Oregon Trail Electric Cooperative is proposing to relocate approx.900 feet of existing underground power line on National Forest land. The proposed work will be confined to the existing 20 ft. right-of-way authorized in the current special use permit
Location
Near OR Hwy 244, near the Grande Ronde River, near the Starkey area.
Project timeline
1
Scoping Start
02/26/2015
2
Decision
07/2015 (Estimated)
3
Implementation
07/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| OTEC Starkey Power line Relocation Project | Decision Signed Date: 07/15/2015 |
| Forests | Wallowa-Whitman National Forest |
| Districts | La Grande Ranger District |
| Legal Land Description | T3S, R35E, Section 36 |