Decision Memo Completed

55 Road Repair Project

Umatilla National Forest Umatilla, Oregon North Fork John Day Ranger District

An approximately 25 foot portion of the 55 Road shoulder failed during above average precipitation, resulting in a public safety hazard. The proposed action will widen the existing road by excavating into the hillslope approximately 8 to 10 feet.

Location

On USFS Road 55 at Township 06S Range 32E Section 32

Project timeline

1
Scoping Start
03/04/2025
2
Decision
03/2025 (Estimated)
3
Implementation
05/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
55 Road Repair ProjectDecision Signed Date: 03/13/2025
ForestsUmatilla National Forest
DistrictsNorth Fork John Day Ranger District
Legal Land DescriptionNot Applicable
Road management