issue a Special Use Permit for a term of 20 years that authorizes Idaho Power to occupy and use National Forest System lands for the purpose of operation and maintenance of a 7.2 kV electric distribution line and the necessary appurtenances thereto.
Location
Approximately 5 miles west of Unity, Oregon.
Project timeline
1
Scoping Start
09/28/2017
2
Decision
01/2018 (Estimated)
3
Implementation
05/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Idaho Power-Elkhorn Electronic Site Distribution Line | Decision Signed Date: 01/29/2018 |
| Forests | Wallowa-Whitman National Forest |
| Districts | Whitman Ranger District |
| Legal Land Description | T. 13 S. R. 36 E. Sec 22, arriving at Elkhorn Communication Site at T. 16 S. R. 35 E. Sec 16. |