Decision Memo Completed

Catherine Creek Bank Stabilization / 7785 Road Prism Repair

Wallowa-Whitman National Forest Union, Oregon Wallowa-Whitman National Forest All Units

Repair a section of streambank from an uprooted dead tree adjacent to National Forest System Road 7785 to prevent further erosion.

Location

National Forest Road 7785 mile 2.8

Project timeline

1
Scoping Start
07/16/2024
2
Decision
09/2024 (Estimated)
3
Implementation
07/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Catherine Creek Bank Stabilization / 7785 Road Prism RepairDecision Signed Date: 09/13/2024
ForestsWallowa-Whitman National Forest
DistrictsLa Grande Ranger District
Legal Land DescriptionNot Applicable
Road management