Supplemental EIS will provide additional analysis of cumulative effects. Notice of Intent to prepare a supplemental EIS was published in the Federal Register on January 30, 2013.
Location
Wallowa-Whitman National Forest, Northeast Oregon.
Project timeline
1
NOI in Federal Register
01/30/2013
2
DEIS NOA in Federal Register
03/20/2015
3
FEIS NOA in Federal Register
01/15/2016
4
Objection Period Start
12/04/2015
5
Decision
03/2016 (Estimated)
6
Implementation
04/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Noxious Weed Treatments |
| Wallowa-Whitman National Forest Invasive Plants Treatment Suppplemental EIS | Decision Signed Date: 03/11/2016 |
| Forests | Wallowa-Whitman National Forest |
| Districts | Wallowa-Whitman National Forest All Units |