An approximately 25 foot portion of the 55 Road shoulder failed during above average precipitation, resulting in a public safety hazard. The proposed action will widen the existing road by excavating into the hillslope approximately 8 to 10 feet.
Location
On USFS Road 55 at Township 06S Range 32E Section 32
Project timeline
1
Scoping Start
03/04/2025
2
Decision
03/2025 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| 55 Road Repair Project | Decision Signed Date: 03/13/2025 |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | Not Applicable |