Decision Memo · Heppner Ranger District · updated 7/18/2017
Potamus drainage on the Heppner and North Fork John Day Ranger District of the Umatilla National Forest. · Morrow, Oregon
Reduce the risk of stand replacement wildfire by reducing natural fuel loading and ladder fuels and increase forage for big game and livestock by reintroducing fire to the landscape through prescribed fire.
Fuels management
Scoping Start
05/2017 (Estimated)
Decision
04/2018 (Estimated)
Implementation
09/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · North Fork John Day Ranger District · updated 7/18/2017
Located on the north east side of Tower Mountain accessed by Forest Road 5226. · Umatilla, Oregon
Re-issue a SUP allowing continued use/maintenance of the current structure. Allow occasional removal of trees (pre-commercial) to maintain clear path for the repeater and maintenance to the structure. Authorize modification of existing facility.
Facility managementSpecial use management
Decision
04/2017 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Township 6 South, Range 34 East, Section 12; Willamette Principal Meridian |
Decision Memo · North Fork John Day Ranger District · updated 7/18/2017
Approximately 30 miles south of Ukiah on Forest Service Road 5505. · Umatilla, Oregon
Proposing to plant areas within the Turner Basin Fire area with a mixture of ponderosa pine, Douglas-fir, and western larch at a planting density of 200 trees per acre. Trees will be protected from big game browse with vexar tubes.
Vegetation management (other than forest products)
Decision
04/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Township 7 South, Range 32 East, Sections 1; Willamette Principal Meridian |
Decision Memo · Heppner Ranger District · updated 12/15/2016
This project is within the 2015 Collins Butte Fire, overlapping the Wheeler Point Fire Scar. The project lies within Wheeler County, T7S, R24E, Sections 14 & 15. · Wheeler, Oregon
This project proposes post-fire rehabilitation following the 2015 Collins Butter Fire by planning 25,000 ponderosa pine seedlings within the fire area.
Vegetation management (other than forest products)
Decision
07/2016 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (11), 36 Cfr 220.6(E)(11) |
| Special Authority | National Fire Plan - Healthy Forests Initiative Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T7S, R24E, Sections 14 & 15 |
Decision Memo · Walla Walla Ranger District · updated 12/7/2016
Ski Bluewood · Columbia, Washington
Bluewood is proposing to replace a platter pull towing device with up to 3 conveyors to move the beginning skiers and boarders up the slope.
Special use management
Decision
12/2016 (Estimated)
Implementation
12/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T.7N, R.40E, Section 18, W.M. |
Decision Memo · Pomeroy Ranger District · updated 9/30/2016
Approximately 13 linear miles southeast of Dayton, WA. Near Forest Road 4620. · Columbia, Washington
Install post assisted log structures (PALS) with large and small woody debris along lower 1.5 miles of Little Tucannon River to improve habitat diversity and floodplain connection.
Watershed management
Decision
09/2016 (Estimated)
Implementation
10/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Little Tucannon PALS | Decision Signed Date: 09/26/2016 |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | T 9N, R 40E, Section 25 and T 9N, R 41E, section 30 |
Decision Memo · North Fork John Day Ranger District · updated 9/8/2016
T. 6 S. R. 33 E., sections 26, 27, 34, and 35; and T. 7 S., R. 33 E., sections 3 and 10 · Grant; Umatilla, Oregon
Designate 9.6 miles of new OHV trail to provide additional access to the Winom-Frazier OHV Complex from the Oriental Campground. Most of the route would occur on existing open and closed roads, with only 1-2 miles of new construction.
Recreation management
Decision
05/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Follows existing open and closed roads beside Oriental Creek from Oriental Creek Campground on the N. Fork John Day River to the Winom-Frazier OHV Trail system. |
Decision Memo · North Fork John Day Ranger District · updated 9/8/2016
The trail is located within the North Fork John Day Wilderness · Grant, Oregon
Reroute the lower portion of the Paradise Trail to install grade-reducing switchbacks (3.4 miles), bringing the grade from 40% to 10-15% for the entire trail. Decommission 1.1 miles of existing, steep trail.
Recreation management
Decision
03/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T 6 S., R. 34 E. sections 2 and 3. |
Decision Memo · North Fork John Day Ranger District · updated 9/8/2016
Approximately three miles southwest of the town of Granite, OR · Grant, Oregon
This is an existing, un-groomed snowmobile trail. In order to groom the trail, a bridge will be constructed over Ruby Creek and trees less than six inches DBH along each side of the trail will be removed to a 14-foot width.
Recreation management
Scoping Start
02/2012 (Estimated)
Decision
05/2013 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T9S R35E Secs 14, 15, 17 & 18 |
Decision Memo · Walla Walla Ranger District · updated 8/18/2016
Walla Walla County, Table Rock Lookout · Walla Walla, Washington
Project would issue a special use permit to the City of Walla Walla to install a radio repeater at the Table Rock Lookout.
Special use management
Decision
08/2016 (Estimated)
Implementation
09/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Township 7 North, Range 39 East, Section 3 |
Decision Memo · Walla Walla Ranger District · updated 8/18/2016
On the west side of Indian Ridge between the Indian Ridge Trail and Forest Road 65,outside of the Mill Creek Watershed hydrologic boundary, on the west edge of the Mill Creek Inventoried Roadless Area · Umatilla, Oregon
Install a self-contained remote reporting weather station at a point on Indian Ridge to be able to respond to weather changes that could affect the snowpack in the Mill Creek Watershed and lead to flooding conditions in Mill Creek.
Special use management
Decision
08/2016 (Estimated)
Implementation
08/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T.6N., R.38E., Section 26, NW ¼ |
Decision Memo · Walla Walla Ranger District · updated 8/18/2016
The project is located in Union County, Oregon, at the Spout Springs Communication site on the Walla Walla Ranger District, Umatilla National Forest. · Union, Oregon
The proposed action is to issue a new communications site lease to T-Mobile for their new building at the existing approved communications site and the installation of underground utilities to the new building.
Special use management
Decision
08/2016 (Estimated)
Implementation
10/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T.3N., R.38E., Sec. 10 |
Decision Memo · Walla Walla Ranger District · updated 8/15/2016
Power lines run from the forest boundary to the Spout Springs Recreation Residences, the Spout Springs Ski Area, and to the Spout Springs Communications Sites. · Umatilla, Oregon
Convert 3,200 feet of overhead electric line to underground.
Special use management
Decision
07/2016 (Estimated)
Implementation
08/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T.4N., R.38E., portions of sections 32 & 33; and T.3N., R38E., portions of section 10. |
Environmental Impact Statement · Heppner Ranger District · updated 6/27/2016
Kahler Creek watershed, Heppner Ranger District. Wheeler and Grant Counties. · Grant; Wheeler, Oregon
The Kahler Dry Forest Restoration project seeks to restore dry upland forest conditions throughout the Kahler Creek watershed through a combination of thinning and prescribed burning.
Vegetation management (other than forest products)Forest products
NOI in Federal Register
03/11/2013
DEIS NOA in Federal Register
11/29/2013
FEIS NOA in Federal Register
01/29/2016
Objection Period Start
02/05/2016
Decision
06/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Rangeland Vegetation Improvements; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T7S, R24E, Sec 13, 14; T7S, R24E, Sec 8-18, 20-24; T7S, R25E, Sec 4-10, 14-27, 34-36; T7S, R26E, Sec 31; T8S, R25E, Sec 1, 2, 11-14; T8S, R26E, Sec 5-30, 33-35 |
Decision Memo · North Fork John Day Ranger District · updated 5/31/2016
301 East Waid Street, Ukiah, OR, 97880 · Umatilla, Oregon
Selling of the Forest Service owned house located at 301 East Waid Street, Ukiah, Oregon. This proposed conveyance is authorized under the Forest Service Facility Realignment and Enhancement Act of 2005
Facility managementLand ownership management
Decision
05/2016 (Estimated)
Implementation
05/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (7), 36 Cfr 220.6(D)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance; Land Exchanges |
| NFJD Waid Street House Conveyance Decision Memo | Decision Signed Date: 05/11/2016 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Section 14, Township 5 South, Range 31 East, Willamette Meridian Surveyed |
Decision Memo · North Fork John Day Ranger District · updated 5/13/2016
Granite and Desolation Watersheds · Grant, Oregon
The project will include aquatic restoration, instream work, meadow restoration, pre-commercial thinning, riparian planting, and road decommissioning.
Watershed management
Decision
05/2016 (Estimated)
Implementation
06/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (7), 36 Cfr 220.6(E)(7); 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Walla Walla Ranger District · updated 4/25/2016
T. 6 N., R. 41-42 E. and T. 5 N., R. 41-42 E. within Wallowa County, OR. Approx. 8 linear miles west of town of Troy, OR and 25 linear miles north of town of Wallowa, OR. · Wallowa, Oregon
Salvage fire-killed and fire-injured trees on approximately 250 acres and reforestation activities on (up to) 6,000 acres that were affected by the Grizzly Bear Complex Fire.
Vegetation management (other than forest products)
Decision
04/2016 (Estimated)
Implementation
04/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Pomeroy Ranger District · updated 3/17/2016
Approximately 5 miles northwest of the town of Troy, Oregon. · Wallowa; Garfield, Oregon; Washington
Salvage fire-killed and fire-injured trees on approximately 250 acres and reforestation activities on (up to)900 acres that were affected by the Grizzly Bear Complex Fire.
Vegetation management (other than forest products)
Decision
03/2016 (Estimated)
Implementation
06/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Not Applicable |
Environmental Impact Statement · Walla Walla Ranger District · updated 1/13/2016
T. 6 N., R. 41-42 E. and T. 5 N., R. 41-42 E. within Wallowa County, OR. Approx. 5 linear miles west of town of Troy, OR and 25 linear miles north of town of Wallowa, OR. · Wallowa, Oregon
Harvest fire-killed and fire-injured trees on approximately 2,000 acres and plant trees and other vegetation on approximately 4,400 acres on Walla Walla Ranger District affected by the Grizzly Bear Complex Fire.
Vegetation management (other than forest products)
NOI in Federal Register
12/2015 (Estimated)
DEIS NOA in Federal Register
05/2016 (Estimated)
FEIS NOA in Federal Register
08/2016 (Estimated)
Objection Period Start
08/2016 (Estimated)
Decision
12/2016 (Estimated)
Implementation
01/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · North Fork John Day Ranger District · updated 9/30/2015
Upper Five Mile Sub Watershed (170702020604) of the Lower Camas Creek Watershed (1707020206) of the North Fork John Day Sub-Basin (17070202). · Morrow; Umatilla, Oregon
Precommercial thinning of small diameter trees, on average less than 9 inches in diameter at breast height, is being proposed. Proposed thinning (135acres) would occur along the scenic Byway (Western Route) that were either planted or have natural
Fuels management
Decision
06/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| 53 Road Pre-Commercial Thinning Project Decision Memo | Decision Signed Date: 06/01/2015 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Upper Five Mile Sub Watershed (170702020604) of the Lower Camas Creek Watershed (1707020206) of the North Fork John Day Sub-Basin (17070202). |
Environmental Impact Statement · Walla Walla Ranger District · updated 9/11/2015
Located within Tollgate Wildland Urban Interface, established in Umatilla County CWPP · Umatilla, Oregon
The project seeks to conduct fuels reduction activities within the Tollgate Wildland Urban Interface (WUI).
Fuels management
NOI in Federal Register
10/19/2010
DEIS NOA in Federal Register
12/31/2012
FEIS NOA in Federal Register
12/13/2013
Objection Period Start
12/13/2013
Decision
06/2014 (Estimated)
Implementation
07/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Pomeroy Ranger District · updated 7/31/2015
Entire mainstem of the Wenaha River approximately 22 miles · Wallowa, Oregon
Develop a comprehensive river management plan for Wenaha River which is part of the Wild and Scenic River System.
Special area management
Comment Period
10/21/2014
Objection Period Start
02/17/2015
Decision
07/2015 (Estimated)
Implementation
07/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Area Management |
| Wenaha Wild and Scenic River Management Plan Environmental Assessment | Decision Signed Date: 07/02/2015 |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Heppner Ranger District · updated 7/21/2015
Heppner Ranger District - Approximately 17 miles southeast of Heppner · Morrow, Oregon
The Herren Thin project proposes to reduce stocking levels by using a commercial timber sale. This project consists of one thinning unit totaling approximately 70 acres located along the 5326020 road.
Forest products
Decision
07/2015 (Estimated)
Implementation
07/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Herren DM | Decision Signed Date: 07/20/2015 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Township 4 S., Range 28 E., Sections 25 & 26 |
Decision Memo · Heppner Ranger District · updated 7/6/2015
Heppner Ranger District, approximately 25 miles from the town of Heppner, OR. · Morrow, Oregon
The Smith Commercial Thin project proposes to reduce stocking levels by using a commercial timber sale. This project consists of one thinning unit totaling approximately 70 acres in size located north of the 5300750 road and east of the 5300252 road.
Forest products
Scoping Start
03/2013 (Estimated)
Decision
07/2013 (Estimated)
Implementation
08/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T 4 S, R 28 E, Section 25 and 26 |
Decision Memo · Walla Walla Ranger District · updated 2/3/2015
On China Creek in Mill Creek drainage. Size is 0.10 acres · Umatilla, Oregon
The project would issue a new special use permit for the operations and maintenance of the existing water line and diversion for a term of 20-years, with the new permit expiring December 31, 2036.
Special use management
Decision
01/2015 (Estimated)
Implementation
02/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | NE Corner of the NW 1/4, SW 1/4 of Sec 21, T6N, R38E, W.M. |
Decision Memo · North Fork John Day Ranger District · updated 11/18/2014
Township 7 South, Range 31 East, Sections 6, Willamette Meridian surveyed, Grant County, Oregon. · Grant, Oregon
The Bone Point Repeater Placement project would move the Forest Service radio repeater from the lookout building to a ground level building designed specifically for housing and protecting the equipment.
Facility management
Decision
08/2014 (Estimated)
Implementation
12/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Township 7 South, Range 31 East, Sections 6, Willamette Meridian surveyed, Grant County, Oregon. |
Decision Memo · Heppner Ranger District · updated 11/18/2014
Approximately ¬¬14 aerial miles southeast of Heppner, and consist of .02 acres and is 589 ft long and 15 ft. wide. This area is north of Black Mountain and west of Arbucle Mountain on the edge of Blake%u2019s Range. · Umatilla, Oregon
Re-issue the permit for a pipeline and spring development for livestock and domestic use.
Grazing management
Decision
08/2014 (Estimated)
Implementation
12/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T. 4S., R. 28E., Sec. 14 of the Willamette Principle Meridian |
Decision Memo · Walla Walla Ranger District · updated 10/30/2014
At Summer homes adjacent to OR HWY 204 · Union, Oregon
This project would isolate a spring and associated wet area with poor drainage from the snowmobile trail. This would be accomplished by placing pit run aggregate and filter cloth in layers over the trail so it will be able to freeze.
Recreation management
Scoping Start
10/2014 (Estimated)
Decision
02/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N, R38E, S10, SW of NE |
Decision Memo · Walla Walla Ranger District · updated 10/30/2014
Spout Springs Communications Site, Size 0.1 acres. · Union, Oregon
The project proposes to install security chain link fence around a cellular tower and propane tank that provides fuel for an auxiliary generator. A backhoe and jackhammer would be used to dig holes for the posts and a trench for ground wire.
Special use management
Decision
06/2014 (Estimated)
Implementation
12/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Verizon Wireless Fence Project | Decision Signed Date: 06/05/2014 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T.3N., R38E. Sec 15. NE 1/4 |
Environmental Assessment · Heppner Ranger District · updated 7/14/2014
Central portion of the district approximately 14 miles north of the town of Monument; Penland Lake, Ditch Creek area · Grant; Morrow, Oregon
Authorization for the continued cattle grazing of the Swale Creek Allotment.
Grazing management
Comment Period
09/04/2013
Decision
07/2014 (Estimated)
Implementation
07/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Grazing, Rescissions Act Of 1995 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management |
| Swale Creek Permit Renewal and Allotment Management Plan | Decision Signed Date: 07/14/2014 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T 5 S., R 27 E., Sections 13, 14, 22-27, and 34-36; T. 5 S., R28E., Sections 17-20, and 29-33; T. 6 S., R 27 E., Sections 1, 2, 11-14 and 22-26; T. 6 S., R 28 E., Sections 3-11, 15- 22 and 28-33; a |
Decision Memo · North Fork John Day Ranger District · updated 7/9/2014
FS 3986-022 T8S R32E sec.18 Willamette Meridian · Grant, Oregon
This proposal would address the removal of the failing road-stream crossing at Little Indian Creek and Forest Service road 3986-022
Wildlife, fish, rare plants
Decision
07/2014 (Estimated)
Implementation
07/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (19), 36 Cfr 220.6(E)(19); 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Little Indian Creek Culvert Removal | Decision Signed Date: 07/07/2014 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T8S R32E sec.18 Willamette Meridian |
Decision Memo · Walla Walla Ranger District · updated 6/24/2014
Southeast of Lookout Mountain, situated between National Forest system road 6200000 and the Grande Ronde river. · Union; Wallowa, Oregon
The project objective is to reduce hazardous fuels along a strategic landscape break according to the Forest Landscape Wildfire Strategy which seeks increased defensibility in key areas, as well as retention of large, fire resistant trees. 1,531 ac.
Fuels managementVegetation management (other than forest products)
Decision
06/2014 (Estimated)
Implementation
09/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Decision Memo for Grande Ronde Landscape Burn | Decision Signed Date: 06/19/2014 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N R40E sec. 1, 2, 10, 11, 12, 14 & T5N R40 E sec. 24, 25, 36 & T5N R41E sec. 18, 19, 20, 21, 28, 29 |
Decision Memo · Pomeroy Ranger District · updated 11/13/2013
Pomeroy District · Asotin; Columbia; Garfield, Washington
Reduce stocking levels in timbered stands without removal of any material. Work will be done by hand using chainsaws.
Vegetation management (other than forest products)Fuels management
Comment Period
08/08/2013
Decision
11/2013 (Estimated)
Implementation
03/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements |
| Non-Commercial Thinning Project | Decision Signed Date: 11/11/2013 Legal Notice Date: 11/12/2013 |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
Decision Memo · Walla Walla Ranger District · updated 9/19/2013
West of Palmer Junction · Union, Oregon
Landscape prescribed fire proposal on NFS lands that are adjacent to private property. Project activities would be designed to reduce fine dead fuel loading, tree densities, and ladder fuels. Project area covers approximately 5,000 acres.
Fuels managementVegetation management (other than forest products)
Comment Period
04/13/2013
Decision
09/2013 (Estimated)
Implementation
09/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Balloon Cabin Landscape Prescribed Burn Project | Decision Signed Date: 09/12/2013 Legal Notice Date: 09/19/2013 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T3N; R39E; Sections 16, 17, 19, 20, 21, 28, 29, 30, 31, 32 |
Environmental Assessment · North Fork John Day Ranger District · updated 8/8/2013
10 miles east of Ukiah, Oregon, off the 53 road system, Deerlick Creek and Wilkins Creek drainages. · Umatilla, Oregon
Restore upland forest conditions, encourage growth of large trees, and move the analysis area towards its Historical Range of Variability (HRV) in tree density, species composition and stand structure using commercial and noncommercial thinning.
Forest productsFuels managementVegetation management (other than forest products)
Comment Period
02/19/2013
Decision
07/2013 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T5S, R30E multiple sections including 3, 10, 11, 14 , 15, 22, 23, 26, 27 |
Decision Memo · North Fork John Day Ranger District · updated 7/11/2013
Umatilla County, North Fork John Day Ranger District, approximately 6 miles south of the town of Ukiah. · Umatilla, Oregon
Protect the sensitive riparian area around a spring from being trampled by cattle. A permanent fence will be constructed around the one acre area. This will improve aquatic habitat for spotted frogs, and shrub habitat for neotropical migratory birds.
Grazing managementWildlife, fish, rare plants
Comment Period
03/07/2013
Decision
04/2013 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Grazing Structural Improvements |
| 2013 North Fork John Day Spring Development Project | Decision Signed Date: 04/15/2013 Legal Notice Date: 04/19/2013 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Township 76 South, Range 32 East, Section 16 |
Decision Memo · Walla Walla Ranger District · updated 4/8/2013
Located along Forest Road 6406 · Union, Oregon
Project proposes commerical thinning activities on approximately 60 acres. Project activities would occur within the footprint of an old clearcut unit which was harvested in the 1960s.
Forest products
Comment Period
07/22/2012
Decision
04/2013 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Green) |
| Swamp Creek Commercial Thin | Decision Signed Date: 04/03/2013 Legal Notice Date: 04/06/2013 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N; R38E: Section 25 |
Decision Memo · Walla Walla Ranger District · updated 4/3/2013
The project is located in and immediately surrounding the campground facilities on the southwest shores of Jubilee Lake on the Walla Walla Ranger District, Umatilla National Forest., Union County, OR · Union, Oregon
The project would involve the removal of trees that have been identified as hazardous to users of the Jubilee Lake Campground. Removal would occur in 2013 across approximately 50 acres in and around the campground.
Facility managementRecreation managementVegetation management (other than forest products)
Comment Period
12/11/2012
Decision
03/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Forest Vegetation Improvements; Facility Maintenance; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Township 4 North, Range 39 East, Section 17 |
Decision Memo · North Fork John Day Ranger District · updated 3/29/2013
The project areas are located on the North Fork John Day Ranger District in Grant County, T. 7 S., R. 31 E., Sections 22 and 27, and at T. 8S., R. 32 E., Sections 17 and 18, south of the town of Ukiah · Grant, Oregon
This project will include construction of approximately 2.1 miles of fence to limit cattle access to designated critical habitat for steelhead along Smith Creek and Little Indian Creek.
Grazing managementWildlife, fish, rare plants
Decision
03/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| North Fork John Day 2013 Riparian Improvement Project | Decision Signed Date: 03/19/2013 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T. 7 S., R. 31 E., Sections 22 and 27, and at T. 8S., R. 32 E., Sections 17 and 18 |
Decision Memo · Heppner Ranger District · updated 10/19/2012
Approximately 22 miles SE of the town of Heppner, OR. · Morrow, Oregon
The Swale Commercial Thin project proposes to reduce stocking levels by using a commercial timber sale. This project consists of one unit of approximately 70 acres in size.
Forest products
Comment Period
06/12/2012
Decision
10/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T. 6 S., R. 28 E., Sections 3, 4, and 10 |
Decision Memo · Walla Walla Ranger District · updated 9/27/2012
Located on SF Walla Walla Trail. · Umatilla, Oregon
This project proposes routine trail maintenance in the form of replacing a native log stringer bridge with a pressure treated glue-laminated bridge. The proposal does not proposes changes to the existing authorized uses of the trail.
Recreation management
Decision
06/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| South Fork Walla Walla Trail Bridge Replacement Project | Decision Signed Date: 06/12/2012 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T4N., R37E., Section 14 |
Decision Memo · Walla Walla Ranger District · updated 8/24/2012
Loon timber sale unit #23 · Union, Oregon
Project would install a long-term (30-year) forest productivity study examing forest nutrient management issues. The study is led by the Intermountain Forest Tree Nutrition Cooperative which is headquartered at the University of Idaho.
ResearchVegetation management (other than forest products)
Decision
08/2012 (Estimated)
Implementation
08/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Research And Development |
| Site Productivity Research Study Project | Decision Signed Date: 08/24/2012 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T.3N., R.39E., Section 30 |
Decision Memo · Walla Walla Ranger District · updated 8/21/2012
Spout Springs Electronics Site · Union, Oregon
Project proposes the issuance of a special use permit to Umatilla Electric Cooperative for the installation of an underground powerline at the Spout Springs Electronics site that will provide power to an existing US Cellular cell phone facility.
Special use management
Comment Period
06/22/2012
Decision
08/2012 (Estimated)
Implementation
08/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Spout Springs Underground Powerline Special Use Permit Project | Decision Signed Date: 08/06/2012 Legal Notice Date: 08/16/2012 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T3N., R38E., Section 15 |
Decision Memo · Walla Walla Ranger District · updated 8/21/2012
Ski Bluewood · Columbia, Washington
Project proposes the issuance of an amended special use permit to Verizon Wireless for the installation of a 12,000 gallon propane tank and associated structures at the existing cell phone site located at Ski Bluewood.
Special use management
Comment Period
06/22/2012
Decision
08/2012 (Estimated)
Implementation
08/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Verizon Propane Tank Replacement Project | Decision Signed Date: 08/06/2012 Legal Notice Date: 08/16/2012 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T7N., R40E., Section 19 NW/SE |
Environmental Impact Statement · Pomeroy Ranger District · updated 7/27/2012
Project planning area is approx. 21,000 acres. Treatments proposed on approx. 4,500 acres. · Asotin; Garfield, Washington
Vegetation management project to improve vigor, health, and fire resistence within a forested ecosystem. It includes timber harvest, treatment of acitivity and natural fuels, landscape prescribed burning, and non-commercial treatments.
Forest productsFuels managementVegetation management (other than forest products)
NOI in Federal Register
03/09/2009
DEIS NOA in Federal Register
02/24/2012
FEIS NOA in Federal Register
07/27/2012
Decision
07/2012 (Estimated)
Implementation
11/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Improvements/Construction; Timber Sales (Green) |
| South George Vegetation and Fuels Management Project | Decision Signed Date: 07/17/2012 Legal Notice Date: 07/27/2012 |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | T7N,R44E,sec1; T7N,R43E,sec 1-2; T8N,R43E,sec 1,2,10-15,21-28,33-36; T8N,R44E,sec 5-8,17-20,26-36; T9N,R43E,sec 35 |
Decision Memo · Heppner Ranger District · updated 7/24/2012
Approximately 32 miles SE of the town of Heppner, OR. · Morrow, Oregon
The Groschen Cabin Commercial Thin project proposes to reduce stocking levels by using a commercial timber sale. This project will use consist of one unit of approximately 70 acres.
Forest products
Comment Period
05/08/2012
Decision
07/2012 (Estimated)
Implementation
08/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T. 6 S., R. 28 E., Sections 2 & 11 |
Decision Memo · Heppner Ranger District · updated 7/24/2012
Approximately 26 miles SE of the town of Heppner, OR. · Morrow, Oregon
The McMurdo Cabin Commercial Thin project proposes to reduce stocking levels by using a commercial timber sale. The project consists of on thinning unit of approximately 70 acres in size.
Forest products
Comment Period
05/09/2012
Decision
07/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Green) |
| McMurdo Cabin Commerical Thin | Decision Signed Date: 07/24/2012 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T. 6 S., R. 29 E., Section 17 |
Environmental Impact Statement · WO - Washington Office - National headquarters · updated 7/10/2012
11 contiguous Western States (Arizona, California, Colorado, Idaho, Montana, New Mexico, Nevada, Oregon, Utah, Washington, and Wyoming) and Alaska. · Bonner; Aleutians East; La Paz; Columbia; Coos; Colusa; Denver; Douglas, Alaska; Arizona; California; Colorado; District of Columbia; Idaho; Kansas; Montana; North Dakota; Nebraska; New Mexico; Nevada; Oklahoma; Oregon; South Dakota; Texas; Utah; Washington; Wyoming
The Forest Service was a cooperating agency, assisting the Bureau of Land Management (BLM) in that Agency's geothermal leasing analysis and decision. The BLM issued a record of decision on 12/17/2008.
Regulations, directives, orders
NOI in Federal Register
06/13/2007
DEIS NOA in Federal Register
06/13/2008
FEIS NOA in Federal Register
10/24/2008
Decision
02/2010 (Estimated)
Implementation
03/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Regulation Creation/Modification |
| Forests | Beaverhead-Deerlodge National Forest; Bitterroot National Forest; Clearwater National Forest; Custer National Forest; Custer Gallatin National Forest; Helena National Forest; Lewis And Clark National Forest; Lolo National Forest; Nez Perce-Clearwater National Forest; Grand Mesa, Uncompahgre and Gunnison National Forests; Medicine Bow-Routt National Forest; Rio Grande National Forest; Arapaho and Roosevelt National Forests; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands; San Juan National Forest; White River National Forest; Apache-Sitgreaves National Forests; Carson National Forest; Cibola National Forest; Coronado National Forest; Gila National Forest; Lincoln National Forest; Santa Fe National Forest; Tonto National Forest; Boise National Forest; Bridger-Teton National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Payette National Forest; Salmon-Challis National Forest; Sawtooth National Forest; Caribou-Targhee National Forest; Humboldt-Toiyabe National Forest; Uinta-Wasatch-Cache National Forest; Angeles National Forest; Cleveland National Forest; Eldorado National Forest; Inyo National Forest; Klamath National Forest; Lassen National Forest; Los Padres National Forest; Mendocino National Forest; Modoc National Forest; Plumas National Forest; San Bernardino National Forest; Sequoia National Forest; Shasta Trinity National Forest; Sierra National Forest; Tahoe National Forest; Deschutes National Forest; Fremont-Winema National Forest; Gifford Pinchot National Forest; Malheur National Forest; Mt Baker-Snoqualmie National Forest; Mt. Hood National Forest; Ochoco National Forest; Rogue River-Siskiyou National Forest; Umatilla National Forest; Umpqua National Forest; Wallowa-Whitman National Forest; Okanogan-Wenatchee National Forest; Willamette National Forest; R10 - Alaska Region All Units; WO - Washington Office - National headquarters |
| Districts | Beaverhead-Deerlodge National Forest All Units; Bitterroot National Forest All Units; Clearwater National Forest All Units; Custer National Forest All Units; Custer Gallatin National Forest; Custer Gallatin National Forest All Units; Helena National Forest All Units; Lewis And Clark National Forest All Units; Lolo National Forest All Units; Nez Perce-Clearwater National Forest All Units; Grand Mesa Uncompahgre and Gunnison National Forest All Units; Medicine Bow-Routt National Forest All Units; Rio Grande National Forest All Units; Arapaho and Roosevelt National Forests All Units; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands All Units; San Juan National Forest All Units; White River National Forest All Units; Apache-Sitgreaves National Forests All Units; Carson National Forest All Units; Cibola National Forest All Units; Coronado National Forest All Units; Gila National Forest All Units; Lincoln National Forest All Units; Santa Fe National Forest All Units; Tonto National Forest All Units; Boise National Forest All Units; Bridger-Teton National Forest All Units; Dixie National Forest All Units; Fishlake National Forest All Units; Manti-La Sal National Forest All Units; Payette National Forest All Units; Salmon-Challis National Forest All Units; Sawtooth National Forest All Units; Caribou-Targhee National Forest All Units; Humboldt-Toiyabe National Forest All Units; Uinta-Wasatch-Cache All Units; Angeles National Forest All Units; Cleveland National Forest All Units; Eldorado National Forest All Units; Inyo National Forest All Units; Klamath National Forest All Units; Lassen National Forest All Units; Los Padres National Forest All Units; Mendocino National Forest All Units; Modoc National Forest All Units; Plumas National Forest All Units; San Bernardino National Forest All Units; Sequoia National Forest All Units; Shasta Trinity National Forest All Units; Sierra National Forest All Units; Tahoe National Forest All Units; Deschutes National Forest All Units; Fremont-Winema National Forest All Units; Gifford Pinchot National Forest All Units; Malheur National Forest All Units; Mt Baker-Snoqualmie National Forest All Units; Mt. Hood National Forest All Units; Ochoco National Forest All Units; Rogue River-Siskiyou National Forest All Units; Umatilla National Forest All Units; Umpqua National Forest All Units; Wallowa-Whitman National Forest All Units; Okanogan-Wenatchee National Forest All Units; Willamette National Forest All Units; R10 - Alaska Region All Units; WO - Washington Office - National headquarters |
Decision Memo · Pomeroy Ranger District · updated 3/12/2012
Area east of Forest road 40 from the junction of the 40 and 44 road. North of Monument Ridge. NW of Indian Tom Trail. South of road 43. · Asotin; Garfield, Washington
Implement prescribed fire on approx. 7,600 acres to reduce ground fuel accumulations, tree densities, and ladder fuels. Reduce canopy biomass to historical levels, improve timber stand resistance to disease and insects, and improve wildlife forage.
Wildlife, fish, rare plantsFuels management
Decision
02/2012 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Wenatchee Prescribed Fire Project | Decision Signed Date: 02/22/2012 |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | T7N, R43E, Sections 1-6 and 8-12; T7N, R44E, Sections 6 and 7; and T8N, R43E, Sections 31-35 |
Environmental Assessment · Heppner Ranger District · updated 3/9/2012
Selected roads throughout the Wall Creek Watershed, including the 21, 23, and 24 roads and their associated secondary roads. · Grant; Morrow; Wheeler, Oregon
Reconstruction, decommissioning, storm damage risk reduction including culvert removal and waterbar construction, and aquatic organism passage improvement on selected roads throughout the Wall Creek watershed.
Wildlife, fish, rare plantsWatershed managementRoad management
Comment Period
01/24/2012
Decision
03/2012 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Species Habitat Improvements; Road Maintenance; Road Improvements/Construction; Watershed Improvements |
| Wall Creek Road and Watershed Improvement DN | Decision Signed Date: 03/07/2012 Legal Notice Date: 03/08/2012 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T6S, R26E, Sec 13, 24, 25, 36, T6S, R27E, Sec 8, 9, 15, 16, 24, 31, 32, T6S, R28E, Sec 4,T7S, R26E, Sec 6-9, 15, 17, 18, 22, 24, 27, 31-34, T7S, R27E, Sec 5-9, 17, 19, 32, 33, T8S, R26E, Sec 9, 13 |
Decision Memo · North Fork John Day Ranger District · updated 1/5/2012
North Fork John Day Ranger District- District wide · Grant; Umatilla, Oregon
Pocket gophers are causing measurable damage and mortality to conifer seedlings in reforestation units. The goal of this project is to reduce gopher populations within reforestation units using mechanical traps.
Vegetation management (other than forest products)
Decision
01/2012 (Estimated)
Implementation
04/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Decision Memo - District Wide Gopher Trapping | Decision Signed Date: 01/05/2012 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T3SR32Es25,28- 34T3SR33Es15,T4SR30Es29,31-32,T4 SR32Es3,6,10,13, T4SR33Es6,28,33,T5SR33Es4-5,9,T6SR29Esec14-15,T6SR32Es24,T6SR33Es17-21, 33,T7SR31Es4,T7SR33Es18,29-31,T8SR33Es31-33,T9SR33Es4-6,9 |
Environmental Impact Statement · Walla Walla Ranger District · updated 9/9/2011
NW of Elgin, OR · Umatilla; Union; Wallowa, Oregon
This project proposes the continuation of a livestock (sheep) grazing permit in the North End Allotment.
Grazing management
NOI in Federal Register
12/24/2009
DEIS NOA in Federal Register
02/11/2011
FEIS NOA in Federal Register
09/09/2011
Decision
08/2011 (Estimated)
Implementation
01/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Grazing, Rescissions Act Of 1995 |
| Notice and Comment Regulation | 215 |
| Project Activity | Grazing Allotment Management; Grazing Authorizations; Grazing Structural Improvements |
| North End Sheep Allotment Record of Decision | Decision Signed Date: 08/24/2011 Legal Notice Date: 09/09/2011 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
Decision Memo · Pomeroy Ranger District · updated 9/8/2011
Located near Tallow Flats · Columbia, Washington
Salvage harvest dead and dying trees on approximately 250 acres.
Forest products
Decision
09/2011 (Estimated)
Implementation
09/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Salvage) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Portions of Secs. 2, 11, 13, and 14, T8N, R40E and Sec 9 T9N, R40E. |
Decision Memo · North Fork John Day Ranger District · updated 9/1/2011
Umatilla County, OR. Approximately 15 miles west of Ukiah in the upper Owens Creek watershed. · Umatilla, Oregon
Commercial thinning on approx. 67 acres to improve forest health. This unit has been identified as at risk of mortality from insects, disease and wildfire due to the dense overstocked stand condition. No trees over 21” diameter will be removed.
Vegetation management (other than forest products)Fuels managementForest products
Decision
09/2011 (Estimated)
Implementation
09/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | W ½, S22, T4S, R30E |
Environmental Assessment · North Fork John Day Ranger District · updated 8/16/2011
Indian Creek watershed near Dale, Oregon · Grant, Oregon
Analysis of Indian Creek watershed to improve the long-term sustainability and fire resistance of upland forests while capturing the commercial value of raw wood material.
Vegetation management (other than forest products)Forest products
Comment Period
09/23/2010
Decision
08/2011 (Estimated)
Implementation
11/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T8S R31E, T9S R32E |
Decision Memo · Heppner Ranger District · updated 8/8/2011
Project is located approximately 19 miles northeast of Monument, OR. · Morrow, Oregon
Vegetation treatment that includes approximately 70 acres of commercial thinning.
Forest products
Decision
08/2011 (Estimated)
Implementation
08/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T. 6 S, R. 29 E, Sections 3, 4, 9, and 10. Willamette Meridian |
Decision Memo · Heppner Ranger District · updated 7/25/2011
Project is approximately 11 miles northwest of Spray, OR. · Wheeler, Oregon
Vegetation treatment that includes commercial thinning one unit of approximately 70 acres.
Forest products
Decision
06/2011 (Estimated)
Implementation
07/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Decision Memo Radar Commercial Thin | Decision Signed Date: 06/30/2011 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T. 7 S, R. 23 E, Sections 11-14, Willamette Meridian |
Decision Memo · Walla Walla Ranger District · updated 6/14/2011
Various locations across the District · Umatilla; Union; Wallowa; Columbia; Walla Walla, Oregon; Washington
Project proposes the implementation of a commercial firewood program.
Forest products
Decision
06/2011 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Products Sales |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
Decision Memo · Walla Walla Ranger District · updated 6/14/2011
South of Black Mountain and North of I-84 · Umatilla; Union, Oregon
Non-commercial thinning effort targeted at reducing fuels and enhancing fire resistance in selected stands on the southern portion of the district.
Fuels management
Decision
06/2011 (Estimated)
Implementation
07/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| South End Thin | Decision Signed Date: 06/13/2011 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
Decision Memo · Walla Walla Ranger District · updated 4/11/2011
Meacham Creek between River Miles 6 and 7. · Umatilla, Oregon
Joint effort between Confederated Tribes of Umatilla Indian Reservation and Umatilla NF. Project would restore Meacham Creek to near historic channel configuration while providing protection for railroad infrastructure in the area.
Wildlife, fish, rare plantsWatershed management
Decision
04/2011 (Estimated)
Implementation
04/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Meacham Creek Restoration Project | Decision Signed Date: 04/08/2011 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T2N., R36E., Section 30 (on NFS) and T2N., R36E Section 19 (adjacent, non-FS land) |
Decision Memo · Pomeroy Ranger District · updated 1/4/2011
East side of Pomeroy Ranger District · Garfield, Washington
Salvage of dead and/or dying trees from approximately 250 acres using conventional yarding systems. Less than 0.5 miles of temporary construction would be needed.
Forest products
Decision
01/2011 (Estimated)
Implementation
02/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Salvage) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Portions of Sections 4,5,8,9, and 10; T8N; R42E |
Decision Memo · Pomeroy Ranger District · updated 12/6/2010
Asotin, Columbia and Garfield Counties that have had previous fire treatments and initial treatment areas T7N,R43E,S 1-6 and 8-12,T7N, R44E,S6-7, T8N,R43E,S31-35 · Asotin; Columbia; Garfield, Washington
Implement prescribed fire treatments on approx. 28,000 acres to reduce ground and ladder fuels to maintain and restore vegetation. Multi-year project (10 years). Incorporates the Wenatchee Crk and Pomeroy Mtce prescribed fire projects.
Vegetation management (other than forest products)Fuels management
Decision
04/2011 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
Decision Memo · Heppner Ranger District · updated 10/28/2010
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Wheeler. Project area is about 11 miles Northwest of Spray. · Wheeler, Oregon
Vegetation treatment that includes commercial thinning totaling approximately 70 acres.
Forest products
Decision
10/2010 (Estimated)
Implementation
11/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T. 7 S, R. 23 E, Sections 11 and 12 |
Environmental Impact Statement · Umatilla National Forest All Units · updated 10/18/2010
Forest wide · Grant; Morrow; Umatilla; Union; Wallowa; Wheeler; Asotin; Columbia; Garfield; Walla Walla, Oregon; Washington
Treatment of known and newly discovered invasive plants using herbicide, manual, mechanical, biological, and/or cultural methods. The Forest has approx. 25,000 acres of invasive plants, approx. 18,500 acres is proposed for herbicide treatment.
Vegetation management (other than forest products)
NOI in Federal Register
04/06/2006
DEIS NOA in Federal Register
06/22/2007
FEIS NOA in Federal Register
08/13/2010
Decision
07/2010 (Estimated)
Implementation
03/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements; Noxious Weed Treatments; Rangeland Vegetation Improvements |
| Umatilla National Forest Invasive Plants Treatment Project | Decision Signed Date: 07/07/2010 Legal Notice Date: 08/13/2010 |
| Forests | Umatilla National Forest |
| Districts | Umatilla National Forest All Units |
| Legal Land Description | Forest wide |
Decision Memo · Walla Walla Ranger District · updated 9/2/2010
Spout Springs Ski Area · Union, Oregon
Project would issue a new permit to the National Weather Service for operation of a rain gauge located near the Spout Springs lodge. The permit would be issued for a 20-year term.
Special use management
Decision
07/2010 (Estimated)
Implementation
10/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T.3N., R. 38E., Section 10, N.W. 1/4 |
Decision Memo · Walla Walla Ranger District · updated 9/2/2010
Along watershed break between the Wenaha-Tucannon and Mill Creek · Wallowa; Columbia, Oregon; Washington
Replacement of failing culverts, construction of rolling drain dips, application of spot rock along FR 6400 (Skyline Rd.) from FR 6437 to Washington-Oregon Border.
Road management
Decision
07/2010 (Estimated)
Implementation
10/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T 7N., R 39E., Section 14 to T 6N., R 39E., Section 10 |
Decision Memo · Walla Walla Ranger District · updated 9/2/2010
On the Spout Springs side of Hwy. 204 · Union, Oregon
The project would relocate an existing powerline to an alignment that runs along the edge of the paved parking area on the Spout Springs Ski area side of Hwy 204.
Special use management
Decision
08/2010 (Estimated)
Implementation
10/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Umatilla Electric Cooperative Underground Powerline Replacement | Decision Signed Date: 08/20/2010 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T 3N., R 38E., Section 12 |
Decision Memo · Heppner Ranger District · updated 8/19/2010
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Wheeler. Project area is about 11 miles North of Spray. · Wheeler, Oregon
Vegetation treatment that includes commercial thinning three units totaling approximately 70 acres.
Forest products
Decision
08/2010 (Estimated)
Implementation
09/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T. 7 S, R. 25 E Willamette Meridian |
Environmental Assessment · Walla Walla Ranger District · updated 8/11/2010
Headwaters of Swamp Creek, adjacent to Swamp Creek Material Source: Upper Lookingglass Subwatershed · Union, Oregon
Proposal seeks to improve water quality and riparian function in the headwaters of Swamp Creek while maintaining access to the Swamp Creek rock pit. The proposal will decommission the existing access road and construct less than 1 mile of new road.
Road managementWatershed management
Comment Period
05/14/2010
Decision
07/2010 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Road Improvements/Construction; Watershed Improvements |
| Swamp Creek Pit Access Decision Notice | Decision Signed Date: 07/28/2010 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T 4N., R 38 E., sections 23 & 24 |
Environmental Assessment · Heppner Ranger District · updated 7/27/2010
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Morrow. Project area is about 18 miles south of Heppner. · Grant; Morrow, Oregon
Vegetation and fuels treatment that includes approximately 2200 acres of commercial harvest, 2100 acres of mechanical fuels treatment, approximately 10,300 acres of prescribed fire, and approximately 1100 acres of non-commercial thinning.
Vegetation management (other than forest products)Forest productsFuels management
Comment Period
03/24/2010
Decision
07/2010 (Estimated)
Implementation
10/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Plan Amendment; Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | LEGAL - T 5 S, R 27 and R 28 E and T 6 S, R 27 and 28 E, Willamitte Merdian. |
Decision Memo · Heppner Ranger District · updated 6/29/2010
Roads in this project include 3 unnamed spur roads off 2122-072 near tributaries of Box Canyon Creek, 2 unnamed spur roads off 2202-080 near Box Canyon Creek and Squaw Creek, and the 2202-022. · Grant; Morrow, Oregon
The Heppner Ranger District is proposing to decommission currently closed roads in RHCAs which are no longer needed for future management. This project would also remove 11 stream crossing structures associated with these roads.
Watershed management
Scoping Start
04/2010 (Estimated)
Decision
05/2010 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning; Watershed Improvements |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T7S, R27E, sec 6; T6S, R27, secs 19, 29, 30, 31, 32. |
Decision Memo · North Fork John Day Ranger District · updated 6/15/2010
The 3 federal parcels are all located south and west of Ukiah, OR and west of Hwy 395, the private parcel is located east of Ukiah, OR and north of Hwy 244 along Forest Road 54. · Umatilla, Oregon
Trade three parcels of National Forest land (about 280 acres) for one parcel of privately-owned land (about 320 acres)
Land acquisition
Decision
05/2010 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (7), 36 Cfr 220.6(D)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Land Exchanges |
| Jensen Land-for-Land Exchange | Decision Signed Date: 05/06/2010 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Private parcel= T4S, R33E, Section 16, W.M. Federal parcels= T5S, R31E, Section 20 and T6S, R31E Section 20 W.M. |
Decision Memo · North Fork John Day Ranger District · updated 6/15/2010
North Fork John Day Ranger District · Grant; Umatilla, Oregon
Exchange/sale of about 211 acres of National Forest System land for 160 acres of privately owned land.
Land acquisition
Decision
05/2010 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (7), 36 Cfr 220.6(D)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Land Exchanges |
| Suiste Land-for-Land Exchange | Decision Signed Date: 05/06/2010 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | 2 Federal units at T3S, R31E, Section 34 & T4S, R31E, Section 2, lot 1 to be traded for private units at T7S, R35E, Section 24, lots 1 & 2, & T7S, R35 ?E, Section 21, lot 1 W.M. surveyed |
Environmental Assessment · Walla Walla Ranger District · updated 4/23/2010
Fry Meadows area · Wallowa, Oregon
Lower elevation Forest along the breaks to the Grande Ronde river would utilize prescribed fire and timber harvest to restore ponderosa pine and western larch forest and grasslands and brush along the canyon walls.
Wildlife, fish, rare plantsFuels managementVegetation management (other than forest products)Road managementForest productsWatershed management
Comment Period
04/18/2005
Decision
07/2005 (Estimated)
Implementation
10/2005 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Road Improvements/Construction; Watershed Improvements |
| Lower Sheep Timber Sale and Fire Reintroduction Project | Decision Signed Date: 07/08/2005 Legal Notice Date: 07/11/2005 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T. 4N., R. 40E., T. 4N., R39E., Sec. 1, 12, 13, 24, 25; T. 4N., R.,41E., Sec. 7, 18, 30, 31; T.5N., R.40E., Sec. 31, 32, 33, 28, 29 |
Environmental Assessment · Walla Walla Ranger District · updated 4/21/2010
State Highway 204 north through Balloon Tree across Lookingglass Creek to Lugar Springs and Forest Road 63. · Union, Oregon
A fuels reduction project involving the removal of commercial timber and wood fiber from reducing the density of non-commercial trees, existing and activity fuels, down and standing dead woody debris and aerial fuels.
Fuels managementVegetation management (other than forest products)Forest productsRoad management
Comment Period
02/22/2008
Decision
08/2008 (Estimated)
Implementation
04/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Special Products Sales; Road Maintenance; Timber Sales (Salvage); Timber Sales (Green) |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | Portions of T. 2 N. R. 38E sections 1, 2, 3, 10, 11, 12, 14, and 23; T. 3 N. R. 38 E. sections 11, 12, 13, 14, 23, 24, 25, 26, 34, 35, and 36; T. 3 N. R. 39 E. sections 3, 4, 5, 6, 7, 8, 17, 18, 19, 2 |
Environmental Assessment · Heppner Ranger District · updated 4/21/2010
Boundaries are the 22 road on the west , 21 road on the north, the 2120 on the east to the forest boundary on the south. · Grant; Morrow, Oregon
Commercial thinning of dry site stands to reduce tree competition & improve stand health and vigor. Also Includes non-commerical thinning of young conifer stands to reduce stocking in the understory.
Watershed managementVegetation management (other than forest products)Fuels managementForest products
Comment Period
04/07/2006
Decision
06/2006 (Estimated)
Implementation
09/2006 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Noxious Weed Treatments; Road Maintenance; Road Improvements/Construction; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements |
| Sunflower Bacon Project | Decision Signed Date: 06/23/2006 Legal Notice Date: 06/26/2006 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | T6S, R26 E and 27E. 19,750 acres |
Decision Memo · Walla Walla Ranger District · updated 3/11/2010
Upper S.F. Walla Walla Watershed · Umatilla; Wallowa, Oregon
The project would extend the N.F. Walla Walla trail from FR 6500040 to Deduct Pond and the S.F. Walla Walla trailhead.
Recreation management
Comment Period
07/07/2009
Decision
01/2010 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| New Trail Link from NF Walla Walla Trail to Deduct Pond | Decision Signed Date: 01/19/2010 Legal Notice Date: 01/26/2010 |
| Forests | Umatilla National Forest |
| Districts | Walla Walla Ranger District |
| Legal Land Description | T. 5, 6N., R. 39E., Section 5, 6, & 32 |
Environmental Assessment · Heppner Ranger District · updated 9/18/2009
All areas west of Forest Road 22 · Grant; Morrow; Wheeler, Oregon
Designate routes and areas open to OHV use on areas west of Forest Road 22
Recreation management
Comment Period
01/02/2009
Decision
08/2009 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Travel Management |
| West End OHV Project | Decision Signed Date: 08/24/2009 Legal Notice Date: 08/28/2009 |
| Forests | Umatilla National Forest |
| Districts | Heppner Ranger District |
| Legal Land Description | Townships 6, 7, and 8 South, Ranges 23, 24, 25, 26, and 27 East |
Environmental Assessment · North Fork John Day Ranger District · updated 10/2/2007
Approximately 14 miles east of Ukiah, OR · Umatilla; Union, Oregon
Authorization for the continued grazing of the Hidaway allotment
Grazing management
Comment Period
11/17/2006
Decision
07/2007 (Estimated)
Implementation
06/2008 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Grazing Authorizations |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Township 5&6 South, Range 33-34 East, Willamette Meridian Surveyed |
Environmental Assessment · North Fork John Day Ranger District · updated 6/28/2007
Approximately 10-15 miles southwest of Ukiah, OR · Grant, Oregon
The purpose of the Falls/Meadowbrook Vegetation Management project is to improve vigor, health, and fire resistance in about 6,800 acres of upland ecosystems.
Vegetation management (other than forest products)Forest products
Comment Period
04/13/2007
Decision
06/2007 (Estimated)
Implementation
09/2007 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Timber Sales (Green) |
| Falls Meadowbrook Project | Decision Signed Date: 06/19/2007 Legal Notice Date: 06/22/2007 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Towhship 5-8 South, Range 29-32 East, Willamette Meridian Surveyed |
Environmental Impact Statement · Pomeroy Ranger District · updated 6/20/2007
School Fire Salvage Recovery Project Area · Columbia; Garfield, Washington
Supplemental EIS. To amend the Forest Plan to modify the Eastside Screens wildlife standard at 6d. (2) (a) to define both live and dead trees. This amendment applies to, and only for the duration, of School Fire Salvage Recovery Project
Forest products
NOI in Federal Register
02/26/2007
DEIS NOA in Federal Register
03/09/2007
FEIS NOA in Federal Register
05/11/2007
Decision
06/2007 (Estimated)
Implementation
07/2007 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Salvage) |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |