T-Mobile is proposing cell antennas on ATC owned tower. Antennas will be installed on existing tower and ground equipment will be installed inside new equipment building. New solar panels will be installed to provide power.
Location
Summit Ridge Communications Site/ Halfway, Oregon
Project timeline
1
Scoping Start
06/01/2021
2
Decision
07/2022 (Estimated)
3
Implementation
08/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| T-Mobile/Summit Ridge Communication Site | Decision Signed Date: 07/28/2022 |
| Forests | Wallowa-Whitman National Forest |
| Districts | Whitman Ranger District |
| Legal Land Description | T8S, R45E, Sec24 |