Salvage approximately 17 acres of wind throw timber downed during winter storms. The proposal would salvage about 200 mbf of saw logs and reduce fuel buildup. Trees with roots attached would be used as fish habitat.
Location
Upper McKenzie River Watershed, east of Trail Bridge Reservoir along Forest Road 2600612.
Project timeline
1
Scoping Start
09/10/2007
2
Comment Period
12/05/2007
3
Decision
01/2008 (Estimated)
4
Implementation
03/2008 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Salvage); Watershed Improvements |
| Trail Bridge Blowdown Salvage Project | Decision Signed Date: 01/10/2008 Legal Notice Date: 01/15/2008 |
| Forests | Willamette National Forest |
| Districts | McKenzie River Ranger District |