Replace existing 100 yr old water transmission line, providing potable water to the residents of Baker City.
Location
23 miles in the Elkhorn Mountains approximately 15 miles west of Baker City.
Project timeline
1
Scoping Start
08/25/2014
2
Comment Period
03/11/2016
3
Objection Period Start
06/10/2016
4
Decision
08/2016 (Estimated)
5
Implementation
08/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other; Ira - Inventoried Roadless Area Activities Requiring Chief's Approval |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Mountain Line Replacement Project | Decision Signed Date: 08/02/2016 |
| Forests | Wallowa-Whitman National Forest |
| Districts | Whitman Ranger District |
| Legal Land Description | T 9 S, R 38 E; T 9 E, R 39 E |