Project timeline
1
Scoping Start
02/2012 (Estimated)
2
Decision
05/2013 (Estimated)
3
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Umatilla National Forest |
| Districts | North Fork John Day Ranger District |
| Legal Land Description | T9S R35E Secs 14, 15, 17 & 18 |