Project timeline
1
Scoping Start
06/13/2016
2
Comment Period
11/26/2016
3
Objection Period Start
03/11/2017
4
Decision
05/2017 (Estimated)
5
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (16), 36 Cfr 220.6(E)(16) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Forest Vegetation Improvements; Grazing Allotment Management; Plan Amendment; Noxious Weed Treatments |
| Forest Plan Amendment for the Addition of Aminopyralid | Decision Signed Date: 05/11/2017 |