Project timeline

1
Scoping Start
01/31/2011
2
Decision
02/2013 (Estimated)
3
Implementation
06/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Population Enhancements
North Fork Catherine Creek Ford/Bridge Replacement ProjectDecision Signed Date: 02/20/2013
ForestsWallowa-Whitman National Forest
DistrictsLa Grande Ranger District
Legal Land DescriptionNF Catherine Creek Subwatersheds 170601040501 & 170601040108