The Forest Service proposes to issue a special use permit which would provide terms and conditions under which Idaho Power Company could build and operate a housing facility on approximately 3.5 acres of National Forest Service lands at Circle C.
Location
The project area is in the vicinity of the USFS Pittsburg Landing recreational access area within the HCNRA on the Idaho side of the Snake River, approximately 17 miles northwest of Riggins, Idaho.
Project timeline
1
Scoping Start
06/12/2018
2
Comment Period
05/29/2019
3
Objection Period Start
04/2023 (Estimated)
4
Decision
06/2023 (Estimated)
5
Implementation
06/2023 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Wallowa-Whitman National Forest |
| Districts | Hells Canyon NRA |
| Legal Land Description | Township 27N Range 1W Section 33 |