Timber harvest, other tree cutting activities and fuels treatments to move conditions to desired levels and/or ranges. Utilize existing road system except, 11 miles of temp road, of which utilizes 9 miles on existing road templates.
Location
Project is approx. 16 linear miles southwest of Asotin, WA. Project is primarily bounded by 44 Rd (Smoothing Iron), 41 Rd (Upper Lick Rd), and portion of 42 Rd (Iron Springs).
Project timeline
1
NOI in Federal Register
11/28/2014
2
DEIS NOA in Federal Register
06/01/2018
3
FEIS NOA in Federal Register
12/28/2018
4
Objection Period Start
12/28/2018
5
Decision
05/2019 (Estimated)
6
Implementation
05/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Road Maintenance; Timber Sales (Green) |
| Sunrise Vegetation and Fuels Management | Decision Signed Date: 05/01/2019 |
| Forests | Umatilla National Forest |
| Districts | Pomeroy Ranger District |
| Legal Land Description | Not Applicable |