Environmental Assessment Completed

Puderbaugh Vegetation Management Project

Wallowa-Whitman National Forest Wallowa, Oregon Hells Canyon NRA

Reduce fuel loadings in the Puderbaugh Ridge vicinity and address Western Pine Beetle conditions in the upper Imnaha River Corridor.

Location

Puderbaugh Ridge and portions of the Imnaha River drainage.

Project timeline

1
Scoping Start
01/21/2010
2
Comment Period
02/05/2014
3
Objection Period Start
04/23/2014
4
Decision
07/2014 (Estimated)
5
Implementation
10/2014 (Estimated)

NEPA / regulatory detail

Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Timber Sales (Salvage); Timber Sales (Green)
ForestsWallowa-Whitman National Forest
DistrictsHells Canyon NRA
Legal Land DescriptionT4S R48E and T5S R48E, W.M.
Fuels managementForest products